5/8/2025 3:36:06 PM
|
Project Closed
|
5/8/2025 3:36:06 PM
|
Project Approved: 5/8/2025
|
4/7/2025 9:54:57 AM
|
Project Ready for Approval requests. Review Comment period is complete.
|
2/13/2025 3:59:33 PM
|
Request for Review Comments returned by PCD Engineering Division
|
2/13/2025 9:57:42 AM
|
Request for Review Comments returned by PCD Project Manager
|
1/31/2025 1:09:38 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Justin Kilgore on behalf of PCD Project Manager
|
1/31/2025 1:09:35 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Gilbert LaForce on behalf of PCD Engineering Division
|
1/31/2025 1:09:34 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Engineering Manager on behalf of PCD Engineering Division
|
1/31/2025 1:08:32 PM
|
Submission Triaged
|
1/31/2025 10:48:54 AM
|
Submission received from Applicant
|
1/22/2025 2:43:52 PM
|
Submission request sent to Applicant
|
1/22/2025 2:43:25 PM
|
Request for Review Comments returned by PCD Project Manager
|
1/22/2025 2:14:33 PM
|
Request for Review Comments returned by PCD Engineering Division
|
1/8/2025 11:38:20 AM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Justin Kilgore on behalf of PCD Project Manager
|
1/8/2025 11:38:17 AM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Gilbert LaForce on behalf of PCD Engineering Division
|
1/8/2025 11:38:16 AM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Engineering Manager on behalf of PCD Engineering Division
|
1/8/2025 11:37:28 AM
|
Submission Triaged
|
1/8/2025 11:19:50 AM
|
Submission received from Applicant
|
11/25/2024 2:16:55 PM
|
Request for Review Comments returned by Upper Black Squirrel Creek GWMD
|
11/7/2024 12:55:50 PM
|
Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
|
11/2/2024 7:23:50 PM
|
Request for Review Comments returned by Colorado Parks and Wildlife
|
10/30/2024 3:54:04 PM
|
Submission request sent to Applicant
|
10/30/2024 3:53:21 PM
|
Request for Review Comments returned by PCD Project Manager
|
10/29/2024 10:29:58 PM
|
Request for Review Comments returned by PCD Engineering Division
|
10/29/2024 9:00:29 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
10/28/2024 9:19:35 PM
|
Request for Review Comments returned by Peyton 23
|
10/28/2024 2:48:41 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
10/21/2024 10:18:45 AM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
10/16/2024 9:11:12 AM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
10/11/2024 2:41:28 PM
|
Request for Review Comments returned by Falcon Fire Protection District
|
10/9/2024 2:51:13 PM
|
Request for Review Comments returned by Parks Advisory Board
|
10/9/2024 2:40:57 PM
|
Request for Review Comments returned by EPC Parks Department
|
10/9/2024 1:49:20 PM
|
Project Manager Assigned: Ashlyn Mathy
|
10/8/2024 3:52:01 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
10/8/2024 3:23:37 PM
|
Request for Review Comments returned by RBD Floodplain
|
10/8/2024 3:13:17 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Greg Land on behalf of Peyton 23
|
10/8/2024 3:13:15 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Derek Burnside on behalf of Peyton 23
|
10/8/2024 3:13:13 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by General Email on behalf of Mountain View Electric Association, Inc.
|
10/8/2024 3:13:11 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Dave Elliott on behalf of Meadow Lake Airport Association
|
10/8/2024 3:13:09 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Trent Harwig on behalf of Falcon Fire Protection District
|
10/8/2024 3:13:07 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Curtis Kauffman on behalf of Falcon Fire Protection District
|
10/8/2024 3:13:05 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by John Paget on behalf of El Paso County Fire Marshall
|
10/8/2024 3:13:03 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Harry Thomas on behalf of El Paso County Conservation Dist
|
10/8/2024 3:13:01 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Oliver Watkins on behalf of El Paso County Conservation Dist
|
10/8/2024 3:12:59 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Katie Miller on behalf of El Paso County Conservation Dist
|
10/8/2024 3:12:57 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Erica Carter on behalf of El Paso County Conservation Dist
|
10/8/2024 3:12:55 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Mariah Hudson on behalf of El Paso County Conservation Dist
|
10/8/2024 3:12:53 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Cassie Olgren on behalf of El Paso County Conservation Dist
|
10/8/2024 3:12:51 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Billy Richard on behalf of El Paso County Conservation Dist
|
10/8/2024 3:12:49 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by LBS Review on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
10/8/2024 3:12:47 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
10/8/2024 3:12:45 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Pamela Davidson on behalf of Central CO Conservation District
|
10/8/2024 3:12:43 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
|
10/8/2024 3:12:40 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Keith Curtis on behalf of RBD Floodplain
|
10/8/2024 3:12:38 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by on behalf of Pikes Peak Regional Building Department
|
10/8/2024 3:12:36 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by george san miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
10/8/2024 3:12:34 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
10/8/2024 3:12:31 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Daniel Delgado on behalf of US Army Corps of Engineers-Pueblo
|
10/8/2024 3:12:29 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Travis Sauder on behalf of Colorado Parks and Wildlife
|
10/8/2024 3:12:27 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Tim Kroening on behalf of Colorado Parks and Wildlife
|
10/8/2024 3:12:25 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Karen Voltura on behalf of Colorado Parks and Wildlife
|
10/8/2024 3:12:23 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Cassidy English on behalf of Colorado Parks and Wildlife
|
10/8/2024 3:12:21 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
|
10/8/2024 3:12:20 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
|
10/8/2024 3:12:18 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Arthur Gonzales on behalf of Colorado Department of Transportation - Pueblo Office
|
10/8/2024 3:12:16 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
|
10/8/2024 3:12:14 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by on behalf of Parks Advisory Board
|
10/8/2024 3:12:12 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
10/8/2024 3:12:10 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Glenn Reese on behalf of EPC Stormwater Review
|
10/8/2024 3:12:08 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Christina Prete on behalf of EPC Stormwater Review
|
10/8/2024 3:12:06 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Jeff Kramer on behalf of EPC Sheriff's Department
|
10/8/2024 3:12:04 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Christopher Gonzalez on behalf of EPC Sheriff's Department
|
10/8/2024 3:12:02 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Andrew Prehm on behalf of EPC Sheriff's Department
|
10/8/2024 3:12:00 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by on behalf of EPC Parks Department
|
10/8/2024 3:11:56 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Kari Parsons on behalf of PCD Project Manager
|
10/8/2024 3:11:54 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Gilbert LaForce on behalf of PCD Engineering Division
|
10/8/2024 3:11:52 PM
|
Request for Review Comments email sent for Project Esteban Rodriguez Rezone RR-5 for review by Engineering Manager on behalf of PCD Engineering Division
|
10/8/2024 10:19:20 AM
|
Fees paid: 10/8/2024 (Receipt: 1009677)
|
10/7/2024 1:11:11 PM
|
Payment Request sent: 10/7/2024
|
10/7/2024 1:11:10 PM
|
File # Assigned: P2412
|
10/7/2024 1:11:00 PM
|
Submission Triaged
|
10/4/2024 4:49:08 PM
|
Submission received from Applicant
|
10/1/2024 11:21:34 AM
|
Submission request sent to Applicant
|
11/29/2023 12:57:56 PM
|
Submission request sent to Applicant
|
11/29/2023 9:26:17 AM
|
Project Manager Assigned: Ryan Howser
|
11/29/2023 9:26:17 AM
|
EA Assigned: EA23109
|
11/29/2023 9:26:17 AM
|
Project Created
|