Project Details

Search


File Number
TWR258
Project Name
10410 Hwy 115 Tower - Generator Install
Description
T-Mobile plans to install a new diesel generator at the cell tower facility located at 101410 State Hwy 115.
Parcels
7602400004 7602400004
Applicant
Crown Castle - Craig Chagnon
Craig Chagnon ( Craig.Chagnon@crowncastle.com )
(801) 979-9077
Craig Chagnon ( Craig.Chagnon@crowncastle.com )
(801) 979-9077
File Prefix
TWR - Tower
Year
2025
Project Manager
Lacey Dean
Status
Closed
Created
6/19/2024 2:30:45 PM

View: Review Comments


Approved Documents (1)

Link Document
View Site Development Plan


Review Documents (5)

Link Document Date
View Letter of Intent 2/28/2025 9:04:46 AM
View Site Plan Drawing 3/13/2025 11:28:21 AM
View Assessor Tax Record 2/28/2025 9:04:48 AM
View Construction Drawings 2/28/2025 9:04:47 AM
View Elevation Plans 2/28/2025 9:04:45 AM



Events (32)

Date Comment
3/13/2025 4:43:53 PM Project Closed
3/13/2025 4:43:53 PM Project Approved: 3/13/2025
3/13/2025 4:40:06 PM Request for Review Comments returned by PCD Project Manager
3/13/2025 3:40:51 PM Request for Review Comments email sent for Project 10410 Hwy 115 Tower - Generator Install for review by Justin Kilgore on behalf of PCD Project Manager
3/13/2025 3:39:59 PM Submission Triaged
3/13/2025 11:29:32 AM Submission received from Applicant
3/12/2025 6:26:36 PM Submission request sent to Applicant
3/12/2025 11:07:18 AM Request for Review Comments returned by PCD Project Manager
3/11/2025 11:04:00 AM Request for Review Comments returned by EPC Stormwater Review
3/10/2025 12:48:24 PM Request for Review Comments returned by 911 Authority - El Paso/Teller County
3/7/2025 11:48:01 AM Request for Review Comments returned by Pikes Peak Regional Building Department
3/7/2025 9:26:55 AM Request for Review Comments returned by PCD Engineering Division
3/5/2025 12:30:34 PM Request for Review Comments email sent for Project 10410 Hwy 115 Tower - Generator Install for review by Harold Noonan on behalf of U.S. Department of the Army/Fort Carson
3/5/2025 12:30:33 PM Request for Review Comments email sent for Project 10410 Hwy 115 Tower - Generator Install for review by Hart Wright on behalf of Southwestern Hwy 115 Fire Protection District
3/5/2025 12:30:32 PM Request for Review Comments email sent for Project 10410 Hwy 115 Tower - Generator Install for review by on behalf of Pikes Peak Regional Building Department
3/5/2025 12:30:31 PM Request for Review Comments email sent for Project 10410 Hwy 115 Tower - Generator Install for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
3/5/2025 12:30:30 PM Request for Review Comments email sent for Project 10410 Hwy 115 Tower - Generator Install for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
3/5/2025 12:30:28 PM Request for Review Comments email sent for Project 10410 Hwy 115 Tower - Generator Install for review by Mikayla Hartford on behalf of EPC Stormwater Review
3/5/2025 12:30:28 PM Request for Review Comments email sent for Project 10410 Hwy 115 Tower - Generator Install for review by Glenn Reese on behalf of EPC Stormwater Review
3/5/2025 12:30:27 PM Request for Review Comments email sent for Project 10410 Hwy 115 Tower - Generator Install for review by Christina Prete on behalf of EPC Stormwater Review
3/5/2025 12:30:24 PM Request for Review Comments email sent for Project 10410 Hwy 115 Tower - Generator Install for review by Justin Kilgore on behalf of PCD Project Manager
3/5/2025 12:30:23 PM Request for Review Comments email sent for Project 10410 Hwy 115 Tower - Generator Install for review by Gilbert LaForce on behalf of PCD Engineering Division
3/5/2025 12:30:22 PM Request for Review Comments email sent for Project 10410 Hwy 115 Tower - Generator Install for review by Engineering Manager on behalf of PCD Engineering Division
3/4/2025 12:58:12 PM Fees paid: 3/4/2025 (Receipt: 1010232)
2/28/2025 4:47:26 PM Payment Request sent: 2/28/2025
2/28/2025 4:47:26 PM File # Assigned: TWR258
2/28/2025 4:47:23 PM Submission Triaged
2/28/2025 9:06:43 AM Submission received from Applicant
6/27/2024 1:50:09 PM Submission request sent to Applicant
6/19/2024 2:40:31 PM Submission request sent to Applicant
6/19/2024 2:30:47 PM Project Manager Assigned: Lacey Dean
6/19/2024 2:30:47 PM Project Created