| 7/29/2025 2:24:49 PM | Request for Review Comments returned by PCD Engineering Inspections | 
                
                    | 7/23/2025 8:13:40 AM | Submission request sent to Applicant | 
                
                    | 7/23/2025 8:09:28 AM | Request for Review Comments returned by EPC Stormwater Review | 
                
                    | 7/22/2025 2:25:27 PM | Request for Review Comments returned by PCD Engineering Division | 
                
                    | 7/21/2025 9:51:48 AM | Request for Review Comments returned by EPC DPW Asset Management | 
                
                    | 6/30/2025 10:30:29 AM | Request for Review Comments email sent for Project Retreat at Timber Ridge Filing No. 2 for review by Zachary Jannusch on behalf of EPC Stormwater Review | 
                
                    | 6/30/2025 10:30:28 AM | Request for Review Comments email sent for Project Retreat at Timber Ridge Filing No. 2 for review by Mikayla Hartford on behalf of EPC Stormwater Review | 
                
                    | 6/30/2025 10:30:27 AM | Request for Review Comments email sent for Project Retreat at Timber Ridge Filing No. 2 for review by Glenn Reese on behalf of EPC Stormwater Review | 
                
                    | 6/30/2025 10:30:26 AM | Request for Review Comments email sent for Project Retreat at Timber Ridge Filing No. 2 for review by Christina Prete on behalf of EPC Stormwater Review | 
                
                    | 6/30/2025 10:30:24 AM | Request for Review Comments email sent for Project Retreat at Timber Ridge Filing No. 2 for review by  on behalf of EPC DPW Asset Management | 
                
                    | 6/30/2025 10:30:23 AM | Request for Review Comments email sent for Project Retreat at Timber Ridge Filing No. 2 for review by Brad Walters on behalf of PCD Engineering Inspections | 
                
                    | 6/30/2025 10:30:22 AM | Request for Review Comments email sent for Project Retreat at Timber Ridge Filing No. 2 for review by Gilbert LaForce on behalf of PCD Engineering Division | 
                
                    | 6/30/2025 10:30:21 AM | Request for Review Comments email sent for Project Retreat at Timber Ridge Filing No. 2 for review by Engineering Manager on behalf of PCD Engineering Division | 
                
                    | 6/30/2025 10:28:19 AM | Submission Triaged | 
                
                    | 6/27/2025 7:43:31 AM | Submission received from Applicant | 
                
                    | 1/16/2025 1:33:52 PM | Project Manager Assigned: Stormwater Mikayla Hartford | 
                
                    | 12/12/2024 3:15:57 PM | Submission request sent to Applicant | 
                
                    | 1/2/2024 8:45:11 AM | Request for Review Comments returned by PCD Engineering Inspections | 
                
                    | 1/2/2024 8:25:48 AM | Request for Review Comments returned by EPC Stormwater Review | 
                
                    | 12/28/2023 12:29:29 PM | Request for Review Comments returned by PCD Engineering Division | 
                
                    | 12/6/2023 2:37:58 PM | Request for Review Comments email sent for Project Retreat at Timber Ridge Filing No. 2 for review by Mikayla Hartford on behalf of EPC Stormwater Review | 
                
                    | 12/6/2023 2:37:57 PM | Request for Review Comments email sent for Project Retreat at Timber Ridge Filing No. 2 for review by Glenn Reese on behalf of EPC Stormwater Review | 
                
                    | 12/6/2023 2:37:54 PM | Request for Review Comments email sent for Project Retreat at Timber Ridge Filing No. 2 for review by Christina Prete on behalf of EPC Stormwater Review | 
                
                    | 12/6/2023 2:37:51 PM | Request for Review Comments email sent for Project Retreat at Timber Ridge Filing No. 2 for review by Brad Walters on behalf of PCD Engineering Inspections | 
                
                    | 12/6/2023 2:37:49 PM | Request for Review Comments email sent for Project Retreat at Timber Ridge Filing No. 2 for review by Lupe Packman on behalf of PCD Engineering Division | 
                
                    | 12/6/2023 2:37:47 PM | Request for Review Comments email sent for Project Retreat at Timber Ridge Filing No. 2 for review by Gilbert LaForce on behalf of PCD Engineering Division | 
                
                    | 12/6/2023 2:37:45 PM | Request for Review Comments email sent for Project Retreat at Timber Ridge Filing No. 2 for review by Elizabeth Nijkamp on behalf of PCD Engineering Division | 
                
                    | 12/6/2023 2:37:43 PM | Request for Review Comments email sent for Project Retreat at Timber Ridge Filing No. 2 for review by Edward Schoenheit on behalf of PCD Engineering Division | 
                
                    | 12/6/2023 2:37:41 PM | Request for Review Comments email sent for Project Retreat at Timber Ridge Filing No. 2 for review by Engineering Manager on behalf of PCD Engineering Division | 
                
                    | 12/6/2023 2:37:39 PM | Request for Review Comments email sent for Project Retreat at Timber Ridge Filing No. 2 for review by Charlene Durham on behalf of PCD Engineering Division | 
                
                    | 12/6/2023 2:37:37 PM | Request for Review Comments email sent for Project Retreat at Timber Ridge Filing No. 2 for review by Carlos Hernandez Martinez on behalf of PCD Engineering Division | 
                
                    | 12/6/2023 2:36:17 PM | Submission Triaged | 
                
                    | 12/6/2023 12:56:25 PM | Submission received from Applicant | 
                
                    | 11/7/2023 10:57:28 AM | Submission request sent to Applicant | 
                
                    | 11/7/2023 10:54:46 AM | No Fees | 
                
                    | 11/7/2023 10:54:46 AM | File # Assigned: ASB2318 | 
                
                    | 11/7/2023 10:54:45 AM | Project Manager Assigned: Brad Walters | 
                
                    | 11/7/2023 10:54:45 AM | Project Created.  Parent Project: Retreat at TimberRidge Filing No. 2 (SF2121) |