3/24/2025 11:09:26 AM
|
Project Closed
|
3/24/2025 11:09:26 AM
|
Project Approved: 3/24/2025
|
2/12/2025 1:57:05 PM
|
Fees paid: 2/12/2025 (Receipt: 1010158)
|
2/4/2025 10:28:57 AM
|
Payment Request sent: 2/4/2025
|
1/21/2025 3:31:48 PM
|
Request for Review Comments returned by PCD Engineering Division
|
1/21/2025 8:49:51 AM
|
Request for Review Comments returned by PCD Project Manager
|
1/14/2025 9:27:38 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Justin Kilgore on behalf of PCD Project Manager
|
1/14/2025 9:27:35 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Gilbert LaForce on behalf of PCD Engineering Division
|
1/14/2025 9:27:34 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Engineering Manager on behalf of PCD Engineering Division
|
1/14/2025 9:24:20 AM
|
Submission Triaged
|
1/3/2025 1:24:15 PM
|
Submission received from Applicant
|
11/19/2024 4:11:49 PM
|
Request for Review Comments returned by County Attorney - Water
|
11/18/2024 5:15:28 PM
|
Submission request sent to Applicant
|
11/18/2024 5:14:57 PM
|
Request for Review Comments returned by PCD Project Manager
|
11/18/2024 5:05:07 PM
|
Request for Review Comments returned by PCD Engineering Division
|
11/18/2024 2:44:21 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
11/18/2024 8:58:37 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
11/14/2024 9:32:38 AM
|
Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
|
11/4/2024 9:37:55 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District
|
11/4/2024 9:37:53 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Jonathan Bradley on behalf of Tri-Lakes-Monument Fire Protection District
|
11/4/2024 9:37:51 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by on behalf of Black Forest Fire Protection District
|
11/4/2024 9:37:49 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
11/4/2024 9:37:47 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Glenn Reese on behalf of EPC Stormwater Review
|
11/4/2024 9:37:45 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Christina Prete on behalf of EPC Stormwater Review
|
11/4/2024 9:37:43 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Lori Seago on behalf of County Attorney - Water
|
11/4/2024 9:37:41 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Erika Keech on behalf of County Attorney - Water
|
11/4/2024 9:37:40 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by April Willie on behalf of County Attorney - Water
|
11/4/2024 9:37:38 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Lori Seago on behalf of County Attorney - Development Review
|
11/4/2024 9:37:36 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Erika Keech on behalf of County Attorney - Development Review
|
11/4/2024 9:37:34 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by April Willie on behalf of County Attorney - Development Review
|
11/4/2024 9:37:32 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Justin Kilgore on behalf of PCD Project Manager
|
11/4/2024 9:37:26 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Gilbert LaForce on behalf of PCD Engineering Division
|
11/4/2024 9:37:25 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Engineering Manager on behalf of PCD Engineering Division
|
11/4/2024 9:32:57 AM
|
Submission Triaged
|
11/1/2024 2:05:25 PM
|
Submission received from Applicant
|
10/13/2024 2:26:47 PM
|
Request for Review Comments returned by EPC Health Department
|
9/26/2024 10:01:29 AM
|
Request for Review Comments returned by Parks Advisory Board
|
9/26/2024 9:35:33 AM
|
Request for Review Comments returned by EPC Parks Department
|
9/24/2024 10:40:24 PM
|
Request for Review Comments returned by Black Forest Fire Protection District
|
9/24/2024 4:48:45 PM
|
Submission request sent to Applicant
|
9/24/2024 4:43:43 PM
|
Request for Review Comments returned by PCD Project Manager
|
9/24/2024 2:48:04 PM
|
Request for Review Comments returned by PCD Engineering Division
|
9/24/2024 10:35:09 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
9/23/2024 10:48:05 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
9/23/2024 10:17:59 AM
|
Request for Review Comments returned by Colorado Geological Survey
|
9/20/2024 9:51:42 PM
|
Request for Review Comments returned by Colorado Parks and Wildlife
|
9/12/2024 1:43:57 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
9/9/2024 3:03:10 PM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
9/9/2024 10:20:26 AM
|
Request for Review Comments returned by County Attorney - Water
|
9/9/2024 9:55:07 AM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
9/5/2024 1:35:34 PM
|
Request for Review Comments returned by EPC Environmental Services
|
9/5/2024 9:48:07 AM
|
Request for Review Comments returned by Road Impact Fee Administrator
|
9/4/2024 1:57:08 PM
|
Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
|
9/4/2024 9:19:46 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
9/3/2024 7:50:47 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District
|
9/3/2024 7:50:45 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Jonathan Bradley on behalf of Tri-Lakes-Monument Fire Protection District
|
9/3/2024 7:50:43 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Vicki Wood on behalf of Lewis Palmer 38
|
9/3/2024 7:50:41 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Melissa Andrews on behalf of Lewis Palmer 38
|
9/3/2024 7:50:39 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Brett Ridgway on behalf of Lewis Palmer 38
|
9/3/2024 7:50:37 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Harry Thomas on behalf of El Paso County Conservation Dist
|
9/3/2024 7:50:35 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Oliver Watkins on behalf of El Paso County Conservation Dist
|
9/3/2024 7:50:33 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Katie Miller on behalf of El Paso County Conservation Dist
|
9/3/2024 7:50:31 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Erica Carter on behalf of El Paso County Conservation Dist
|
9/3/2024 7:50:29 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Mariah Hudson on behalf of El Paso County Conservation Dist
|
9/3/2024 7:50:28 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Cassie Olgren on behalf of El Paso County Conservation Dist
|
9/3/2024 7:50:26 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Billy Richard on behalf of El Paso County Conservation Dist
|
9/3/2024 7:50:23 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by on behalf of Black Forest Fire Protection District
|
9/3/2024 7:50:21 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by on behalf of Pikes Peak Regional Building Department
|
9/3/2024 7:50:19 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
9/3/2024 7:50:17 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
|
9/3/2024 7:50:15 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Travis Sauder on behalf of Colorado Parks and Wildlife
|
9/3/2024 7:50:14 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Tim Kroening on behalf of Colorado Parks and Wildlife
|
9/3/2024 7:50:12 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Karen Voltura on behalf of Colorado Parks and Wildlife
|
9/3/2024 7:50:10 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Cassidy English on behalf of Colorado Parks and Wildlife
|
9/3/2024 7:50:08 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
9/3/2024 7:50:06 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Melissa Van Der Poel on behalf of Colorado Division of Water Resources
|
9/3/2024 7:50:04 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
9/3/2024 7:50:02 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Victoria Chavez on behalf of Road Impact Fee Administrator
|
9/3/2024 7:50:00 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by on behalf of Parks Advisory Board
|
9/3/2024 7:49:58 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
9/3/2024 7:49:56 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Glenn Reese on behalf of EPC Stormwater Review
|
9/3/2024 7:49:54 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Christina Prete on behalf of EPC Stormwater Review
|
9/3/2024 7:49:52 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Jeff Kramer on behalf of EPC Sheriff's Department
|
9/3/2024 7:49:50 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Christopher Gonzalez on behalf of EPC Sheriff's Department
|
9/3/2024 7:49:48 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Andrew Prehm on behalf of EPC Sheriff's Department
|
9/3/2024 7:49:46 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by on behalf of EPC Parks Department
|
9/3/2024 7:49:44 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Mike McCarthy on behalf of EPC Health Department
|
9/3/2024 7:49:42 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Catherine McGarvy on behalf of EPC Health Department
|
9/3/2024 7:49:40 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by HEAEH LandUse on behalf of EPC Health Department
|
9/3/2024 7:49:38 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Kathy Andrew on behalf of EPC Environmental Services
|
9/3/2024 7:49:36 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Lori Seago on behalf of County Attorney - Water
|
9/3/2024 7:49:34 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Erika Keech on behalf of County Attorney - Water
|
9/3/2024 7:49:32 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by April Willie on behalf of County Attorney - Water
|
9/3/2024 7:49:30 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Lori Seago on behalf of County Attorney - Development Review
|
9/3/2024 7:49:28 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Erika Keech on behalf of County Attorney - Development Review
|
9/3/2024 7:49:26 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by April Willie on behalf of County Attorney - Development Review
|
9/3/2024 7:49:24 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Kari Parsons on behalf of PCD Project Manager
|
9/3/2024 7:49:21 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Gilbert LaForce on behalf of PCD Engineering Division
|
9/3/2024 7:49:19 AM
|
Request for Review Comments email sent for Project Misfit Crew Estates Final Plat for review by Engineering Manager on behalf of PCD Engineering Division
|
8/30/2024 12:49:50 PM
|
Project Manager Assigned: Joe Letke
|
8/30/2024 11:44:44 AM
|
Fees paid: 8/30/2024 (Receipt: 1009535)
|
8/28/2024 11:57:46 AM
|
Payment Request sent: 8/28/2024
|
8/28/2024 11:57:46 AM
|
File # Assigned: SF2417
|
8/28/2024 11:57:37 AM
|
Submission Triaged
|
8/28/2024 10:37:21 AM
|
Submission received from Applicant
|
8/28/2024 9:44:59 AM
|
Submission request sent to Applicant
|
8/28/2024 9:42:52 AM
|
Submission request canceled
|
8/28/2024 9:42:30 AM
|
Submission request sent to Applicant
|
8/28/2024 9:39:25 AM
|
Submission Triaged
|
8/28/2024 9:05:10 AM
|
Submission received from Applicant
|
7/16/2024 2:03:43 PM
|
Submission request sent to Applicant
|
7/15/2024 11:18:47 AM
|
EA Assigned: EA2339
|
7/15/2024 11:18:47 AM
|
Project Created
|