| 10/16/2025 9:18:28 AM | Project Ready for Approval requests.  Review Comment period is complete. | 
                
                    | 10/16/2025 9:17:30 AM | Project reopened for Review Comments | 
                
                    | 9/17/2025 3:25:31 PM | Project Ready for Approval requests.  Review Comment period is complete. | 
                
                    | 9/17/2025 3:16:20 PM | Request for Review Comments returned by PCD Project Manager | 
                
                    | 9/17/2025 3:15:41 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Justin Kilgore on behalf of PCD Project Manager | 
                
                    | 9/17/2025 3:14:06 PM | Submission Triaged | 
                
                    | 9/17/2025 2:38:06 PM | Request for Review Comments returned by County Attorney - Development Review | 
                
                    | 9/17/2025 12:34:26 PM | Submission received from Applicant | 
                
                    | 9/17/2025 8:57:52 AM | Request for Review Comments returned by PCD Engineering Division | 
                
                    | 9/16/2025 12:41:13 PM | Submission request sent to Applicant | 
                
                    | 9/16/2025 12:40:11 PM | Request for Review Comments returned by PCD Project Manager | 
                
                    | 9/9/2025 2:41:17 PM | Request for Review Comments returned by Mountain View Electric Association, Inc. | 
                
                    | 9/3/2025 4:54:50 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Lori Seago on behalf of County Attorney - Development Review | 
                
                    | 9/3/2025 4:54:49 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Erika Keech on behalf of County Attorney - Development Review | 
                
                    | 9/3/2025 4:54:48 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by April Willie on behalf of County Attorney - Development Review | 
                
                    | 9/3/2025 4:54:46 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Justin Kilgore on behalf of PCD Project Manager | 
                
                    | 9/3/2025 4:54:45 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Gilbert LaForce on behalf of PCD Engineering Division | 
                
                    | 9/3/2025 4:54:44 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Engineering Manager on behalf of PCD Engineering Division | 
                
                    | 9/3/2025 4:51:23 PM | Submission Triaged | 
                
                    | 9/3/2025 3:43:15 PM | Submission received from Applicant | 
                
                    | 9/3/2025 3:25:55 PM | Submission request sent to Applicant | 
                
                    | 8/20/2025 2:09:43 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by General Email on behalf of Mountain View Electric Association, Inc. | 
                
                    | 8/11/2025 3:07:17 PM | Submission request sent to Applicant | 
                
                    | 8/11/2025 3:05:52 PM | Request for Review Comments returned by PCD Project Manager | 
                
                    | 8/11/2025 12:11:42 PM | Request for Review Comments returned by County Attorney - Development Review | 
                
                    | 7/28/2025 10:57:27 AM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Lori Seago on behalf of County Attorney - Development Review | 
                
                    | 7/28/2025 10:57:26 AM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Erika Keech on behalf of County Attorney - Development Review | 
                
                    | 7/28/2025 10:57:25 AM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by April Willie on behalf of County Attorney - Development Review | 
                
                    | 7/28/2025 10:57:23 AM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Justin Kilgore on behalf of PCD Project Manager | 
                
                    | 7/28/2025 10:54:15 AM | Submission Triaged | 
                
                    | 7/25/2025 2:31:59 PM | Submission received from Applicant | 
                
                    | 6/23/2025 4:20:38 PM | Request for Review Comments returned by Mountain View Electric Association, Inc. | 
                
                    | 6/5/2025 4:27:21 PM | Submission request sent to Applicant | 
                
                    | 6/5/2025 4:24:22 PM | Request for Review Comments returned by PCD Project Manager | 
                
                    | 6/5/2025 10:52:45 AM | Request for Review Comments returned by PCD Engineering Division | 
                
                    | 5/30/2025 11:28:25 AM | Request for Review Comments returned by County Attorney - 1041 | 
                
                    | 5/28/2025 4:00:42 PM | Request for Review Comments returned by Pikes Peak Regional Building Department | 
                
                    | 5/28/2025 9:57:09 AM | Request for Review Comments returned by EPC DPW Stormwater | 
                
                    | 5/16/2025 4:31:51 PM | Request for Review Comments returned by EPC Health Department | 
                
                    | 5/15/2025 3:42:41 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by General Email on behalf of Mountain View Electric Association, Inc. | 
                
                    | 5/15/2025 3:42:40 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by  on behalf of Pikes Peak Regional Building Department | 
                
                    | 5/15/2025 3:42:39 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Zachary Jannusch on behalf of EPC DPW Stormwater | 
                
                    | 5/15/2025 3:42:38 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Mikayla Hartford on behalf of EPC DPW Stormwater | 
                
                    | 5/15/2025 3:42:37 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Glenn Reese on behalf of EPC DPW Stormwater | 
                
                    | 5/15/2025 3:42:36 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Christina Prete on behalf of EPC DPW Stormwater | 
                
                    | 5/15/2025 3:42:34 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by  on behalf of County Attorney - 1041 | 
                
                    | 5/15/2025 3:42:34 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Erika Keech on behalf of County Attorney - 1041 | 
                
                    | 5/15/2025 3:42:33 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by  on behalf of County Attorney - 1041 | 
                
                    | 5/15/2025 3:42:30 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Justin Kilgore on behalf of PCD Project Manager | 
                
                    | 5/15/2025 3:42:29 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Gilbert LaForce on behalf of PCD Engineering Division | 
                
                    | 5/15/2025 3:42:28 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Engineering Manager on behalf of PCD Engineering Division | 
                
                    | 5/15/2025 3:34:57 PM | Submission Triaged | 
                
                    | 5/14/2025 9:35:49 AM | Submission received from Applicant | 
                
                    | 5/2/2025 10:17:19 AM | Submission request sent to Applicant | 
                
                    | 5/2/2025 10:16:08 AM | Submission Triaged | 
                
                    | 5/2/2025 9:32:24 AM | Submission received from Applicant | 
                
                    | 4/29/2025 7:44:18 AM | Request for Review Comments returned by Mountain View Electric Association, Inc. | 
                
                    | 4/17/2025 2:27:16 PM | Submission request sent to Applicant | 
                
                    | 4/17/2025 2:25:20 PM | Request for Review Comments returned by PCD Project Manager | 
                
                    | 4/15/2025 1:40:29 PM | Request for Review Comments returned by PCD Engineering Division | 
                
                    | 4/14/2025 11:05:55 AM | Request for Review Comments returned by Pikes Peak Regional Building Department | 
                
                    | 4/9/2025 4:30:39 PM | Request for Review Comments returned by EPC DPW Stormwater | 
                
                    | 3/26/2025 10:57:25 AM | Request for Review Comments returned by Monument | 
                
                    | 3/25/2025 12:33:14 PM | Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District | 
                
                    | 3/25/2025 12:16:13 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District | 
                
                    | 3/25/2025 12:16:12 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Jonathan Bradley on behalf of Tri-Lakes-Monument Fire Protection District | 
                
                    | 3/25/2025 12:16:11 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Dawn Collins on behalf of Palmer Lake | 
                
                    | 3/25/2025 12:16:10 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Cathy Green on behalf of Palmer Lake | 
                
                    | 3/25/2025 12:16:08 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by William Bass on behalf of Palmer Lake | 
                
                    | 3/25/2025 12:16:07 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by General Email on behalf of Mountain View Electric Association, Inc. | 
                
                    | 3/25/2025 12:16:06 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by  on behalf of Monument | 
                
                    | 3/25/2025 12:16:05 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Vicki Wood on behalf of Lewis Palmer 38 | 
                
                    | 3/25/2025 12:16:04 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Melissa Andrews on behalf of Lewis Palmer 38 | 
                
                    | 3/25/2025 12:16:03 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Brett Ridgway on behalf of Lewis Palmer 38 | 
                
                    | 3/25/2025 12:16:01 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by  on behalf of Pikes Peak Regional Building Department | 
                
                    | 3/25/2025 12:16:00 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Jeff Kramer on behalf of EPC Sheriff's Department | 
                
                    | 3/25/2025 12:15:59 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Christopher Gonzalez on behalf of EPC Sheriff's Department | 
                
                    | 3/25/2025 12:15:58 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Andrew Prehm on behalf of EPC Sheriff's Department | 
                
                    | 3/25/2025 12:15:57 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Mike McCarthy on behalf of EPC Health Department | 
                
                    | 3/25/2025 12:15:56 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Catherine McGarvy on behalf of EPC Health Department | 
                
                    | 3/25/2025 12:15:55 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by HEAEH LandUse on behalf of EPC Health Department | 
                
                    | 3/25/2025 12:15:54 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Mikayla Hartford on behalf of EPC DPW Stormwater | 
                
                    | 3/25/2025 12:15:53 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Glenn Reese on behalf of EPC DPW Stormwater | 
                
                    | 3/25/2025 12:15:52 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Christina Prete on behalf of EPC DPW Stormwater | 
                
                    | 3/25/2025 12:15:49 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Justin Kilgore on behalf of PCD Project Manager | 
                
                    | 3/25/2025 12:15:47 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Gilbert LaForce on behalf of PCD Engineering Division | 
                
                    | 3/25/2025 12:15:46 PM | Request for Review Comments email sent for Project Town of Monument Tank site Exemption  for review by Engineering Manager on behalf of PCD Engineering Division | 
                
                    | 3/25/2025 8:02:40 AM | Project Manager Assigned: Lisa Elgin | 
                
                    | 3/4/2025 8:38:02 AM | Project Manager Assigned: Kylie Bagley | 
                
                    | 2/24/2025 1:01:25 PM | Fees paid: 2/24/2025 (Receipt: 1010200) | 
                
                    | 2/24/2025 12:29:41 PM | Payment Request sent: 2/24/2025 | 
                
                    | 2/24/2025 12:29:41 PM | File # Assigned: EX251 | 
                
                    | 2/24/2025 12:29:37 PM | Submission Triaged | 
                
                    | 2/24/2025 10:10:52 AM | Submission received from Applicant | 
                
                    | 1/8/2025 12:35:47 PM | Submission request sent to Applicant | 
                
                    | 1/8/2025 12:33:31 PM | Project Manager Assigned: Kari Parsons | 
                
                    | 1/8/2025 12:33:31 PM | Project Created |