Project Details

Search


File Number
TWR264
Project Name
14540 N Meridian Rd - T-Mobile Addition of Ground Equipment
Description
Improvements include installation of a Generac 48kW RD048 diesel generator, a 240-gallon diesel fuel tank, a 4’ x 9’ reinforced concrete equipment pad, and an automatic transfer switch housed within a weatherproof cabinet. The project also includes installation of electrical and communication conduits between the generator and transfer switch. Additional components include a 10 lb ABC fire extinguisher within a weatherproof cabinet, two 20-amp single-pole breakers (one for the generator block heater and one for the battery charger), and a remote emergency stop button.
Parcels
5136401040 5136401040
Applicant
JW Tower & Telecom Consulting
John Wabiszczewicz II ( jw@jwttc.com )
(203) 982-5373
John Wabiszczewicz II ( jw@jwttc.com )
(203) 982-5373
File Prefix
TWR - Tower
Year
2026
Project Manager
Jen Uhler
Status
Closed
Created
2/19/2026 11:29:36 AM

View: Review Comments


Approved Documents (1)

Link Document
View Site Development Plan


Review Documents (6)

Link Document Date
View Application/Petition Form 2/25/2026 2:33:16 PM
View Elevation Plans 3/13/2026 1:10:08 PM
View Letter of Intent 2/25/2026 2:33:18 PM
View Lease Agreement 2/25/2026 2:33:19 PM
View Site Plan Drawing 3/19/2026 10:39:36 AM
View EFR Letter 3/13/2026 1:10:09 PM



Events (37)

Date Comment
3/19/2026 12:00:24 PM Project Closed
3/19/2026 12:00:24 PM Project Approved: 3/19/2026
3/19/2026 11:59:51 AM Project Ready for Approval requests. Review Comment period is complete.
3/19/2026 11:50:06 AM Submission Triaged
3/19/2026 10:40:20 AM Submission received from Applicant
3/18/2026 3:34:42 PM Submission request sent to Applicant
3/18/2026 3:32:22 PM Submission Triaged
3/18/2026 2:17:25 PM Submission received from Applicant
3/13/2026 2:07:00 PM Submission request sent to Applicant
3/13/2026 1:42:42 PM Submission Triaged
3/13/2026 1:10:27 PM Submission received from Applicant
3/13/2026 11:49:36 AM Submission request sent to Applicant
3/13/2026 11:47:05 AM Submission request canceled
3/12/2026 2:01:14 PM Submission request sent to Applicant
3/12/2026 1:58:44 PM Request for Review Comments returned by PCD Project Manager
3/10/2026 5:03:58 PM Request for Review Comments returned by EPC DPW Stormwater
3/9/2026 10:51:08 AM Request for Review Comments returned by Pikes Peak Regional Building Department
3/6/2026 11:10:56 AM Request for Review Comments returned by EPC DPW Development Services - Engineering
3/3/2026 8:16:25 AM Project Manager Assigned: Jen Uhler
2/26/2026 10:33:19 AM Request for Review Comments email sent for Project 14540 N Meridian Rd - T-Mobile Addition of Ground Equipment for review by on behalf of Pikes Peak Regional Building Department
2/26/2026 10:33:18 AM Request for Review Comments email sent for Project 14540 N Meridian Rd - T-Mobile Addition of Ground Equipment for review by Zachary Jannusch on behalf of EPC DPW Stormwater
2/26/2026 10:33:17 AM Request for Review Comments email sent for Project 14540 N Meridian Rd - T-Mobile Addition of Ground Equipment for review by Mikayla Hartford on behalf of EPC DPW Stormwater
2/26/2026 10:33:16 AM Request for Review Comments email sent for Project 14540 N Meridian Rd - T-Mobile Addition of Ground Equipment for review by Glenn Reese on behalf of EPC DPW Stormwater
2/26/2026 10:33:15 AM Request for Review Comments email sent for Project 14540 N Meridian Rd - T-Mobile Addition of Ground Equipment for review by Christina Prete on behalf of EPC DPW Stormwater
2/26/2026 10:33:14 AM Request for Review Comments email sent for Project 14540 N Meridian Rd - T-Mobile Addition of Ground Equipment for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
2/26/2026 10:33:13 AM Request for Review Comments email sent for Project 14540 N Meridian Rd - T-Mobile Addition of Ground Equipment for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
2/26/2026 10:33:12 AM Request for Review Comments email sent for Project 14540 N Meridian Rd - T-Mobile Addition of Ground Equipment for review by Justin Kilgore on behalf of PCD Project Manager
2/26/2026 10:26:22 AM Submission request canceled
2/26/2026 10:25:57 AM Submission request sent to Applicant
2/26/2026 8:54:31 AM Fees paid: 2/26/2026 (Receipt: 1011721)
2/26/2026 7:50:44 AM Payment Request sent: 2/26/2026
2/26/2026 7:50:43 AM File # Assigned: TWR264
2/26/2026 7:50:41 AM Submission Triaged
2/25/2026 2:33:39 PM Submission received from Applicant
2/19/2026 11:54:45 AM Submission request sent to Applicant
2/19/2026 11:29:38 AM Project Manager Assigned: Lisa Elgin
2/19/2026 11:29:38 AM Project Created