9/20/2024 8:40:54 AM
|
Project Closed
|
9/20/2024 8:40:54 AM
|
Project Cancelled: 9/20/2024
|
9/20/2024 8:40:22 AM
|
Submission request canceled
|
4/5/2024 8:36:15 AM
|
Submission request sent to Applicant
|
4/4/2024 9:55:52 PM
|
Request for Review Comments returned by PCD Engineering Division
|
4/4/2024 5:11:49 PM
|
Request for Review Comments returned by PCD Project Manager
|
4/4/2024 4:54:45 PM
|
Request for Review Comments email resent for Project Flying Horse North Phase 2 PUDSP for review by Kari Parsons on behalf of PCD Project Manager
|
4/4/2024 4:53:00 PM
|
Request for Review Comments returned by PCD Project Manager
|
4/3/2024 2:51:15 PM
|
Request for Review Comments returned by Colorado Geological Survey
|
3/29/2024 9:55:06 AM
|
Submission Triaged
|
3/29/2024 8:51:41 AM
|
Submission received from Applicant
|
3/28/2024 11:38:05 AM
|
Submission request sent to Applicant
|
3/27/2024 1:27:51 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
3/27/2024 10:32:29 AM
|
Request for Review Comments returned by EPC Environmental Services
|
3/25/2024 10:02:07 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
3/21/2024 5:13:26 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Vicki Wood on behalf of Lewis Palmer 38
|
3/21/2024 5:13:24 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Melissa Andrews on behalf of Lewis Palmer 38
|
3/21/2024 5:13:23 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Brett Ridgway on behalf of Lewis Palmer 38
|
3/21/2024 5:13:20 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Santiago Tijerina on behalf of Black Hills Energy-Aquila
|
3/21/2024 5:13:19 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Bob Swatek on behalf of Black Hills Energy-Aquila
|
3/21/2024 5:13:16 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Adam Magoon on behalf of Black Hills Energy-Aquila
|
3/21/2024 5:13:14 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by on behalf of Pikes Peak Regional Building Department
|
3/21/2024 5:13:12 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
3/21/2024 5:13:10 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
|
3/21/2024 5:13:08 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by george san miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
3/21/2024 5:13:06 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
3/21/2024 5:13:04 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Joseph Martinez on behalf of US Army Corps of Engineers-Pueblo
|
3/21/2024 5:13:02 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
3/21/2024 5:13:00 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Kathy Andrew on behalf of EPC Environmental Services
|
3/21/2024 5:12:56 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Kari Parsons on behalf of PCD Project Manager
|
3/21/2024 5:12:54 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Gilbert LaForce on behalf of PCD Engineering Division
|
3/21/2024 5:12:51 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Engineering Manager on behalf of PCD Engineering Division
|
3/21/2024 5:08:39 PM
|
Submission Triaged
|
3/21/2024 3:59:36 PM
|
Submission received from Applicant
|
3/13/2024 3:04:51 PM
|
Submission request sent to Applicant
|
2/22/2024 1:14:14 PM
|
Request for Review Comments returned by EPC Parks Department
|
2/20/2024 11:59:59 AM
|
Submission request sent to Applicant
|
2/20/2024 11:59:25 AM
|
Submission request canceled
|
2/20/2024 7:29:54 AM
|
Request for Review Comments returned by PCD Engineering Division
|
2/14/2024 4:13:47 PM
|
Request for Review Comments returned by PCD Project Manager
|
2/13/2024 10:41:40 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
2/12/2024 8:21:43 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
1/31/2024 8:59:08 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
1/29/2024 7:44:11 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
1/26/2024 8:26:08 PM
|
Request for Review Comments returned by EPC Health Department
|
1/26/2024 4:22:43 PM
|
Request for Review Comments returned by Black Forest Fire Protection District
|
1/25/2024 3:13:26 PM
|
Request for Review Comments returned by RBD Floodplain
|
1/24/2024 5:33:13 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by General Email on behalf of Mountain View Electric Association, Inc.
|
1/24/2024 5:33:11 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by PJ Langmaid on behalf of Black Forest Fire Protection District
|
1/24/2024 5:33:09 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Black Forest Fire Chief on behalf of Black Forest Fire Protection District
|
1/24/2024 5:33:07 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Keith Curtis on behalf of RBD Floodplain
|
1/24/2024 5:33:05 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by on behalf of Pikes Peak Regional Building Department
|
1/24/2024 5:33:03 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
1/24/2024 5:33:01 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
|
1/24/2024 5:32:59 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
1/24/2024 5:32:57 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Glenn Reese on behalf of EPC Stormwater Review
|
1/24/2024 5:32:55 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Christina Prete on behalf of EPC Stormwater Review
|
1/24/2024 5:32:53 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by on behalf of EPC Parks Department
|
1/24/2024 5:32:48 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Gilbert LaForce on behalf of PCD Engineering Division
|
1/24/2024 5:32:45 PM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Engineering Manager on behalf of PCD Engineering Division
|
1/24/2024 5:17:38 PM
|
Submission request sent to Applicant
|
1/24/2024 5:17:06 PM
|
Submission Triaged
|
1/24/2024 4:57:48 PM
|
Submission received from Applicant
|
1/9/2024 12:23:09 PM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
1/2/2024 2:44:04 PM
|
Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
|
12/28/2023 9:00:00 AM
|
Submission request sent to Applicant
|
12/20/2023 2:25:11 PM
|
Request for Review Comments returned by Colorado Parks and Wildlife
|
12/14/2023 11:19:00 AM
|
Request for Review Comments returned by Parks Advisory Board
|
12/8/2023 5:02:16 PM
|
Request for Review Comments returned by PCD Engineering Division
|
12/7/2023 2:24:28 PM
|
Request for Review Comments returned by EPC Parks Department
|
12/6/2023 4:20:57 PM
|
Request for Review Comments returned by PCD Project Manager
|
12/6/2023 2:37:10 PM
|
Request for Review Comments returned by Black Forest Fire Protection District
|
12/6/2023 10:07:32 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
12/5/2023 2:00:27 PM
|
Request for Review Comments returned by Colorado Geological Survey
|
12/5/2023 12:52:41 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
12/5/2023 9:13:00 AM
|
Request for Review Comments returned by Black Forest Land Use Committee
|
12/5/2023 8:07:47 AM
|
Request for Review Comments returned by Colorado Springs Public Works
|
11/30/2023 2:58:45 PM
|
Request for Review Comments returned by EPC Environmental Services
|
11/30/2023 10:50:57 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
11/29/2023 1:54:02 PM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
11/29/2023 12:12:20 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
11/28/2023 3:33:54 PM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
11/27/2023 5:08:43 PM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
11/27/2023 8:53:02 AM
|
Request for Review Comments returned by Academy SD 20 Building Fund
|
11/21/2023 10:14:43 AM
|
Request for Review Comments returned by Colorado Department of Public Health and Environment
|
11/20/2023 1:29:10 PM
|
Request for Review Comments returned by County Attorney - Water
|
11/20/2023 7:52:27 AM
|
Request for Review Comments returned by Colorado Springs Planning & Community Development
|
11/16/2023 9:11:23 AM
|
Request for Review Comments returned by Cherokee Metro Dist
|
11/14/2023 1:29:01 PM
|
Request for Review Comments returned by Colorado State Forest Service
|
11/14/2023 10:33:51 AM
|
Request for Review Comments returned by RBD Floodplain
|
11/14/2023 10:10:48 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Bob Mooney on behalf of Northern EPC Coalition of Community Organizations, Inc. (NEPCO)(to also include the TLLU areas)
|
11/14/2023 10:10:44 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by General Email on behalf of Mountain View Electric Association, Inc.
|
11/14/2023 10:10:40 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Vicki Wood on behalf of Lewis Palmer 38
|
11/14/2023 10:10:38 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Chris Coulter on behalf of Lewis Palmer 38
|
11/14/2023 10:10:34 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Mariah Hudson on behalf of El Paso County Conservation Dist
|
11/14/2023 10:10:31 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Dave Munger on behalf of Council of Neighborhood Organizations (CONO)
|
11/14/2023 10:10:28 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Tim Thomas on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
11/14/2023 10:10:25 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Paul Clifton on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
11/14/2023 10:10:23 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by LBS Review on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
11/14/2023 10:10:19 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Gary Rust on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
11/14/2023 10:10:17 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Caelen Went on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
11/14/2023 10:10:14 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
11/14/2023 10:10:11 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Zaker Alazzeh on behalf of Colorado Springs Public Works
|
11/14/2023 10:10:09 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Rae Carlson on behalf of Colorado Springs Public Works
|
11/14/2023 10:10:06 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Patrick Morris on behalf of Colorado Springs Public Works
|
11/14/2023 10:10:04 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by LaShunda Simpson on behalf of Colorado Springs Public Works
|
11/14/2023 10:10:02 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Jonathan Scherer on behalf of Colorado Springs Public Works
|
11/14/2023 10:09:59 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Joel Metzker on behalf of Colorado Springs Public Works
|
11/14/2023 10:09:57 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Joel Dagnillo on behalf of Colorado Springs Public Works
|
11/14/2023 10:09:55 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Jeff Bailey on behalf of Colorado Springs Public Works
|
11/14/2023 10:09:53 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Erin Powers on behalf of Colorado Springs Public Works
|
11/14/2023 10:09:50 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by General Email on behalf of Colorado Springs Public Works
|
11/14/2023 10:09:48 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Dana Davison on behalf of Colorado Springs Public Works
|
11/14/2023 10:09:46 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Brian Shevock on behalf of Colorado Springs Public Works
|
11/14/2023 10:09:41 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Gabe Sevigny on behalf of Colorado Springs Planning & Community Development
|
11/14/2023 10:09:32 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Tyler Drennan on behalf of Cherokee Metro Dist
|
11/14/2023 10:09:22 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Kevin Brown on behalf of Cherokee Metro Dist
|
11/14/2023 10:09:20 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Jeff Munger on behalf of Cherokee Metro Dist
|
11/14/2023 10:09:17 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by CONNIE HUGHES on behalf of Cherokee Metro Dist
|
11/14/2023 10:09:15 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Santiago Tijerina on behalf of Black Hills Energy-Aquila
|
11/14/2023 10:09:12 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Bob Swatek on behalf of Black Hills Energy-Aquila
|
11/14/2023 10:09:10 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Adam Magoon on behalf of Black Hills Energy-Aquila
|
11/14/2023 10:09:07 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Cheryl Pixley on behalf of Black Forest Trails Association
|
11/14/2023 10:09:05 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Terry Stokka on behalf of Black Forest Land Use Committee
|
11/14/2023 10:09:03 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Terry Stokka on behalf of Black Forest Land Use Committee
|
11/14/2023 10:09:00 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by PJ Langmaid on behalf of Black Forest Fire Protection District
|
11/14/2023 10:08:58 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Black Forest Fire Chief on behalf of Black Forest Fire Protection District
|
11/14/2023 10:08:56 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Tom Gregory on behalf of Academy SD 20 Building Fund
|
11/14/2023 10:08:53 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Donald Smith on behalf of Academy SD 20 Building Fund
|
11/14/2023 10:08:51 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Becky Allan on behalf of Academy SD 20 Building Fund
|
11/14/2023 10:08:42 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Keith Curtis on behalf of RBD Floodplain
|
11/14/2023 10:08:40 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by on behalf of Pikes Peak Regional Building Department
|
11/14/2023 10:08:38 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
11/14/2023 10:08:35 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
|
11/14/2023 10:08:33 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Jennifer DeWoody on behalf of US Forest Service, Pikes Peak Ranger District
|
11/14/2023 10:08:30 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by george san miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
11/14/2023 10:08:27 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
11/14/2023 10:08:25 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Joseph Martinez on behalf of US Army Corps of Engineers-Pueblo
|
11/14/2023 10:08:19 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Andy Schlosberg on behalf of Colorado State Forest Service
|
11/14/2023 10:08:17 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Tyson Floersheim on behalf of Colorado Parks and Wildlife
|
11/14/2023 10:08:14 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Travis Sauder on behalf of Colorado Parks and Wildlife
|
11/14/2023 10:08:12 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Tim Kroening on behalf of Colorado Parks and Wildlife
|
11/14/2023 10:08:09 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Sarah Watson on behalf of Colorado Parks and Wildlife
|
11/14/2023 10:08:07 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Philip Gurule on behalf of Colorado Parks and Wildlife
|
11/14/2023 10:08:04 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Karen Voltura on behalf of Colorado Parks and Wildlife
|
11/14/2023 10:08:02 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Corey Adler on behalf of Colorado Parks and Wildlife
|
11/14/2023 10:08:00 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Cassidy English on behalf of Colorado Parks and Wildlife
|
11/14/2023 10:07:58 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Drew Vrbenec on behalf of Colorado Parks and Wildlife
|
11/14/2023 10:07:55 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Aaron Berscheid on behalf of Colorado Parks and Wildlife
|
11/14/2023 10:07:52 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
11/14/2023 10:07:49 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Melissa Van Der Poel on behalf of Colorado Division of Water Resources
|
11/14/2023 10:07:47 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
11/14/2023 10:07:44 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
|
11/14/2023 10:07:42 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
|
11/14/2023 10:07:39 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Arthur Gonzales on behalf of Colorado Department of Transportation - Pueblo Office
|
11/14/2023 10:07:37 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
|
11/14/2023 10:07:34 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by on behalf of Colorado Department of Public Health and Environment
|
11/14/2023 10:07:31 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by on behalf of Parks Advisory Board
|
11/14/2023 10:07:27 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
11/14/2023 10:07:25 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Glenn Reese on behalf of EPC Stormwater Review
|
11/14/2023 10:07:23 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Christina Prete on behalf of EPC Stormwater Review
|
11/14/2023 10:07:20 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Jeff Kramer on behalf of EPC Sheriff's Department
|
11/14/2023 10:07:18 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Jane Fromme on behalf of EPC Sheriff's Department
|
11/14/2023 10:07:16 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Christopher Gonzalez on behalf of EPC Sheriff's Department
|
11/14/2023 10:07:13 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Andrew Prehm on behalf of EPC Sheriff's Department
|
11/14/2023 10:07:11 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by on behalf of EPC Public Works, County Engineer
|
11/14/2023 10:07:09 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by on behalf of EPC Public Works, County Engineer
|
11/14/2023 10:07:06 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by on behalf of EPC Parks Department
|
11/14/2023 10:07:03 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Mike McCarthy on behalf of EPC Health Department
|
11/14/2023 10:07:01 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Catherine McGarvy on behalf of EPC Health Department
|
11/14/2023 10:06:59 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by HEAEH LandUse on behalf of EPC Health Department
|
11/14/2023 10:06:55 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Kathy Andrew on behalf of EPC Environmental Services
|
11/14/2023 10:06:53 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Lori Seago on behalf of County Attorney - Water
|
11/14/2023 10:06:51 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by April Willie on behalf of County Attorney - Water
|
11/14/2023 10:06:47 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Lori Seago on behalf of County Attorney - Development Review
|
11/14/2023 10:06:44 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by April Willie on behalf of County Attorney - Development Review
|
11/14/2023 10:06:40 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Lupe Packman on behalf of PCD Engineering Division
|
11/14/2023 10:06:38 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Gilbert LaForce on behalf of PCD Engineering Division
|
11/14/2023 10:06:33 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
11/14/2023 10:06:28 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Edward Schoenheit on behalf of PCD Engineering Division
|
11/14/2023 10:06:21 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Engineering Manager on behalf of PCD Engineering Division
|
11/14/2023 10:06:19 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Charlene Durham on behalf of PCD Engineering Division
|
11/14/2023 10:06:15 AM
|
Request for Review Comments email sent for Project Flying Horse North Phase 2 PUDSP for review by Carlos Hernandez Martinez on behalf of PCD Engineering Division
|
11/9/2023 4:14:44 PM
|
Fees paid: 11/9/2023 (Receipt: 1008505)
|
11/8/2023 4:48:19 PM
|
Payment Request sent: 11/8/2023
|
11/8/2023 4:48:18 PM
|
File # Assigned: PUDSP234
|
11/8/2023 4:48:09 PM
|
Submission Triaged
|
11/8/2023 4:35:07 PM
|
Submission received from Applicant
|
11/2/2023 3:49:11 PM
|
Submission request sent to Applicant
|
10/18/2023 3:20:31 PM
|
Submission request sent to Applicant
|
10/11/2023 12:41:31 PM
|
Project Manager Assigned: Ryan Howser
|
10/11/2023 12:41:31 PM
|
Project Created
|