8/19/2025 11:29:01 AM
|
Project Closed
|
8/19/2025 11:29:01 AM
|
Project Approved: 8/19/2025
|
8/19/2025 11:18:36 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
8/11/2025 4:10:54 PM
|
Request for Review Comments email sent for Project LDC Church Parking Lot at HWY 105 Site Dev. Plan for review by Zachary Jannusch on behalf of EPC Stormwater Review
|
8/11/2025 4:10:53 PM
|
Request for Review Comments email sent for Project LDC Church Parking Lot at HWY 105 Site Dev. Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
8/11/2025 4:10:52 PM
|
Request for Review Comments email sent for Project LDC Church Parking Lot at HWY 105 Site Dev. Plan for review by Glenn Reese on behalf of EPC Stormwater Review
|
8/11/2025 4:10:51 PM
|
Request for Review Comments email sent for Project LDC Church Parking Lot at HWY 105 Site Dev. Plan for review by Christina Prete on behalf of EPC Stormwater Review
|
8/11/2025 4:02:42 PM
|
Submission Triaged
|
8/11/2025 10:43:09 AM
|
Submission received from Applicant
|
8/7/2025 7:00:34 AM
|
Submission request sent to Applicant
|
8/7/2025 7:00:22 AM
|
Submission Triaged
|
8/6/2025 5:06:34 PM
|
Submission received from Applicant
|
3/18/2025 4:09:58 PM
|
Submission request sent to Applicant
|
3/18/2025 3:46:49 PM
|
Request for Review Comments returned by PCD Engineering Inspections
|
3/17/2025 10:43:57 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
3/3/2025 1:40:57 PM
|
Request for Review Comments email sent for Project LDC Church Parking Lot at HWY 105 Site Dev. Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
3/3/2025 1:40:56 PM
|
Request for Review Comments email sent for Project LDC Church Parking Lot at HWY 105 Site Dev. Plan for review by Glenn Reese on behalf of EPC Stormwater Review
|
3/3/2025 1:40:55 PM
|
Request for Review Comments email sent for Project LDC Church Parking Lot at HWY 105 Site Dev. Plan for review by Christina Prete on behalf of EPC Stormwater Review
|
3/3/2025 1:40:54 PM
|
Request for Review Comments email sent for Project LDC Church Parking Lot at HWY 105 Site Dev. Plan for review by Brad Walters on behalf of PCD Engineering Inspections
|
2/18/2025 7:01:11 AM
|
Submission Triaged
|
2/14/2025 10:10:04 AM
|
Submission received from Applicant
|
1/29/2025 7:39:55 AM
|
Submission request sent to Applicant
|
1/29/2025 7:38:43 AM
|
No Fees
|
1/29/2025 7:38:43 AM
|
File # Assigned: ASB256
|
1/29/2025 7:38:42 AM
|
Project Manager Assigned: Stormwater Mikayla Hartford
|
1/29/2025 7:38:42 AM
|
Project Created. Parent Project: LDC Church Parking Lot at HWY 105 Site Dev. Plan (PPR2419)
|