8/17/2026 1:52:09 PM
|
Project Closed
|
|
8/17/2026 1:52:09 PM
|
Project Approved: 8/17/2026
|
|
8/17/2026 1:49:35 PM
|
Project Ready for Approval requests. Review Comment period is complete.
|
|
8/17/2026 1:49:14 PM
|
Request for Review Comments returned by PCD Project Manager
|
|
8/17/2026 7:04:41 AM
|
Request for Review Comments email sent for Project 11712 FLAP JACK LN - Accessory Use Agreement for review by Justin Kilgore on behalf of PCD Project Manager
|
|
8/17/2026 7:04:28 AM
|
Submission Triaged
|
|
8/14/2026 8:33:30 AM
|
Submission received from Applicant
|
|
7/29/2026 11:45:47 AM
|
Submission request sent to Applicant
|
|
7/29/2026 11:45:35 AM
|
Request for Review Comments returned by PCD Project Manager
|
|
7/29/2026 11:19:26 AM
|
Project Manager Assigned: Kari Parsons
|
|
7/27/2026 5:16:31 PM
|
Request for Review Comments email sent for Project 11712 FLAP JACK LN - Accessory Use Agreement for review by Justin Kilgore on behalf of PCD Project Manager
|
|
7/27/2026 5:14:00 PM
|
Submission request canceled
|
|
7/27/2026 3:18:16 PM
|
Fees paid: 7/27/2026 (Receipt: 1012384)
|
|
7/27/2026 11:38:12 AM
|
File # Assigned: AUA262
|
|
7/20/2026 10:03:26 AM
|
Submission request sent to Applicant
|
|
7/20/2026 10:03:03 AM
|
Submission request canceled
|
|
7/7/2026 4:21:52 PM
|
Submission request sent to Applicant
|
|
7/7/2026 2:32:12 PM
|
Submission request sent to Applicant
|
|
7/7/2026 2:31:24 PM
|
Project Manager Assigned: Lacey Dean
|
|
7/7/2026 2:31:24 PM
|
Project Created
|