Project Details

Search | All Active Projects


File Number
PPR2536
Project Name
Sterling Ranch East Community Center Parkland Area Phase 1
Description
Phase 1 of the planned community center: outdoor mini stage, pickleball courts, parks and trails, all planned for with the Preliminary Plan.
Parcels
5233410022 5233410022
Applicant
N.E.S. Inc.
Andrea Barlow ( abarlow@nescolorado.com )
(719) 471-0073
Andrea Barlow ( abarlow@nescolorado.com )
(719) 471-0073
File Prefix
PPR - Plot Plan Review
Year
2025
Project Manager
Kari Parsons
Status
Active
Created
8/19/2025 3:44:03 PM

View: Review Comments



Review Documents (17)

Link Document Date
View Application/Petition Form 11/4/2025 9:50:09 AM
View Elevation Plans 11/5/2025 8:39:42 AM
View Landscape Plan drawings 10/31/2025 1:02:11 PM
View Letter of Intent 11/4/2025 9:50:10 AM
View Lighting Plan 11/4/2025 9:50:11 AM
View Road Impact Fee Acknowledgement 10/31/2025 2:06:06 PM
View Site Development Plan 10/31/2025 12:35:26 PM
View Erosion and Stormwater Quality Control Permit (ESQCP) 10/10/2025 4:48:20 PM
View Financial Assurance Estimate (FAE) Form 10/31/2025 1:52:24 PM
View Grading & Erosion Control (GEC) Checklist 10/7/2025 11:14:36 AM
View Grading & Erosion Control (GEC) Plan 10/31/2025 1:01:01 PM
View PCM Applicability Form 10/7/2025 11:07:42 AM
View Storm Water Management Plan (SWMP) 10/10/2025 4:48:21 PM
View Storm Water Management Plan (SWMP) Checklist 10/10/2025 4:48:22 PM
View Sign Plan 11/4/2025 9:50:11 AM
View Drainage Report - Final 10/31/2025 12:35:25 PM
View Traffic Memo 11/5/2025 8:39:43 AM



Events (41)

Date Comment
11/19/2025 8:09:12 AM Request for Review Comments returned by 911 Authority - El Paso/Teller County
11/18/2025 7:09:09 AM Request for Review Comments returned by Academy SD 20 Building Fund
11/13/2025 8:41:36 AM Request for Review Comments returned by Pikes Peak Regional Building Department
11/13/2025 7:52:31 AM Request for Review Comments returned by RBD Floodplain
11/12/2025 4:23:31 PM Request for Review Comments email sent for Project Sterling Ranch East Community Center Parkland Area Phase 1 for review by Keith Curtis on behalf of RBD Floodplain
11/12/2025 4:20:48 PM Request for Review Comments email sent for Project Sterling Ranch East Community Center Parkland Area Phase 1 for review by Roland Peterson on behalf of EPC Fire and Wildfire Program Manager
11/12/2025 4:18:27 PM Request for Review Comments email sent for Project Sterling Ranch East Community Center Parkland Area Phase 1 for review by Tabitha Barile on behalf of Sterling Ranch Metropolitan District 1-3
11/12/2025 4:18:26 PM Request for Review Comments email sent for Project Sterling Ranch East Community Center Parkland Area Phase 1 for review by Roger Austin on behalf of Mountain Metro Transit (City of COS)
11/12/2025 4:18:25 PM Request for Review Comments email sent for Project Sterling Ranch East Community Center Parkland Area Phase 1 for review by Steve White on behalf of Mountain Metro Transit (City of COS)
11/12/2025 4:18:23 PM Request for Review Comments email sent for Project Sterling Ranch East Community Center Parkland Area Phase 1 for review by Bob Swatek on behalf of Black Hills Energy-Aquila
11/12/2025 4:18:22 PM Request for Review Comments email sent for Project Sterling Ranch East Community Center Parkland Area Phase 1 for review by Trish Riber on behalf of Black Hills Energy-Aquila
11/12/2025 4:18:21 PM Request for Review Comments email sent for Project Sterling Ranch East Community Center Parkland Area Phase 1 for review by Marcus Henderson on behalf of Black Hills Energy-Aquila
11/12/2025 4:18:20 PM Request for Review Comments email sent for Project Sterling Ranch East Community Center Parkland Area Phase 1 for review by Adam Magoon on behalf of Black Hills Energy-Aquila
11/12/2025 4:18:19 PM Request for Review Comments email sent for Project Sterling Ranch East Community Center Parkland Area Phase 1 for review by on behalf of Black Forest Fire Protection District
11/12/2025 4:18:18 PM Request for Review Comments email sent for Project Sterling Ranch East Community Center Parkland Area Phase 1 for review by Fielding Lucas on behalf of Black Forest Fire Protection District
11/12/2025 4:18:17 PM Request for Review Comments email sent for Project Sterling Ranch East Community Center Parkland Area Phase 1 for review by Rachel Dunn on behalf of Black Forest Fire Protection District
11/12/2025 4:18:16 PM Request for Review Comments email sent for Project Sterling Ranch East Community Center Parkland Area Phase 1 for review by Michael Alvarado on behalf of Black Forest Fire Protection District
11/12/2025 4:18:15 PM Request for Review Comments email sent for Project Sterling Ranch East Community Center Parkland Area Phase 1 for review by Chad Herdt on behalf of Black Forest Fire Protection District
11/12/2025 4:18:14 PM Request for Review Comments email sent for Project Sterling Ranch East Community Center Parkland Area Phase 1 for review by Donald Smith on behalf of Academy SD 20 Building Fund
11/12/2025 4:18:13 PM Request for Review Comments email sent for Project Sterling Ranch East Community Center Parkland Area Phase 1 for review by Becky Allan on behalf of Academy SD 20 Building Fund
11/12/2025 4:18:12 PM Request for Review Comments email sent for Project Sterling Ranch East Community Center Parkland Area Phase 1 for review by Tom Gregory on behalf of Academy SD 20 Building Fund
11/12/2025 4:18:11 PM Request for Review Comments email sent for Project Sterling Ranch East Community Center Parkland Area Phase 1 for review by on behalf of Pikes Peak Regional Building Department
11/12/2025 4:18:09 PM Request for Review Comments email sent for Project Sterling Ranch East Community Center Parkland Area Phase 1 for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
11/12/2025 4:18:08 PM Request for Review Comments email sent for Project Sterling Ranch East Community Center Parkland Area Phase 1 for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
11/12/2025 4:18:07 PM Request for Review Comments email sent for Project Sterling Ranch East Community Center Parkland Area Phase 1 for review by General Email on behalf of Mountain View Electric Association, Inc.
11/12/2025 4:18:06 PM Request for Review Comments email sent for Project Sterling Ranch East Community Center Parkland Area Phase 1 for review by on behalf of EPC Parks Department
11/12/2025 4:18:05 PM Request for Review Comments email sent for Project Sterling Ranch East Community Center Parkland Area Phase 1 for review by Christina Prete on behalf of EPC DPW Stormwater
11/12/2025 4:18:04 PM Request for Review Comments email sent for Project Sterling Ranch East Community Center Parkland Area Phase 1 for review by Zachary Jannusch on behalf of EPC DPW Stormwater
11/12/2025 4:18:03 PM Request for Review Comments email sent for Project Sterling Ranch East Community Center Parkland Area Phase 1 for review by Mikayla Hartford on behalf of EPC DPW Stormwater
11/12/2025 4:18:02 PM Request for Review Comments email sent for Project Sterling Ranch East Community Center Parkland Area Phase 1 for review by Glenn Reese on behalf of EPC DPW Stormwater
11/12/2025 4:18:01 PM Request for Review Comments email sent for Project Sterling Ranch East Community Center Parkland Area Phase 1 for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
11/12/2025 4:18:00 PM Request for Review Comments email sent for Project Sterling Ranch East Community Center Parkland Area Phase 1 for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
11/12/2025 4:17:59 PM Request for Review Comments email sent for Project Sterling Ranch East Community Center Parkland Area Phase 1 for review by Justin Kilgore on behalf of PCD Project Manager
11/6/2025 8:54:58 AM Fees paid: 11/6/2025 (Receipt: 1011314)
11/5/2025 1:53:09 PM Payment Request sent: 11/5/2025
11/5/2025 1:53:09 PM File # Assigned: PPR2536
11/5/2025 1:53:04 PM Submission Triaged
11/5/2025 8:39:51 AM Submission received from Applicant
8/19/2025 3:47:58 PM Submission request sent to Applicant
8/19/2025 3:44:09 PM Project Manager Assigned: Kari Parsons
8/19/2025 3:44:09 PM Project Created