8/25/2025 8:47:23 AM
|
Request for Review Comments email sent for Project Villages at Lorson Ranch for review by Jalal Saleh on behalf of EPC DPW Development Services - Engineering
|
8/25/2025 8:47:22 AM
|
Request for Review Comments email sent for Project Villages at Lorson Ranch for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
8/25/2025 8:47:21 AM
|
Request for Review Comments email sent for Project Villages at Lorson Ranch for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
8/25/2025 8:44:35 AM
|
Submission Triaged
|
8/21/2025 5:19:54 PM
|
Submission received from Applicant
|
8/20/2025 9:42:34 AM
|
Submission request sent to Applicant
|
8/15/2025 3:49:45 PM
|
Request for Review Comments returned by EPC DPW Development Services - Engineering
|
8/13/2025 9:55:39 AM
|
Request for Review Comments email sent for Project Villages at Lorson Ranch for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
8/13/2025 9:55:38 AM
|
Request for Review Comments email sent for Project Villages at Lorson Ranch for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
8/13/2025 9:53:17 AM
|
Submission Triaged
|
8/12/2025 4:08:16 PM
|
Submission received from Applicant
|
8/12/2025 3:59:50 PM
|
Submission request sent to Applicant
|
8/12/2025 3:59:28 PM
|
Submission Triaged
|
8/12/2025 12:25:00 PM
|
Submission received from Applicant
|
7/22/2025 2:29:23 PM
|
Submission request sent to Applicant
|
7/22/2025 11:00:01 AM
|
Request for Review Comments returned by EPC DPW Development Services - Engineering
|
7/16/2025 1:23:47 PM
|
Request for Review Comments sent for Project Villages at Lorson Ranch for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
7/16/2025 1:23:11 PM
|
Submission Triaged
|
7/10/2025 10:53:04 AM
|
Submission received from Applicant
|
5/6/2025 6:52:40 PM
|
Submission request sent to Applicant
|
5/6/2025 2:52:20 PM
|
Request for Review Comments returned by EPC DPW Development Services - Inspections
|
5/6/2025 2:40:31 PM
|
Request for Review Comments returned by EPC DPW Development Services - Engineering
|
4/29/2025 11:02:16 AM
|
Request for Review Comments email sent for Project Villages at Lorson Ranch for review by Brad Walters on behalf of EPC DPW Development Services - Inspections
|
4/29/2025 11:02:15 AM
|
Request for Review Comments email sent for Project Villages at Lorson Ranch for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
4/29/2025 11:02:14 AM
|
Request for Review Comments email sent for Project Villages at Lorson Ranch for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
4/29/2025 10:53:35 AM
|
Submission Triaged
|
4/28/2025 3:16:39 PM
|
Submission received from Applicant
|
4/24/2025 11:08:46 AM
|
File # Assigned: PAV257
|
4/23/2025 7:55:18 AM
|
Submission request sent to Applicant
|
4/23/2025 7:54:41 AM
|
No Fees
|
4/23/2025 7:54:41 AM
|
Project Manager Assigned: Charlene Durham
|
4/23/2025 7:54:41 AM
|
File # Assigned: PAV256
|
4/23/2025 7:54:41 AM
|
EA Assigned: EA2413
|
4/23/2025 7:54:41 AM
|
Project Created
|