6/13/2025 8:23:47 AM
|
Project Closed
|
|
6/13/2025 8:23:47 AM
|
Project Approved: 6/13/2025
|
|
6/13/2025 8:23:43 AM
|
Request for Approval returned by PCD Project Manager
|
|
6/13/2025 8:22:57 AM
|
Request for Approval sent for Project 8906 BLUE FEATHER LOOP for review by Justin Kilgore on behalf of PCD Project Manager
|
|
6/13/2025 8:18:57 AM
|
Child BESQCP (drainage permit) project Approved (ESR25543)
|
|
6/12/2025 3:54:49 PM
|
Child Access Permit (driveway) project Approved (AP25595)
|
|
6/11/2025 2:47:13 PM
|
Fees will be collected by Building Department
|
|
6/11/2025 2:47:13 PM
|
File # Assigned: SFD25562
|
|
6/11/2025 2:47:12 PM
|
Project Manager Assigned: Petra Rangel
|
|
6/11/2025 2:47:12 PM
|
Project Created
|