Project Details
Search |
All Active Projects
-
File Number
-
ASB2625
-
Project Name
-
Rocky Top Site Development Plan
-
Parcels
-
8309200011
8309200011
-
Applicant
-
G&D
Nicholas Jokerst ( njokerst@allterraineng.com )
(530) 391-7635
Nicholas Jokerst ( njokerst@allterraineng.com )
(530) 391-7635
-
File Prefix
-
ASB - As Builts
-
Year
-
2026
-
Project Manager
-
Stormwater Mikayla Hartford
-
Status
-
Active
-
Created
-
9/15/2026 1:12:12 PM
Review Documents (4)
|
Link
|
Document
|
Date
|
|
View
|
Engineering Record Drawings (As-Builts)
|
10/7/2026 8:37:07 AM
|
|
View
|
PCM Certification Letter and Revised MHFD Calcs (ASB)
|
10/7/2026 8:37:08 AM
|
|
View
|
PCM Contact form
|
10/7/2026 8:37:09 AM
|
|
View
|
Spec Sheet and Receipt for grass seed
|
9/16/2026 11:33:38 AM
|
Events (16)
|
Date
|
Comment
|
|
10/7/2026 2:14:05 PM
|
Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Zachary Jannusch on behalf of EPC DPW Stormwater
|
|
10/7/2026 2:14:04 PM
|
Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Mikayla Hartford on behalf of EPC DPW Stormwater
|
|
10/7/2026 2:14:03 PM
|
Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Glenn Reese on behalf of EPC DPW Stormwater
|
|
10/7/2026 2:14:02 PM
|
Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Erica Rylander on behalf of EPC DPW Stormwater
|
|
10/7/2026 2:14:01 PM
|
Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Christina Prete on behalf of EPC DPW Stormwater
|
|
10/7/2026 2:14:00 PM
|
Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
|
10/7/2026 2:13:59 PM
|
Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
|
10/7/2026 2:13:58 PM
|
Request for Review Comments email sent for Project Rocky Top Site Development Plan for review by on behalf of EPC DPW Asset Management
|
|
10/7/2026 12:48:33 PM
|
Submission Triaged
|
|
10/7/2026 8:37:40 AM
|
Submission received from Applicant
|
|
9/29/2026 7:29:59 AM
|
Project Manager Assigned: Stormwater Mikayla Hartford
|
|
9/15/2026 1:14:48 PM
|
Submission request sent to Applicant
|
|
9/15/2026 1:12:15 PM
|
No Fees
|
|
9/15/2026 1:12:15 PM
|
File # Assigned: ASB2625
|
|
9/15/2026 1:12:15 PM
|
Project Manager Assigned: Stormwater Glenn Reese
|
|
9/15/2026 1:12:15 PM
|
Project Created. Parent Project: Rocky Top Site Development Plan (PPR2140)
|