| 5/16/2024 3:23:21 PM | Project Closed | 
                
                    | 5/16/2024 3:23:21 PM | Project Approved: 5/16/2024 | 
                
                    | 5/16/2024 9:43:18 AM | Request for Review Comments returned by Pikes Peak Regional Building Department | 
                
                    | 5/10/2024 10:21:53 AM | Request for Review Comments email sent for Project 3593 Saguaro Cir - CMRS Addition/Modification for review by  on behalf of Pikes Peak Regional Building Department | 
                
                    | 5/10/2024 10:21:24 AM | Submission Triaged | 
                
                    | 5/10/2024 9:40:08 AM | Submission received from Applicant | 
                
                    | 4/26/2024 8:33:03 AM | Submission request sent to Applicant | 
                
                    | 4/22/2024 9:12:20 AM | Request for Review Comments returned by Pikes Peak Regional Building Department | 
                
                    | 4/19/2024 3:48:41 PM | Request for Review Comments returned by PCD Project Manager | 
                
                    | 4/18/2024 7:13:43 AM | Request for Review Comments email sent for Project 3593 Saguaro Cir - CMRS Addition/Modification for review by Rachel Martell on behalf of USAFA Base Planner | 
                
                    | 4/18/2024 7:13:41 AM | Request for Review Comments email sent for Project 3593 Saguaro Cir - CMRS Addition/Modification for review by matthew. fitzsimmons on behalf of USAFA Base Planner | 
                
                    | 4/18/2024 7:13:39 AM | Request for Review Comments email sent for Project 3593 Saguaro Cir - CMRS Addition/Modification for review by Amy Kelley on behalf of USAFA Base Planner | 
                
                    | 4/18/2024 7:13:37 AM | Request for Review Comments email sent for Project 3593 Saguaro Cir - CMRS Addition/Modification for review by  on behalf of USAFA Base Planner | 
                
                    | 4/17/2024 4:39:01 PM | Request for Review Comments returned by Meadow Lake Airport Association | 
                
                    | 4/17/2024 4:11:37 PM | Request for Review Comments email sent for Project 3593 Saguaro Cir - CMRS Addition/Modification for review by Dave Elliott on behalf of Meadow Lake Airport Association | 
                
                    | 4/17/2024 4:11:35 PM | Request for Review Comments email sent for Project 3593 Saguaro Cir - CMRS Addition/Modification for review by Chris Padilla on behalf of Colorado Springs Airport Advisory Commission | 
                
                    | 4/17/2024 4:11:33 PM | Request for Review Comments email sent for Project 3593 Saguaro Cir - CMRS Addition/Modification for review by Keith Klaehn on behalf of Defense Mission Task Force | 
                
                    | 4/17/2024 4:11:31 PM | Request for Review Comments email sent for Project 3593 Saguaro Cir - CMRS Addition/Modification for review by  on behalf of Pikes Peak Regional Building Department | 
                
                    | 4/17/2024 4:11:27 PM | Request for Review Comments email sent for Project 3593 Saguaro Cir - CMRS Addition/Modification for review by Kari Parsons on behalf of PCD Project Manager | 
                
                    | 4/17/2024 4:11:25 PM | Request for Review Comments email sent for Project 3593 Saguaro Cir - CMRS Addition/Modification for review by Gilbert LaForce on behalf of PCD Engineering Division | 
                
                    | 4/17/2024 4:11:23 PM | Request for Review Comments email sent for Project 3593 Saguaro Cir - CMRS Addition/Modification for review by Engineering Manager on behalf of PCD Engineering Division | 
                
                    | 4/17/2024 3:08:39 PM | Project Manager Assigned: Ryan Howser | 
                
                    | 4/12/2024 12:33:46 PM | Fees paid: 4/12/2024 (Receipt: 1008996) | 
                
                    | 3/28/2024 9:23:01 AM | Payment Request sent: 3/28/2024 | 
                
                    | 3/28/2024 9:23:00 AM | File # Assigned: TWR242 | 
                
                    | 3/28/2024 9:22:55 AM | Submission Triaged | 
                
                    | 3/27/2024 1:56:47 PM | Submission received from Applicant | 
                
                    | 3/21/2024 11:33:17 AM | Submission request sent to Applicant | 
                
                    | 3/21/2024 11:31:38 AM | Project Manager Assigned: Christian Haas | 
                
                    | 3/21/2024 11:31:38 AM | Project Created |