5/29/2024 2:26:08 PM
|
Project Closed
|
5/29/2024 2:26:08 PM
|
Project Approved: 5/29/2024
|
5/21/2024 9:58:09 AM
|
Meeting scheduled: 5/29/2024 10:00:00 AM
|
5/21/2024 8:46:10 AM
|
Meeting scheduled: 5/29/2024 10:00:00 AM
|
5/15/2024 1:54:31 PM
|
Request for Review Comments returned by EPC Parks Department
|
5/15/2024 1:22:30 PM
|
Meeting scheduled: 5/29/2024 10:00:00 AM
|
5/14/2024 10:15:05 AM
|
Project Manager Assigned: Kylie Bagley
|
5/14/2024 9:57:24 AM
|
Request for Assignment email sent for Project Beacon Lite Road Travel Center for review by LaShunda Simpson on behalf of Colorado Springs Public Works
|
5/14/2024 9:57:05 AM
|
Request for Assignment sent to Colorado Springs Public Works
|
5/14/2024 9:56:59 AM
|
Request for Assignment email sent for Project Beacon Lite Road Travel Center for review by Christina Prete on behalf of EPC Stormwater Review
|
5/14/2024 9:56:57 AM
|
Request for Assignment sent to EPC Stormwater Review
|
5/14/2024 9:56:57 AM
|
Request for Assignment email sent for Project Beacon Lite Road Travel Center for review by Gabe Sevigny on behalf of Colorado Springs Planning & Community Development
|
5/14/2024 9:56:54 AM
|
Request for Assignment sent to Colorado Springs Planning & Community Development
|
5/14/2024 9:56:54 AM
|
Request for Assignment email sent for Project Beacon Lite Road Travel Center for review by Kari Parsons on behalf of PCD Project Manager
|
5/14/2024 9:56:52 AM
|
Request for Assignment sent to PCD Project Manager
|
5/14/2024 9:56:49 AM
|
Request for Assignment email sent for Project Beacon Lite Road Travel Center for review by Engineering Manager on behalf of PCD Engineering Division
|
5/14/2024 9:56:47 AM
|
Request for Assignment sent to PCD Engineering Division
|
5/14/2024 9:56:38 AM
|
Fees paid: 5/14/2024 (Receipt: 1009126)
|
5/8/2024 10:31:00 AM
|
Payment Request sent: 5/8/2024
|
5/8/2024 10:30:58 AM
|
EA Assigned: EA2461
|
5/8/2024 10:30:58 AM
|
Project Created
|
5/8/2024 10:30:55 AM
|
Application Triaged/Accepted
|
5/8/2024 10:29:37 AM
|
Application submitted
|