1/21/2025 8:29:04 AM
|
Project Manager Assigned: Stormwater Mikayla Hartford
|
1/7/2025 1:31:41 PM
|
Project Closed
|
1/7/2025 1:31:41 PM
|
Project Approved: 1/7/2025
|
9/9/2024 9:10:49 AM
|
Request for Review Comments returned by PCD Engineering Division
|
9/9/2024 9:04:25 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
8/19/2024 7:17:24 AM
|
Request for Review Comments email sent for Project Paint Brush Hills Filing No. 13E for review by Shannon Mustoe on behalf of EPC Stormwater Review
|
8/19/2024 7:17:23 AM
|
Request for Review Comments email sent for Project Paint Brush Hills Filing No. 13E for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
8/19/2024 7:17:21 AM
|
Request for Review Comments email sent for Project Paint Brush Hills Filing No. 13E for review by Glenn Reese on behalf of EPC Stormwater Review
|
8/19/2024 7:17:19 AM
|
Request for Review Comments email sent for Project Paint Brush Hills Filing No. 13E for review by Christina Prete on behalf of EPC Stormwater Review
|
8/19/2024 7:17:15 AM
|
Request for Review Comments email sent for Project Paint Brush Hills Filing No. 13E for review by Gilbert LaForce on behalf of PCD Engineering Division
|
8/19/2024 7:17:13 AM
|
Request for Review Comments email sent for Project Paint Brush Hills Filing No. 13E for review by Engineering Manager on behalf of PCD Engineering Division
|
8/19/2024 7:16:26 AM
|
Submission Triaged
|
8/15/2024 3:25:09 PM
|
Submission received from Applicant
|
6/20/2024 11:54:14 AM
|
Submission request sent to Applicant
|
6/20/2024 11:53:36 AM
|
Submission request canceled
|
5/8/2024 7:22:17 AM
|
Submission request sent to Applicant
|
5/8/2024 7:21:52 AM
|
Request for Review Comments returned by PCD Engineering Inspections
|
5/6/2024 12:52:01 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
5/6/2024 12:32:05 PM
|
Request for Review Comments returned by PCD Engineering Division
|
4/15/2024 8:13:31 AM
|
Request for Review Comments email sent for Project Paint Brush Hills Filing No. 13E for review by Shannon Mustoe on behalf of EPC Stormwater Review
|
4/15/2024 8:13:29 AM
|
Request for Review Comments email sent for Project Paint Brush Hills Filing No. 13E for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
4/15/2024 8:13:27 AM
|
Request for Review Comments email sent for Project Paint Brush Hills Filing No. 13E for review by Glenn Reese on behalf of EPC Stormwater Review
|
4/15/2024 8:13:26 AM
|
Request for Review Comments email sent for Project Paint Brush Hills Filing No. 13E for review by Christina Prete on behalf of EPC Stormwater Review
|
4/15/2024 8:13:23 AM
|
Request for Review Comments email sent for Project Paint Brush Hills Filing No. 13E for review by Brad Walters on behalf of PCD Engineering Inspections
|
4/15/2024 8:13:21 AM
|
Request for Review Comments email sent for Project Paint Brush Hills Filing No. 13E for review by Gilbert LaForce on behalf of PCD Engineering Division
|
4/15/2024 8:13:20 AM
|
Request for Review Comments email sent for Project Paint Brush Hills Filing No. 13E for review by Engineering Manager on behalf of PCD Engineering Division
|
4/15/2024 8:12:11 AM
|
Submission Triaged
|
4/11/2024 10:57:26 AM
|
Submission received from Applicant
|
4/10/2024 2:12:56 PM
|
Submission request sent to Applicant
|
4/10/2024 2:10:23 PM
|
No Fees
|
4/10/2024 2:10:23 PM
|
File # Assigned: ASB2415
|
4/10/2024 2:10:23 PM
|
Project Manager Assigned: Brad Walters
|
4/10/2024 2:10:23 PM
|
Project Created. Parent Project: Paint Brush Hills Filing No. 13E (SF189)
|