| 9/24/2025 3:46:19 PM | Request for Review Comments returned by PCD Project Manager | 
                
                    | 9/24/2025 2:31:08 PM | Request for Review Comments returned by EPC DPW Development Services - Engineering | 
                
                    | 9/22/2025 11:04:20 AM | Request for Review Comments returned by EPC DPW Stormwater | 
                
                    | 9/10/2025 11:12:58 AM | Request for Review Comments email sent for Project Black Forest Road Hydrant #17 for review by Zachary Jannusch on behalf of EPC DPW Stormwater | 
                
                    | 9/10/2025 11:12:55 AM | Request for Review Comments email sent for Project Black Forest Road Hydrant #17 for review by Mikayla Hartford on behalf of EPC DPW Stormwater | 
                
                    | 9/10/2025 11:12:54 AM | Request for Review Comments email sent for Project Black Forest Road Hydrant #17 for review by Glenn Reese on behalf of EPC DPW Stormwater | 
                
                    | 9/10/2025 11:12:53 AM | Request for Review Comments email sent for Project Black Forest Road Hydrant #17 for review by Christina Prete on behalf of EPC DPW Stormwater | 
                
                    | 9/10/2025 11:12:51 AM | Request for Review Comments email sent for Project Black Forest Road Hydrant #17 for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering | 
                
                    | 9/10/2025 11:12:50 AM | Request for Review Comments email sent for Project Black Forest Road Hydrant #17 for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering | 
                
                    | 9/10/2025 11:12:47 AM | Request for Review Comments email sent for Project Black Forest Road Hydrant #17 for review by Justin Kilgore on behalf of PCD Project Manager | 
                
                    | 9/10/2025 11:09:57 AM | Request for Review Comments sent for Project Black Forest Road Hydrant #17 for review by Justin Kilgore on behalf of PCD Project Manager | 
                
                    | 9/9/2025 4:06:33 PM | Submission Triaged | 
                
                    | 9/9/2025 3:51:57 PM | Submission received from Applicant | 
                
                    | 8/25/2025 2:30:39 PM | Submission request sent to Applicant | 
                
                    | 8/25/2025 2:27:47 PM | Request for Review Comments returned by PCD Project Manager | 
                
                    | 8/25/2025 2:27:01 PM | Request for Review Comments returned by EPC DPW Development Services - Engineering | 
                
                    | 8/25/2025 1:40:46 PM | Request for Review Comments returned by EPC DPW Stormwater | 
                
                    | 8/11/2025 2:38:56 PM | Request for Review Comments email sent for Project Black Forest Road Hydrant #17 for review by Zachary Jannusch on behalf of EPC DPW Stormwater | 
                
                    | 8/11/2025 2:38:55 PM | Request for Review Comments email sent for Project Black Forest Road Hydrant #17 for review by Mikayla Hartford on behalf of EPC DPW Stormwater | 
                
                    | 8/11/2025 2:38:54 PM | Request for Review Comments email sent for Project Black Forest Road Hydrant #17 for review by Glenn Reese on behalf of EPC DPW Stormwater | 
                
                    | 8/11/2025 2:38:53 PM | Request for Review Comments email sent for Project Black Forest Road Hydrant #17 for review by Christina Prete on behalf of EPC DPW Stormwater | 
                
                    | 8/11/2025 2:38:52 PM | Request for Review Comments email sent for Project Black Forest Road Hydrant #17 for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering | 
                
                    | 8/11/2025 2:38:51 PM | Request for Review Comments email sent for Project Black Forest Road Hydrant #17 for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering | 
                
                    | 8/11/2025 2:38:50 PM | Request for Review Comments email sent for Project Black Forest Road Hydrant #17 for review by Justin Kilgore on behalf of PCD Project Manager | 
                
                    | 8/8/2025 10:57:55 AM | Fees paid: 8/8/2025 (Receipt: 1010895) | 
                
                    | 8/8/2025 10:33:44 AM | Payment Request sent: 8/8/2025 | 
                
                    | 8/8/2025 10:33:44 AM | File # Assigned: CDR257 | 
                
                    | 8/8/2025 10:33:37 AM | Submission Triaged | 
                
                    | 8/8/2025 9:32:20 AM | Submission received from Applicant | 
                
                    | 7/31/2025 8:39:13 AM | Project Manager Assigned: Bret Dilts | 
                
                    | 7/18/2025 2:38:47 PM | Submission request sent to Applicant | 
                
                    | 7/18/2025 2:34:58 PM | Project Manager Assigned: Engineering Manager | 
                
                    | 7/18/2025 2:34:58 PM | Project Created |