12/5/2024 2:40:00 PM
|
Project Closed
|
12/5/2024 2:40:00 PM
|
Project Approved: 4/24/2024
|
4/24/2024 10:39:38 PM
|
Request for Review Comments returned by PCD Engineering Division
|
4/10/2024 10:09:29 PM
|
Request for Review Comments email sent for Project Falcon Field Deviations for review by Gilbert LaForce on behalf of PCD Engineering Division
|
4/10/2024 10:09:27 PM
|
Request for Review Comments email sent for Project Falcon Field Deviations for review by Engineering Manager on behalf of PCD Engineering Division
|
4/10/2024 10:08:15 PM
|
Submission Triaged
|
4/10/2024 12:37:08 PM
|
Submission received from Applicant
|
3/27/2024 8:21:39 AM
|
Submission request sent to Applicant
|
3/7/2024 11:35:36 PM
|
Request for Review Comments returned by PCD Engineering Division
|
2/22/2024 9:21:59 AM
|
Request for Review Comments returned by PCD Project Manager
|
2/22/2024 7:26:48 AM
|
Project Manager Assigned: Daniel Torres
|
2/22/2024 7:26:20 AM
|
Request for Review Comments email sent for Project Falcon Field Deviations for review by Gilbert LaForce on behalf of PCD Engineering Division
|
2/22/2024 7:26:18 AM
|
Request for Review Comments email sent for Project Falcon Field Deviations for review by Engineering Manager on behalf of PCD Engineering Division
|
2/22/2024 7:24:00 AM
|
Submission Triaged
|
2/21/2024 4:19:00 PM
|
Submission received from Applicant
|
12/20/2023 2:36:10 PM
|
Submission request sent to Applicant
|
12/19/2023 5:11:26 PM
|
Request for Review Comments returned by PCD Engineering Division
|
11/28/2023 10:17:20 AM
|
Request for Review Comments email sent for Project Falcon Field Deviations for review by on behalf of EPC Public Works, County Engineer
|
11/28/2023 10:17:19 AM
|
Request for Review Comments email sent for Project Falcon Field Deviations for review by on behalf of EPC Public Works, County Engineer
|
11/28/2023 10:17:16 AM
|
Request for Review Comments email sent for Project Falcon Field Deviations for review by Lupe Packman on behalf of PCD Engineering Division
|
11/28/2023 10:17:14 AM
|
Request for Review Comments email sent for Project Falcon Field Deviations for review by Gilbert LaForce on behalf of PCD Engineering Division
|
11/28/2023 10:17:12 AM
|
Request for Review Comments email sent for Project Falcon Field Deviations for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
11/28/2023 10:17:10 AM
|
Request for Review Comments email sent for Project Falcon Field Deviations for review by Edward Schoenheit on behalf of PCD Engineering Division
|
11/28/2023 10:17:08 AM
|
Request for Review Comments email sent for Project Falcon Field Deviations for review by Engineering Manager on behalf of PCD Engineering Division
|
11/28/2023 10:17:06 AM
|
Request for Review Comments email sent for Project Falcon Field Deviations for review by Charlene Durham on behalf of PCD Engineering Division
|
11/28/2023 10:17:04 AM
|
Request for Review Comments email sent for Project Falcon Field Deviations for review by Carlos Hernandez Martinez on behalf of PCD Engineering Division
|
11/28/2023 9:58:43 AM
|
Fees paid: 11/28/2023 (Receipt: 1008559)
|
11/28/2023 7:09:52 AM
|
Payment Request sent: 11/28/2023
|
11/28/2023 7:09:52 AM
|
File # Assigned: DEV238
|
11/28/2023 7:09:42 AM
|
Submission Triaged
|
11/27/2023 8:13:49 PM
|
Submission received from Applicant
|
11/15/2023 3:14:19 PM
|
Submission request sent to Applicant
|
11/15/2023 3:12:32 PM
|
Project Manager Assigned: Ryan Howser
|
11/15/2023 3:12:32 PM
|
EA Assigned: EA20142
|
11/15/2023 3:12:32 PM
|
Project Created
|