Project Details

Search | All Active Projects


File Number
CDR2513
Project Name
MVEA - Vollmer Sub West Circuit
Description
The project is for the installation of 15KV underground electric facilities along Oto Road and Brule Road, Falcon, CO. Underground facilities shall be installed in 6” diameter conduit.
Applicant
MVEA
permitting@mvea.coop ( permitting@mvea.coop ) permitting@mvea.coop ( permitting@mvea.coop )
File Prefix
CDR - Construction Drawing Review
Year
2025
Project Manager
Stormwater Glenn Reese
Status
Active
Created
11/5/2025 4:29:01 PM

View: Review Comments



Review Documents (10)

Link Document Date
View Legal Description (MS WORD Version required) 1/19/2026 4:46:51 PM
View Letter of Intent 1/19/2026 4:46:51 PM
View Erosion and Stormwater Quality Control Permit (ESQCP) 1/19/2026 4:46:51 PM
View Financial Assurance Estimate (FAE) Form 1/19/2026 4:46:49 PM
View Grading & Erosion Control (GEC) Checklist 1/19/2026 4:46:53 PM
View Grading & Erosion Control (GEC) Plan 1/19/2026 4:46:50 PM
View PCM Applicability Form 1/19/2026 4:46:54 PM
View Storm Water Management Plan (SWMP) 1/19/2026 4:46:52 PM
View Storm Water Management Plan (SWMP) Checklist 1/19/2026 4:46:53 PM
View Drainage Letter 1/29/2026 11:58:01 AM



Events (35)

Date Comment
2/9/2026 12:20:11 PM Request for Review Comments returned by Meridian Ranch/Meridian Service Metro Dist.
2/6/2026 2:03:24 PM Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
2/5/2026 1:24:31 PM Request for Review Comments email sent for Project MVEA - Vollmer Sub West Circuit for review by Rebecca Hardekopf on behalf of Woodmen Road Metro
2/5/2026 1:24:29 PM Request for Review Comments email sent for Project MVEA - Vollmer Sub West Circuit for review by Tabitha Barile on behalf of Sterling Ranch Metropolitan District 1-3
2/5/2026 1:24:28 PM Request for Review Comments email sent for Project MVEA - Vollmer Sub West Circuit for review by Jeff Munger on behalf of Cherokee Metro Dist
2/5/2026 1:24:27 PM Request for Review Comments email sent for Project MVEA - Vollmer Sub West Circuit for review by Brandon Zembles on behalf of Cherokee Metro Dist
2/5/2026 1:24:26 PM Request for Review Comments email sent for Project MVEA - Vollmer Sub West Circuit for review by Daniel Delgado on behalf of US Army Corps of Engineers
2/5/2026 1:24:25 PM Request for Review Comments email sent for Project MVEA - Vollmer Sub West Circuit for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
2/5/2026 1:24:24 PM Request for Review Comments email sent for Project MVEA - Vollmer Sub West Circuit for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
2/5/2026 1:24:23 PM Request for Review Comments email sent for Project MVEA - Vollmer Sub West Circuit for review by Kimberly Blanchard on behalf of Colorado Department of Transportation - Pueblo Office
2/5/2026 1:24:22 PM Request for Review Comments email sent for Project MVEA - Vollmer Sub West Circuit for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
2/5/2026 1:24:21 PM Request for Review Comments email sent for Project MVEA - Vollmer Sub West Circuit for review by Tom Kerby on behalf of Meridian Ranch/Meridian Service Metro Dist.
2/5/2026 1:24:20 PM Request for Review Comments email sent for Project MVEA - Vollmer Sub West Circuit for review by Linda Warren on behalf of Meridian Ranch/Meridian Service Metro Dist.
2/5/2026 1:24:19 PM Request for Review Comments email sent for Project MVEA - Vollmer Sub West Circuit for review by Jennette Coe on behalf of Meridian Ranch/Meridian Service Metro Dist.
2/5/2026 1:24:18 PM Request for Review Comments email sent for Project MVEA - Vollmer Sub West Circuit for review by on behalf of EPC Public Works, County Engineer
2/5/2026 1:24:17 PM Request for Review Comments email sent for Project MVEA - Vollmer Sub West Circuit for review by on behalf of EPC Public Works, County Engineer
2/5/2026 1:24:16 PM Request for Review Comments email sent for Project MVEA - Vollmer Sub West Circuit for review by Zachary Jannusch on behalf of EPC DPW Stormwater
2/5/2026 1:24:15 PM Request for Review Comments email sent for Project MVEA - Vollmer Sub West Circuit for review by Mikayla Hartford on behalf of EPC DPW Stormwater
2/5/2026 1:24:14 PM Request for Review Comments email sent for Project MVEA - Vollmer Sub West Circuit for review by Glenn Reese on behalf of EPC DPW Stormwater
2/5/2026 1:24:13 PM Request for Review Comments email sent for Project MVEA - Vollmer Sub West Circuit for review by Christina Prete on behalf of EPC DPW Stormwater
2/5/2026 1:24:12 PM Request for Review Comments email sent for Project MVEA - Vollmer Sub West Circuit for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
2/5/2026 1:24:11 PM Request for Review Comments email sent for Project MVEA - Vollmer Sub West Circuit for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
2/3/2026 10:23:14 AM Fees paid: 2/3/2026 (Receipt: 1011630)
1/29/2026 2:47:30 PM Payment Request sent: 1/29/2026
1/29/2026 2:47:27 PM Submission Triaged
1/29/2026 11:58:15 AM Submission received from Applicant
1/29/2026 8:52:56 AM Submission request sent to Applicant
1/29/2026 8:51:52 AM Submission Triaged
1/28/2026 11:02:06 AM Submission received from Applicant
1/28/2026 10:59:59 AM Submission request sent to Applicant
11/5/2025 4:38:55 PM Submission request sent to Applicant
11/5/2025 4:37:54 PM Submission request sent to Applicant
11/5/2025 4:29:11 PM File # Assigned: CDR2513
11/5/2025 4:29:03 PM Project Manager Assigned: Stormwater Glenn Reese
11/5/2025 4:29:03 PM Project Created