1/8/2025 10:09:56 AM
|
Project Closed
|
1/8/2025 10:09:56 AM
|
Project Approved: 1/8/2025
|
1/8/2025 10:09:48 AM
|
Project Ready for Approval requests. Review Comment period is complete.
|
1/8/2025 9:54:47 AM
|
Request for Review Comments returned by PCD Project Manager
|
1/6/2025 10:53:59 AM
|
Request for Review Comments email sent for Project 15620 Hwy 94 (AT&T) Tower Equipment Swap for review by Justin Kilgore on behalf of PCD Project Manager
|
1/6/2025 10:53:36 AM
|
Submission Triaged
|
1/6/2025 10:09:09 AM
|
Submission received from Applicant
|
11/12/2024 1:23:52 PM
|
Request for Review Comments returned by Upper Black Squirrel Creek GWMD
|
10/24/2024 9:51:13 PM
|
Request for Review Comments returned by Ellicott Fire Protection District
|
10/22/2024 8:21:15 AM
|
Request for Review Comments returned by Meadow Lake Airport Association
|
10/15/2024 11:48:13 AM
|
Request for Review Comments returned by Schriever AFB
|
10/15/2024 9:26:15 AM
|
Submission request sent to Applicant
|
10/15/2024 9:25:07 AM
|
Request for Review Comments returned by PCD Project Manager
|
10/15/2024 8:51:18 AM
|
Request for Review Comments returned by County Attorney - Development Review
|
10/11/2024 12:18:09 PM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
10/10/2024 5:27:27 PM
|
Request for Review Comments returned by PCD Engineering Division
|
10/10/2024 10:38:32 AM
|
Request for Review Comments returned by Colorado Springs Airport Advisory Commission
|
10/10/2024 8:04:13 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
10/9/2024 1:53:54 PM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
10/9/2024 10:39:57 AM
|
Request for Review Comments email sent for Project 15620 Hwy 94 (AT&T) Tower Equipment Swap for review by Darren Horstmeier on behalf of Schriever AFB
|
10/9/2024 10:39:55 AM
|
Request for Review Comments email sent for Project 15620 Hwy 94 (AT&T) Tower Equipment Swap for review by Dave Elliott on behalf of Meadow Lake Airport Association
|
10/9/2024 10:39:53 AM
|
Request for Review Comments email sent for Project 15620 Hwy 94 (AT&T) Tower Equipment Swap for review by Chris Smith on behalf of Ellicott SD 22
|
10/9/2024 10:39:51 AM
|
Request for Review Comments email sent for Project 15620 Hwy 94 (AT&T) Tower Equipment Swap for review by Peggy Current on behalf of Ellicott Metro
|
10/9/2024 10:39:49 AM
|
Request for Review Comments email sent for Project 15620 Hwy 94 (AT&T) Tower Equipment Swap for review by Michael Henley on behalf of Ellicott Fire Protection District
|
10/9/2024 10:39:47 AM
|
Request for Review Comments email sent for Project 15620 Hwy 94 (AT&T) Tower Equipment Swap for review by Norma Houghton on behalf of Ellicott Fire Protection District
|
10/9/2024 10:39:45 AM
|
Request for Review Comments email sent for Project 15620 Hwy 94 (AT&T) Tower Equipment Swap for review by LBS Review on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
10/9/2024 10:39:43 AM
|
Request for Review Comments email sent for Project 15620 Hwy 94 (AT&T) Tower Equipment Swap for review by on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
10/9/2024 10:39:41 AM
|
Request for Review Comments email sent for Project 15620 Hwy 94 (AT&T) Tower Equipment Swap for review by Chris Padilla on behalf of Colorado Springs Airport Advisory Commission
|
10/9/2024 10:39:39 AM
|
Request for Review Comments email sent for Project 15620 Hwy 94 (AT&T) Tower Equipment Swap for review by Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
|
10/9/2024 10:39:37 AM
|
Request for Review Comments email sent for Project 15620 Hwy 94 (AT&T) Tower Equipment Swap for review by on behalf of Pikes Peak Regional Building Department
|
10/9/2024 10:39:35 AM
|
Request for Review Comments email sent for Project 15620 Hwy 94 (AT&T) Tower Equipment Swap for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
10/9/2024 10:39:33 AM
|
Request for Review Comments email sent for Project 15620 Hwy 94 (AT&T) Tower Equipment Swap for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
|
10/9/2024 10:39:31 AM
|
Request for Review Comments email sent for Project 15620 Hwy 94 (AT&T) Tower Equipment Swap for review by Mike McCarthy on behalf of EPC Health Department
|
10/9/2024 10:39:29 AM
|
Request for Review Comments email sent for Project 15620 Hwy 94 (AT&T) Tower Equipment Swap for review by Catherine McGarvy on behalf of EPC Health Department
|
10/9/2024 10:39:27 AM
|
Request for Review Comments email sent for Project 15620 Hwy 94 (AT&T) Tower Equipment Swap for review by HEAEH LandUse on behalf of EPC Health Department
|
10/9/2024 10:39:25 AM
|
Request for Review Comments email sent for Project 15620 Hwy 94 (AT&T) Tower Equipment Swap for review by Lori Seago on behalf of County Attorney - Development Review
|
10/9/2024 10:39:23 AM
|
Request for Review Comments email sent for Project 15620 Hwy 94 (AT&T) Tower Equipment Swap for review by Erika Keech on behalf of County Attorney - Development Review
|
10/9/2024 10:39:21 AM
|
Request for Review Comments email sent for Project 15620 Hwy 94 (AT&T) Tower Equipment Swap for review by April Willie on behalf of County Attorney - Development Review
|
10/9/2024 10:39:19 AM
|
Request for Review Comments email sent for Project 15620 Hwy 94 (AT&T) Tower Equipment Swap for review by Kari Parsons on behalf of PCD Project Manager
|
10/9/2024 10:39:17 AM
|
Request for Review Comments email sent for Project 15620 Hwy 94 (AT&T) Tower Equipment Swap for review by Gilbert LaForce on behalf of PCD Engineering Division
|
10/9/2024 10:39:16 AM
|
Request for Review Comments email sent for Project 15620 Hwy 94 (AT&T) Tower Equipment Swap for review by Engineering Manager on behalf of PCD Engineering Division
|
10/3/2024 1:14:53 PM
|
Fees paid: 10/3/2024 (Receipt: 1009658)
|
9/30/2024 2:54:10 PM
|
Payment Request sent: 9/30/2024
|
9/30/2024 2:54:10 PM
|
File # Assigned: TWR2411
|
9/30/2024 2:54:03 PM
|
Submission Triaged
|
9/30/2024 2:48:59 PM
|
Submission received from Applicant
|
9/27/2024 2:36:58 PM
|
Submission request sent to Applicant
|
9/27/2024 2:21:39 PM
|
Project Manager Assigned: Ashlyn Mathy
|
9/27/2024 2:21:39 PM
|
Project Created
|