8/5/2026 6:30:25 AM
|
Submission request sent to Applicant
|
|
8/5/2026 6:28:27 AM
|
Request for Review Comments returned by EPC DPW Stormwater
|
|
7/27/2026 12:01:50 PM
|
Request for Review Comments email sent for Project High Country Crane New Office/Warehouse for review by Zachary Jannusch on behalf of EPC DPW Stormwater
|
|
7/27/2026 12:01:49 PM
|
Request for Review Comments email sent for Project High Country Crane New Office/Warehouse for review by Mikayla Hartford on behalf of EPC DPW Stormwater
|
|
7/27/2026 12:01:48 PM
|
Request for Review Comments email sent for Project High Country Crane New Office/Warehouse for review by Glenn Reese on behalf of EPC DPW Stormwater
|
|
7/27/2026 12:01:47 PM
|
Request for Review Comments email sent for Project High Country Crane New Office/Warehouse for review by Erica Rylander on behalf of EPC DPW Stormwater
|
|
7/27/2026 12:01:46 PM
|
Request for Review Comments email sent for Project High Country Crane New Office/Warehouse for review by Christina Prete on behalf of EPC DPW Stormwater
|
|
7/27/2026 12:01:24 PM
|
Submission Triaged
|
|
7/24/2026 4:25:13 PM
|
Submission received from Applicant
|
|
7/1/2026 10:37:37 AM
|
Submission request sent to Applicant
|
|
7/1/2026 10:23:21 AM
|
Request for Review Comments returned by EPC DPW Stormwater
|
|
6/15/2026 7:01:34 AM
|
Request for Review Comments email sent for Project High Country Crane New Office/Warehouse for review by Zachary Jannusch on behalf of EPC DPW Stormwater
|
|
6/15/2026 7:01:33 AM
|
Request for Review Comments email sent for Project High Country Crane New Office/Warehouse for review by Mikayla Hartford on behalf of EPC DPW Stormwater
|
|
6/15/2026 7:01:33 AM
|
Request for Review Comments email sent for Project High Country Crane New Office/Warehouse for review by Glenn Reese on behalf of EPC DPW Stormwater
|
|
6/15/2026 7:01:32 AM
|
Request for Review Comments email sent for Project High Country Crane New Office/Warehouse for review by Erica Rylander on behalf of EPC DPW Stormwater
|
|
6/15/2026 7:01:31 AM
|
Request for Review Comments email sent for Project High Country Crane New Office/Warehouse for review by Christina Prete on behalf of EPC DPW Stormwater
|
|
6/15/2026 7:00:52 AM
|
Submission Triaged
|
|
6/12/2026 3:20:45 PM
|
Submission received from Applicant
|
|
6/12/2026 2:51:23 PM
|
Submission request sent to Applicant
|
|
6/12/2026 11:55:49 AM
|
Submission request sent to Applicant
|
|
6/12/2026 11:55:29 AM
|
Submission Triaged
|
|
6/11/2026 5:15:58 PM
|
Submission received from Applicant
|
|
4/14/2026 4:19:45 PM
|
Submission request sent to Applicant
|
|
4/14/2026 4:18:37 PM
|
No Fees
|
|
4/14/2026 4:18:37 PM
|
File # Assigned: ASB268
|
|
4/14/2026 4:18:37 PM
|
Project Manager Assigned: Stormwater Glenn Reese
|
|
4/14/2026 4:18:37 PM
|
Project Created. Parent Project: High Country Crane New Office/Warehouse (PPR2417)
|