6/4/2025 5:27:19 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
5/28/2025 4:09:42 PM
|
Submission request sent to Applicant
|
5/28/2025 4:05:10 PM
|
Request for Review Comments returned by PCD Project Manager
|
5/28/2025 9:20:39 AM
|
Request for Review Comments returned by EPC DPW Development Services - Engineering
|
5/28/2025 8:30:43 AM
|
Request for Review Comments email resent for Project Stealth Tower - 7600 Wayfarer Dr for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
5/27/2025 5:27:35 PM
|
Request for Review Comments returned by EPC DPW Stormwater
|
5/27/2025 9:38:23 AM
|
Request for Review Comments returned by Colorado Springs Airport Advisory Commission
|
5/21/2025 8:22:27 AM
|
Request for Review Comments returned by EPC DPW Development Services - Engineering
|
5/20/2025 8:59:01 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
5/16/2025 8:38:26 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
5/14/2025 1:01:19 PM
|
Request for Review Comments returned by Widefield SD 3
|
5/13/2025 4:59:40 PM
|
Request for Review Comments email sent for Project Stealth Tower - 7600 Wayfarer Dr for review by Justin Kilgore on behalf of PCD Project Manager
|
5/13/2025 4:57:40 PM
|
Request for Review Comments email sent for Project Stealth Tower - 7600 Wayfarer Dr for review by Travis Jones on behalf of Widefield Water & San
|
5/13/2025 4:57:39 PM
|
Request for Review Comments email sent for Project Stealth Tower - 7600 Wayfarer Dr for review by Rob Banister on behalf of Widefield Water & San
|
5/13/2025 4:57:37 PM
|
Request for Review Comments email sent for Project Stealth Tower - 7600 Wayfarer Dr for review by Travis Jones on behalf of Widefield Water & San
|
5/13/2025 4:57:36 PM
|
Request for Review Comments email sent for Project Stealth Tower - 7600 Wayfarer Dr for review by Dave Gish on behalf of Widefield SD 3
|
5/13/2025 4:57:35 PM
|
Request for Review Comments email sent for Project Stealth Tower - 7600 Wayfarer Dr for review by Garrett Markus on behalf of Southeastern Colorado Water Conservancy
|
5/13/2025 4:57:34 PM
|
Request for Review Comments email sent for Project Stealth Tower - 7600 Wayfarer Dr for review by General Email on behalf of Mountain View Electric Association, Inc.
|
5/13/2025 4:57:33 PM
|
Request for Review Comments email sent for Project Stealth Tower - 7600 Wayfarer Dr for review by John Sanders on behalf of Ft. Carson, Directorate of Public Works, Master Planning
|
5/13/2025 4:57:31 PM
|
Request for Review Comments email sent for Project Stealth Tower - 7600 Wayfarer Dr for review by Gary Steen on behalf of Fountain Mutual Irrigation Company
|
5/13/2025 4:57:30 PM
|
Request for Review Comments email sent for Project Stealth Tower - 7600 Wayfarer Dr for review by Kristy Martinez on behalf of Fountain
|
5/13/2025 4:57:29 PM
|
Request for Review Comments email sent for Project Stealth Tower - 7600 Wayfarer Dr for review by Brandy Williams on behalf of Fountain
|
5/13/2025 4:57:28 PM
|
Request for Review Comments email sent for Project Stealth Tower - 7600 Wayfarer Dr for review by Ben Sheets on behalf of Fountain
|
5/13/2025 4:57:27 PM
|
Request for Review Comments email sent for Project Stealth Tower - 7600 Wayfarer Dr for review by Chris Padilla on behalf of Colorado Springs Airport Advisory Commission
|
5/13/2025 4:57:26 PM
|
Request for Review Comments email sent for Project Stealth Tower - 7600 Wayfarer Dr for review by Santiago Tijerina on behalf of Black Hills Energy-Aquila
|
5/13/2025 4:57:25 PM
|
Request for Review Comments email sent for Project Stealth Tower - 7600 Wayfarer Dr for review by Marcus Henderson on behalf of Black Hills Energy-Aquila
|
5/13/2025 4:57:24 PM
|
Request for Review Comments email sent for Project Stealth Tower - 7600 Wayfarer Dr for review by Bob Swatek on behalf of Black Hills Energy-Aquila
|
5/13/2025 4:57:22 PM
|
Request for Review Comments email sent for Project Stealth Tower - 7600 Wayfarer Dr for review by Adam Magoon on behalf of Black Hills Energy-Aquila
|
5/13/2025 4:57:21 PM
|
Request for Review Comments email sent for Project Stealth Tower - 7600 Wayfarer Dr for review by on behalf of Pikes Peak Regional Building Department
|
5/13/2025 4:57:20 PM
|
Request for Review Comments email sent for Project Stealth Tower - 7600 Wayfarer Dr for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
5/13/2025 4:57:19 PM
|
Request for Review Comments email sent for Project Stealth Tower - 7600 Wayfarer Dr for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
|
5/13/2025 4:57:18 PM
|
Request for Review Comments email sent for Project Stealth Tower - 7600 Wayfarer Dr for review by Zachary Jannusch on behalf of EPC DPW Stormwater
|
5/13/2025 4:57:17 PM
|
Request for Review Comments email sent for Project Stealth Tower - 7600 Wayfarer Dr for review by Mikayla Hartford on behalf of EPC DPW Stormwater
|
5/13/2025 4:57:16 PM
|
Request for Review Comments email sent for Project Stealth Tower - 7600 Wayfarer Dr for review by Glenn Reese on behalf of EPC DPW Stormwater
|
5/13/2025 4:57:15 PM
|
Request for Review Comments email sent for Project Stealth Tower - 7600 Wayfarer Dr for review by Christina Prete on behalf of EPC DPW Stormwater
|
5/13/2025 4:57:14 PM
|
Request for Review Comments email sent for Project Stealth Tower - 7600 Wayfarer Dr for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
5/13/2025 4:57:13 PM
|
Request for Review Comments email sent for Project Stealth Tower - 7600 Wayfarer Dr for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
5/13/2025 4:57:12 PM
|
Request for Review Comments email sent for Project Stealth Tower - 7600 Wayfarer Dr for review by Michael Shannon on behalf of EPC Code Enforcement Inspections
|
5/13/2025 4:57:11 PM
|
Request for Review Comments email sent for Project Stealth Tower - 7600 Wayfarer Dr for review by Kurt Arnoldussen on behalf of EPC Code Enforcement Inspections
|
5/13/2025 2:09:05 PM
|
Fees paid: 5/13/2025 (Receipt: 1010520)
|
5/13/2025 1:42:00 PM
|
Payment Request sent: 5/13/2025
|
5/13/2025 1:42:00 PM
|
File # Assigned: TWR2514
|
5/13/2025 1:41:56 PM
|
Submission Triaged
|
5/13/2025 8:52:06 AM
|
Submission received from Applicant
|
5/12/2025 11:03:21 AM
|
Submission request sent to Applicant
|
5/12/2025 11:03:15 AM
|
Submission Triaged
|
5/8/2025 12:46:53 PM
|
Submission request sent to Applicant
|
5/8/2025 12:45:56 PM
|
Submission Triaged
|
5/8/2025 11:56:06 AM
|
Submission received from Applicant
|
4/8/2025 2:40:30 PM
|
Submission request sent to Applicant
|
4/8/2025 2:40:19 PM
|
Submission Triaged
|
4/1/2025 4:50:09 PM
|
Submission request sent to Applicant
|
4/1/2025 4:49:20 PM
|
Submission request sent to Applicant
|
4/1/2025 4:49:07 PM
|
Submission Triaged
|
3/31/2025 6:18:08 PM
|
Submission received from Applicant
|
3/24/2025 9:48:03 AM
|
Submission request sent to Applicant
|
3/14/2025 3:59:53 PM
|
Submission request sent to Applicant
|
3/14/2025 2:46:36 PM
|
Project Manager Assigned: Lacey Dean
|
3/14/2025 2:46:36 PM
|
Project Created
|