5/9/2025 9:30:07 AM
|
Project Closed
|
5/9/2025 9:30:07 AM
|
Project Approved: 5/9/2025
|
3/20/2025 1:07:28 PM
|
Request for Review Comments returned by PCD Project Manager
|
3/18/2025 9:47:41 AM
|
Request for Review Comments email sent for Project Crystal Park Site S-353 Plat for review by Justin Kilgore on behalf of PCD Project Manager
|
3/18/2025 9:47:04 AM
|
Submission Triaged
|
3/18/2025 8:33:48 AM
|
Submission received from Applicant
|
3/17/2025 11:01:34 AM
|
Submission request sent to Applicant
|
3/17/2025 11:01:00 AM
|
Request for Review Comments returned by PCD Project Manager
|
3/14/2025 11:44:43 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
3/11/2025 11:07:29 AM
|
Request for Review Comments email sent for Project Crystal Park Site S-353 Plat for review by on behalf of Pikes Peak Regional Building Department
|
3/11/2025 11:07:28 AM
|
Request for Review Comments email sent for Project Crystal Park Site S-353 Plat for review by Justin Kilgore on behalf of PCD Project Manager
|
3/11/2025 10:10:56 AM
|
Fees paid: 3/11/2025 (Receipt: 1010264)
|
12/20/2024 2:53:14 PM
|
Payment Request sent: 12/20/2024
|
12/20/2024 2:53:13 PM
|
File # Assigned: SF2438
|
12/20/2024 2:53:02 PM
|
Submission Triaged
|
12/20/2024 1:41:57 PM
|
Submission received from Applicant
|
11/25/2024 11:15:42 AM
|
Submission request sent to Applicant
|
11/25/2024 11:14:44 AM
|
Project Manager Assigned: Ashlyn Mathy
|
11/25/2024 11:14:44 AM
|
Project Created
|