9/11/2026 9:45:51 AM
|
Project Closed
|
|
9/11/2026 9:45:51 AM
|
Project Approved: 9/11/2026
|
|
9/11/2026 9:45:51 AM
|
Request for Approval returned by PCD Project Manager
|
|
9/11/2026 9:45:19 AM
|
Request for Approval sent for Project 13132 CRESCENT CREEK DR for review by Justin Kilgore on behalf of PCD Project Manager
|
|
9/11/2026 9:43:41 AM
|
Fees will be collected by Building Department
|
|
9/11/2026 9:43:41 AM
|
File # Assigned: ADD26554
|
|
9/11/2026 9:43:40 AM
|
Project Manager Assigned: Tim Chambers
|
|
9/11/2026 9:43:40 AM
|
Project Created
|