3/13/2025 4:43:53 PM
|
Project Closed
|
3/13/2025 4:43:53 PM
|
Project Approved: 3/13/2025
|
3/13/2025 4:40:06 PM
|
Request for Review Comments returned by PCD Project Manager
|
3/13/2025 3:40:51 PM
|
Request for Review Comments email sent for Project 10410 Hwy 115 Tower - Generator Install for review by Justin Kilgore on behalf of PCD Project Manager
|
3/13/2025 3:39:59 PM
|
Submission Triaged
|
3/13/2025 11:29:32 AM
|
Submission received from Applicant
|
3/12/2025 6:26:36 PM
|
Submission request sent to Applicant
|
3/12/2025 11:07:18 AM
|
Request for Review Comments returned by PCD Project Manager
|
3/11/2025 11:04:00 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
3/10/2025 12:48:24 PM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
3/7/2025 11:48:01 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
3/7/2025 9:26:55 AM
|
Request for Review Comments returned by PCD Engineering Division
|
3/5/2025 12:30:34 PM
|
Request for Review Comments email sent for Project 10410 Hwy 115 Tower - Generator Install for review by Harold Noonan on behalf of U.S. Department of the Army/Fort Carson
|
3/5/2025 12:30:33 PM
|
Request for Review Comments email sent for Project 10410 Hwy 115 Tower - Generator Install for review by Hart Wright on behalf of Southwestern Hwy 115 Fire Protection District
|
3/5/2025 12:30:32 PM
|
Request for Review Comments email sent for Project 10410 Hwy 115 Tower - Generator Install for review by on behalf of Pikes Peak Regional Building Department
|
3/5/2025 12:30:31 PM
|
Request for Review Comments email sent for Project 10410 Hwy 115 Tower - Generator Install for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
3/5/2025 12:30:30 PM
|
Request for Review Comments email sent for Project 10410 Hwy 115 Tower - Generator Install for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
|
3/5/2025 12:30:28 PM
|
Request for Review Comments email sent for Project 10410 Hwy 115 Tower - Generator Install for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
3/5/2025 12:30:28 PM
|
Request for Review Comments email sent for Project 10410 Hwy 115 Tower - Generator Install for review by Glenn Reese on behalf of EPC Stormwater Review
|
3/5/2025 12:30:27 PM
|
Request for Review Comments email sent for Project 10410 Hwy 115 Tower - Generator Install for review by Christina Prete on behalf of EPC Stormwater Review
|
3/5/2025 12:30:24 PM
|
Request for Review Comments email sent for Project 10410 Hwy 115 Tower - Generator Install for review by Justin Kilgore on behalf of PCD Project Manager
|
3/5/2025 12:30:23 PM
|
Request for Review Comments email sent for Project 10410 Hwy 115 Tower - Generator Install for review by Gilbert LaForce on behalf of PCD Engineering Division
|
3/5/2025 12:30:22 PM
|
Request for Review Comments email sent for Project 10410 Hwy 115 Tower - Generator Install for review by Engineering Manager on behalf of PCD Engineering Division
|
3/4/2025 12:58:12 PM
|
Fees paid: 3/4/2025 (Receipt: 1010232)
|
2/28/2025 4:47:26 PM
|
Payment Request sent: 2/28/2025
|
2/28/2025 4:47:26 PM
|
File # Assigned: TWR258
|
2/28/2025 4:47:23 PM
|
Submission Triaged
|
2/28/2025 9:06:43 AM
|
Submission received from Applicant
|
6/27/2024 1:50:09 PM
|
Submission request sent to Applicant
|
6/19/2024 2:40:31 PM
|
Submission request sent to Applicant
|
6/19/2024 2:30:47 PM
|
Project Manager Assigned: Lacey Dean
|
6/19/2024 2:30:47 PM
|
Project Created
|