3/24/2025 11:08:32 AM
|
Project Closed
|
3/24/2025 11:08:32 AM
|
Project Approved: 3/24/2025
|
2/10/2025 2:10:10 PM
|
Request for Review Comments returned by Falcon Fire Protection District
|
2/6/2025 9:49:58 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Trent Harwig on behalf of Falcon Fire Protection District
|
2/6/2025 9:49:57 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Curtis Kauffman on behalf of Falcon Fire Protection District
|
2/4/2025 11:55:13 AM
|
Payment Request sent: 2/4/2025
|
1/29/2025 5:29:58 PM
|
Request for Review Comments returned by PCD Engineering Division
|
1/28/2025 11:00:16 AM
|
Request for Review Comments returned by County Attorney - Development Review
|
1/28/2025 10:34:12 AM
|
Submission request sent to Applicant
|
1/28/2025 10:25:16 AM
|
Request for Review Comments returned by County Attorney - Water
|
1/28/2025 8:13:50 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Gilbert LaForce on behalf of PCD Engineering Division
|
1/28/2025 8:13:49 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Engineering Manager on behalf of PCD Engineering Division
|
1/28/2025 8:10:47 AM
|
Submission Triaged
|
1/27/2025 2:27:49 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
1/27/2025 10:33:45 AM
|
Submission received from Applicant
|
1/27/2025 8:07:55 AM
|
Submission request sent to Applicant
|
1/27/2025 8:06:28 AM
|
Submission Triaged
|
1/27/2025 7:46:41 AM
|
Request for Review Comments returned by PCD Engineering Division
|
1/27/2025 7:33:45 AM
|
Submission received from Applicant
|
1/23/2025 10:44:00 AM
|
Submission request sent to Applicant
|
1/23/2025 10:20:33 AM
|
Request for Review Comments returned by PCD Project Manager
|
1/10/2025 10:47:54 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
1/9/2025 9:26:11 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by General Email on behalf of Mountain View Electric Association, Inc.
|
1/9/2025 9:26:10 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by on behalf of Pikes Peak Regional Building Department
|
1/9/2025 9:26:09 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Lori Seago on behalf of County Attorney - Water
|
1/9/2025 9:26:07 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Erika Keech on behalf of County Attorney - Water
|
1/9/2025 9:26:06 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by April Willie on behalf of County Attorney - Water
|
1/9/2025 9:26:05 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Lori Seago on behalf of County Attorney - Development Review
|
1/9/2025 9:26:03 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Erika Keech on behalf of County Attorney - Development Review
|
1/9/2025 9:26:02 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by April Willie on behalf of County Attorney - Development Review
|
1/9/2025 9:26:01 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Justin Kilgore on behalf of PCD Project Manager
|
1/9/2025 9:25:57 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Gilbert LaForce on behalf of PCD Engineering Division
|
1/9/2025 9:25:55 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Engineering Manager on behalf of PCD Engineering Division
|
1/9/2025 9:17:05 AM
|
Submission Triaged
|
1/7/2025 12:34:57 PM
|
Submission received from Applicant
|
12/16/2024 3:19:47 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
12/16/2024 2:49:13 PM
|
Submission request sent to Applicant
|
12/16/2024 2:47:35 PM
|
Request for Review Comments returned by PCD Project Manager
|
12/16/2024 2:14:57 PM
|
Request for Review Comments returned by PCD Engineering Division
|
12/11/2024 10:03:13 AM
|
Request for Review Comments returned by County Attorney - Water
|
12/9/2024 2:45:31 PM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Lori Seago on behalf of County Attorney - Water
|
12/9/2024 2:45:29 PM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Erika Keech on behalf of County Attorney - Water
|
12/9/2024 2:45:28 PM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by April Willie on behalf of County Attorney - Water
|
12/9/2024 2:44:18 PM
|
Submission Triaged
|
12/9/2024 2:43:18 PM
|
Submission received from Applicant
|
12/2/2024 7:52:29 AM
|
Submission request sent to Applicant
|
12/2/2024 7:17:50 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Lori Seago on behalf of County Attorney - Development Review
|
12/2/2024 7:17:48 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Erika Keech on behalf of County Attorney - Development Review
|
12/2/2024 7:17:46 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by April Willie on behalf of County Attorney - Development Review
|
12/2/2024 7:17:44 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Justin Kilgore on behalf of PCD Project Manager
|
12/2/2024 7:17:40 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Gilbert LaForce on behalf of PCD Engineering Division
|
12/2/2024 7:17:37 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Engineering Manager on behalf of PCD Engineering Division
|
12/2/2024 7:13:36 AM
|
Submission request canceled
|
12/2/2024 7:13:19 AM
|
Submission Triaged
|
12/2/2024 7:06:19 AM
|
Submission request sent to Applicant
|
12/2/2024 7:06:03 AM
|
Submission Triaged
|
11/26/2024 4:40:31 PM
|
Submission received from Applicant
|
11/25/2024 9:14:59 AM
|
Submission request sent to Applicant
|
11/25/2024 9:14:43 AM
|
Submission Triaged
|
11/24/2024 7:48:23 AM
|
Submission received from Applicant
|
10/24/2024 1:08:41 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
10/22/2024 2:14:31 PM
|
Request for Review Comments returned by County Attorney - Water
|
10/15/2024 10:20:55 AM
|
Request for Review Comments returned by Falcon Fire Protection District
|
10/14/2024 4:32:02 PM
|
Submission request sent to Applicant
|
10/14/2024 4:27:53 PM
|
Request for Review Comments returned by PCD Project Manager
|
10/14/2024 4:20:01 PM
|
Request for Review Comments returned by PCD Engineering Division
|
10/14/2024 3:19:45 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
10/14/2024 10:39:27 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Trent Harwig on behalf of Falcon Fire Protection District
|
10/14/2024 10:39:25 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Curtis Kauffman on behalf of Falcon Fire Protection District
|
10/9/2024 10:59:23 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by General Email on behalf of Mountain View Electric Association, Inc.
|
9/30/2024 12:24:35 PM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Lori Seago on behalf of County Attorney - Water
|
9/30/2024 12:24:33 PM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Erika Keech on behalf of County Attorney - Water
|
9/30/2024 12:24:31 PM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by April Willie on behalf of County Attorney - Water
|
9/30/2024 12:24:28 PM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Lori Seago on behalf of County Attorney - Development Review
|
9/30/2024 12:24:26 PM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Erika Keech on behalf of County Attorney - Development Review
|
9/30/2024 12:24:24 PM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by April Willie on behalf of County Attorney - Development Review
|
9/30/2024 12:24:22 PM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Kari Parsons on behalf of PCD Project Manager
|
9/30/2024 12:24:18 PM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Gilbert LaForce on behalf of PCD Engineering Division
|
9/30/2024 12:24:14 PM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Engineering Manager on behalf of PCD Engineering Division
|
9/30/2024 12:20:38 PM
|
Submission Triaged
|
9/30/2024 9:04:05 AM
|
Submission received from Applicant
|
9/30/2024 7:13:02 AM
|
Submission request sent to Applicant
|
9/30/2024 7:11:15 AM
|
Submission Triaged
|
9/26/2024 4:10:06 PM
|
Submission received from Applicant
|
9/13/2024 6:24:19 PM
|
Request for Review Comments returned by EPC Health Department
|
9/5/2024 9:48:29 AM
|
Request for Review Comments returned by Road Impact Fee Administrator
|
8/23/2024 11:34:36 AM
|
Request for Review Comments returned by Parks Advisory Board
|
8/23/2024 11:33:31 AM
|
Request for Review Comments returned by EPC Parks Department
|
8/20/2024 3:03:24 PM
|
Request for Review Comments returned by Falcon School District 49
|
8/19/2024 5:02:11 PM
|
Submission request sent to Applicant
|
8/19/2024 5:00:50 PM
|
Request for Review Comments returned by PCD Project Manager
|
8/19/2024 4:37:20 PM
|
Request for Review Comments returned by PCD Engineering Division
|
8/19/2024 3:46:54 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
8/19/2024 10:24:59 AM
|
Request for Review Comments returned by Colorado Geological Survey
|
8/19/2024 8:12:14 AM
|
Request for Review Comments returned by Falcon Fire Protection District
|
8/16/2024 10:36:46 AM
|
Request for Review Comments returned by US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
8/15/2024 2:05:40 PM
|
Request for Review Comments returned by Colorado Parks and Wildlife
|
8/15/2024 10:22:49 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
8/12/2024 1:02:25 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
8/6/2024 4:11:13 PM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
8/2/2024 2:52:05 PM
|
Request for Review Comments returned by EPC Environmental Services
|
8/2/2024 12:10:38 PM
|
Request for Review Comments returned by County Attorney - Water
|
8/1/2024 2:04:34 PM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
8/1/2024 1:21:23 PM
|
Submission Triaged
|
8/1/2024 6:47:29 AM
|
Submission received from Applicant
|
7/29/2024 10:52:38 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Evelyn galanephillips on behalf of Falcon School District 49
|
7/29/2024 10:52:36 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Trent Harwig on behalf of Falcon Fire Protection District
|
7/29/2024 10:52:34 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Curtis Kauffman on behalf of Falcon Fire Protection District
|
7/29/2024 10:52:32 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by on behalf of Pikes Peak Regional Building Department
|
7/29/2024 10:52:30 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
7/29/2024 10:52:28 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
|
7/29/2024 10:52:26 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Julie Reeves on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
7/29/2024 10:52:24 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by george san miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
7/29/2024 10:52:22 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
7/29/2024 10:52:20 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Travis Sauder on behalf of Colorado Parks and Wildlife
|
7/29/2024 10:52:18 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Tim Kroening on behalf of Colorado Parks and Wildlife
|
7/29/2024 10:52:16 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Karen Voltura on behalf of Colorado Parks and Wildlife
|
7/29/2024 10:52:14 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Cassidy English on behalf of Colorado Parks and Wildlife
|
7/29/2024 10:52:12 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
7/29/2024 10:52:10 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Melissa Van Der Poel on behalf of Colorado Division of Water Resources
|
7/29/2024 10:52:08 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
7/29/2024 10:52:06 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Victoria Chavez on behalf of Road Impact Fee Administrator
|
7/29/2024 10:52:04 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by on behalf of Parks Advisory Board
|
7/29/2024 10:52:02 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Shannon Mustoe on behalf of EPC Stormwater Review
|
7/29/2024 10:52:00 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
7/29/2024 10:51:58 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Glenn Reese on behalf of EPC Stormwater Review
|
7/29/2024 10:51:56 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Christina Prete on behalf of EPC Stormwater Review
|
7/29/2024 10:51:54 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Jeff Kramer on behalf of EPC Sheriff's Department
|
7/29/2024 10:51:52 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Christopher Gonzalez on behalf of EPC Sheriff's Department
|
7/29/2024 10:51:50 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Andrew Prehm on behalf of EPC Sheriff's Department
|
7/29/2024 10:51:48 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by on behalf of EPC Parks Department
|
7/29/2024 10:51:46 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Mike McCarthy on behalf of EPC Health Department
|
7/29/2024 10:51:44 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Catherine McGarvy on behalf of EPC Health Department
|
7/29/2024 10:51:42 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by HEAEH LandUse on behalf of EPC Health Department
|
7/29/2024 10:51:40 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Kathy Andrew on behalf of EPC Environmental Services
|
7/29/2024 10:51:38 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Lori Seago on behalf of County Attorney - Water
|
7/29/2024 10:51:36 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Erika Keech on behalf of County Attorney - Water
|
7/29/2024 10:51:34 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by April Willie on behalf of County Attorney - Water
|
7/29/2024 10:51:32 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Lori Seago on behalf of County Attorney - Development Review
|
7/29/2024 10:51:30 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Erika Keech on behalf of County Attorney - Development Review
|
7/29/2024 10:51:28 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by April Willie on behalf of County Attorney - Development Review
|
7/29/2024 10:51:26 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Kari Parsons on behalf of PCD Project Manager
|
7/29/2024 10:51:22 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Gilbert LaForce on behalf of PCD Engineering Division
|
7/29/2024 10:51:20 AM
|
Request for Review Comments email sent for Project Berisford Subdivision - Final Plat for review by Engineering Manager on behalf of PCD Engineering Division
|
7/25/2024 12:21:37 PM
|
Project Manager Assigned: Joe Letke
|
7/25/2024 9:24:40 AM
|
Fees paid: 7/25/2024 (Receipt: 1009392)
|
7/24/2024 1:09:51 PM
|
Payment Request sent: 7/24/2024
|
7/24/2024 1:09:47 PM
|
Submission Triaged
|
7/24/2024 11:23:53 AM
|
File # Assigned: SF2415
|
7/24/2024 11:23:44 AM
|
Submission request sent to Applicant
|
7/24/2024 7:24:45 AM
|
Submission request sent to Applicant
|
7/24/2024 7:24:36 AM
|
Submission Triaged
|
7/23/2024 5:40:32 PM
|
Submission received from Applicant
|
6/13/2024 3:54:41 PM
|
Submission request sent to Applicant
|
6/13/2024 8:09:41 AM
|
EA Assigned: EA2468
|
6/13/2024 8:09:41 AM
|
Project Created
|