9/1/2026 7:46:21 AM
|
Project Closed
|
|
9/1/2026 7:46:21 AM
|
Project Approved: 9/1/2026
|
|
8/19/2026 9:33:31 AM
|
Request for Review Comments returned by EPC Parks Department
|
|
8/18/2026 1:59:48 PM
|
Meeting scheduled: 8/26/2026 11:00:00 AM
|
|
8/11/2026 12:50:49 PM
|
Project Manager Assigned: Joe Letke
|
|
8/5/2026 11:28:07 AM
|
Project Manager Assigned: Ryan Howser
|
|
8/4/2026 5:50:20 PM
|
Request for Assignment sent to EPC Fire and Wildfire Program Manager
|
|
8/4/2026 5:50:14 PM
|
Request for Assignment email sent for Project Leach - Outbuilding for review by General Email on behalf of Colorado Springs Public Works
|
|
8/4/2026 5:50:12 PM
|
Request for Assignment sent to Colorado Springs Public Works
|
|
8/4/2026 5:50:08 PM
|
Request for Assignment email sent for Project Leach - Outbuilding for review by Christina Prete on behalf of EPC DPW Stormwater
|
|
8/4/2026 5:50:07 PM
|
Request for Assignment sent to EPC DPW Stormwater
|
|
8/4/2026 5:50:06 PM
|
Request for Assignment email sent for Project Leach - Outbuilding for review by Catherine McGarvy on behalf of EPC Health Department
|
|
8/4/2026 5:50:04 PM
|
Request for Assignment sent to EPC Health Department
|
|
8/4/2026 5:50:03 PM
|
Request for Assignment email sent for Project Leach - Outbuilding for review by Drew Foxx on behalf of Colorado Springs Planning & Community Development
|
|
8/4/2026 5:50:00 PM
|
Request for Assignment sent to Colorado Springs Planning & Community Development
|
|
8/4/2026 5:49:59 PM
|
Request for Assignment email sent for Project Leach - Outbuilding for review by Justin Kilgore on behalf of PCD Project Manager
|
|
8/4/2026 5:49:58 PM
|
Request for Assignment sent to PCD Project Manager
|
|
8/4/2026 5:49:57 PM
|
Request for Assignment email sent for Project Leach - Outbuilding for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
|
8/4/2026 5:49:56 PM
|
Request for Assignment sent to EPC DPW Development Services - Engineering
|
|
8/4/2026 5:49:50 PM
|
Fees paid: 8/4/2026 (Receipt: 1012435)
|
|
8/4/2026 8:40:58 AM
|
Payment Request sent: 8/4/2026
|
|
8/4/2026 8:40:56 AM
|
EA Assigned: EA2699
|
|
8/4/2026 8:40:55 AM
|
Project Created
|
|
8/4/2026 8:40:53 AM
|
Application Triaged/Accepted
|
|
8/3/2026 1:48:56 PM
|
Application submitted
|