3/24/2025 8:25:32 AM
|
Project Closed
|
3/24/2025 8:25:32 AM
|
Project Approved: 3/24/2025
|
3/24/2025 8:25:06 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
3/24/2025 8:17:19 AM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
3/24/2025 8:17:18 AM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Glenn Reese on behalf of EPC Stormwater Review
|
3/24/2025 8:17:17 AM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review
|
3/24/2025 8:15:31 AM
|
Submission request canceled
|
3/24/2025 8:13:59 AM
|
Submission request sent to Applicant
|
3/17/2025 9:58:57 AM
|
Submission Triaged
|
3/17/2025 9:54:55 AM
|
Submission received from Applicant
|
3/17/2025 9:52:07 AM
|
Submission request sent to Applicant
|
3/6/2025 2:54:35 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
2/27/2025 7:26:54 AM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
2/27/2025 7:26:53 AM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Glenn Reese on behalf of EPC Stormwater Review
|
2/27/2025 7:26:52 AM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review
|
2/27/2025 7:26:27 AM
|
Submission Triaged
|
2/27/2025 7:12:36 AM
|
Submission Triaged
|
2/26/2025 7:06:03 AM
|
Submission received from Applicant
|
2/24/2025 10:28:33 AM
|
Submission request sent to Applicant
|
1/21/2025 8:57:23 AM
|
Project Manager Assigned: Stormwater Glenn Reese
|
1/6/2025 4:40:51 PM
|
Submission request sent to Applicant
|
1/6/2025 4:39:49 PM
|
Request for Review Comments returned by PCD Engineering Inspections
|
12/30/2024 4:48:02 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
12/30/2024 11:29:35 AM
|
Request for Review Comments returned by PCD Engineering Division
|
12/9/2024 7:20:43 AM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
12/9/2024 7:20:41 AM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Glenn Reese on behalf of EPC Stormwater Review
|
12/9/2024 7:20:40 AM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review
|
12/9/2024 7:20:37 AM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Brad Walters on behalf of PCD Engineering Inspections
|
12/9/2024 7:20:35 AM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
|
12/9/2024 7:20:34 AM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
|
12/9/2024 7:18:10 AM
|
Submission Triaged
|
12/6/2024 12:05:07 PM
|
Submission received from Applicant
|
12/5/2024 5:16:24 PM
|
Submission request sent to Applicant
|
12/5/2024 5:13:25 PM
|
Submission request canceled
|
10/31/2024 9:49:23 AM
|
Submission request sent to Applicant
|
10/31/2024 9:45:43 AM
|
Set Applicant to Colorado Commerial Construction
|
10/31/2024 9:44:54 AM
|
No Fees
|
10/31/2024 9:44:54 AM
|
File # Assigned: ASB2442
|
10/31/2024 9:44:54 AM
|
Project Manager Assigned: Brad Walters
|
10/31/2024 9:44:53 AM
|
Project Created. Parent Project: Mt. States Pipe and Supply Site Development Plan (PPR2020)
|