4/4/2025 9:51:32 AM
|
Project Closed
|
4/4/2025 9:51:32 AM
|
Project Approved: 4/4/2025
|
3/14/2025 8:47:23 AM
|
Project Ready for Approval requests. Review Comment period is complete.
|
3/4/2025 10:59:58 AM
|
Request for Review Comments returned by County Attorney - Water
|
2/20/2025 3:25:28 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Lori Seago on behalf of County Attorney - Water
|
2/20/2025 3:25:27 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Erika Keech on behalf of County Attorney - Water
|
2/20/2025 3:25:26 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by April Willie on behalf of County Attorney - Water
|
2/20/2025 3:24:46 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Lori Seago on behalf of County Attorney - Water
|
2/20/2025 3:24:45 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Erika Keech on behalf of County Attorney - Water
|
2/20/2025 3:24:44 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by April Willie on behalf of County Attorney - Water
|
2/20/2025 3:24:00 PM
|
Submission Triaged
|
2/20/2025 3:11:59 PM
|
Submission received from Applicant
|
2/19/2025 2:27:21 PM
|
Submission request sent to Applicant
|
2/19/2025 2:27:06 PM
|
Submission Triaged
|
2/19/2025 10:38:31 AM
|
Submission received from Applicant
|
2/19/2025 7:23:57 AM
|
Submission request sent to Applicant
|
2/18/2025 10:56:55 AM
|
Request for Review Comments returned by County Attorney - Water
|
2/5/2025 3:48:30 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Lori Seago on behalf of County Attorney - Water
|
2/5/2025 3:48:29 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Erika Keech on behalf of County Attorney - Water
|
2/5/2025 3:48:28 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by April Willie on behalf of County Attorney - Water
|
2/5/2025 9:29:51 AM
|
Fees paid: 2/5/2025 (Receipt: 1010129)
|
2/5/2025 8:57:18 AM
|
Payment Request sent: 2/5/2025
|
2/5/2025 7:10:55 AM
|
Submission Triaged
|
2/4/2025 3:37:08 PM
|
Submission received from Applicant
|
2/4/2025 3:26:51 PM
|
Submission request sent to Applicant
|
2/4/2025 8:36:08 AM
|
Project reopened for Review Comments
|
1/16/2025 3:26:53 PM
|
Project Ready for Approval requests. Review Comment period is complete.
|
1/16/2025 3:19:53 PM
|
Request for Review Comments returned by PCD Project Manager
|
1/16/2025 3:19:08 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Justin Kilgore on behalf of PCD Project Manager
|
1/16/2025 3:18:30 PM
|
Submission Triaged
|
1/16/2025 3:15:33 PM
|
Submission received from Applicant
|
1/15/2025 4:49:38 PM
|
Submission request sent to Applicant
|
1/15/2025 1:51:45 PM
|
Request for Review Comments returned by County Attorney - Water
|
1/9/2025 8:49:25 AM
|
Request for Review Comments returned by PCD Project Manager
|
1/7/2025 10:35:06 AM
|
Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
|
1/3/2025 11:13:38 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District
|
1/3/2025 11:13:37 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Jonathan Bradley on behalf of Tri-Lakes-Monument Fire Protection District
|
12/26/2024 9:50:18 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Lori Seago on behalf of County Attorney - Water
|
12/26/2024 9:50:17 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Erika Keech on behalf of County Attorney - Water
|
12/26/2024 9:50:15 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by April Willie on behalf of County Attorney - Water
|
12/26/2024 9:50:11 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Justin Kilgore on behalf of PCD Project Manager
|
12/26/2024 9:49:16 AM
|
Submission Triaged
|
12/26/2024 9:29:49 AM
|
Submission received from Applicant
|
12/26/2024 8:59:20 AM
|
Submission request sent to Applicant
|
12/23/2024 2:24:22 PM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
12/18/2024 4:49:00 PM
|
Request for Review Comments returned by PCD Project Manager
|
12/11/2024 2:30:37 PM
|
Request for Review Comments returned by County Attorney - Water
|
12/4/2024 1:24:20 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Melissa Van Der Poel on behalf of Colorado Division of Water Resources
|
12/4/2024 1:24:18 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
12/4/2024 1:24:15 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Lori Seago on behalf of County Attorney - Water
|
12/4/2024 1:24:13 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Erika Keech on behalf of County Attorney - Water
|
12/4/2024 1:24:11 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by April Willie on behalf of County Attorney - Water
|
12/4/2024 1:24:07 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Justin Kilgore on behalf of PCD Project Manager
|
12/4/2024 1:22:09 PM
|
Submission Triaged
|
12/4/2024 1:12:51 PM
|
Submission received from Applicant
|
12/3/2024 4:20:06 PM
|
Submission request sent to Applicant
|
12/3/2024 11:01:37 AM
|
Project Manager Assigned: Ryan Howser
|
10/30/2024 1:39:50 PM
|
Submission request sent to Applicant
|
10/9/2024 1:38:42 PM
|
Submission request sent to Applicant
|
10/8/2024 10:36:55 AM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
10/1/2024 3:07:02 PM
|
Request for Review Comments returned by PCD Project Manager
|
9/30/2024 1:01:53 PM
|
Request for Review Comments returned by Colorado Geological Survey
|
9/26/2024 2:26:04 PM
|
Submission request sent to Applicant
|
9/26/2024 2:19:56 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Lori Seago on behalf of County Attorney - Water
|
9/26/2024 2:19:54 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Erika Keech on behalf of County Attorney - Water
|
9/26/2024 2:19:52 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by April Willie on behalf of County Attorney - Water
|
9/25/2024 1:50:51 PM
|
Request for Review Comments returned by PCD Engineering Division
|
9/18/2024 12:05:35 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
9/18/2024 12:05:33 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Kari Parsons on behalf of PCD Project Manager
|
9/18/2024 12:05:29 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Engineering Manager on behalf of PCD Engineering Division
|
9/18/2024 12:05:24 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Gilbert LaForce on behalf of PCD Engineering Division
|
9/17/2024 4:59:47 PM
|
Submission Triaged
|
9/17/2024 3:54:25 PM
|
Submission received from Applicant
|
9/12/2024 10:13:08 AM
|
Submission request sent to Applicant
|
9/12/2024 9:33:49 AM
|
Submission request sent to Applicant
|
9/12/2024 9:32:15 AM
|
Submission Triaged
|
9/12/2024 9:31:11 AM
|
Submission received from Applicant
|
9/12/2024 9:26:16 AM
|
Submission request sent to Applicant
|
9/10/2024 7:09:26 PM
|
Submission request sent to Applicant
|
9/10/2024 6:35:53 PM
|
Request for Review Comments returned by PCD Engineering Division
|
9/10/2024 5:43:04 PM
|
Request for Review Comments returned by PCD Project Manager
|
9/10/2024 5:40:55 PM
|
Request for Review Comments email resent for Project Kettle Creek Estates Filing No. 2 for review by Kari Parsons on behalf of PCD Project Manager
|
9/6/2024 1:34:16 PM
|
Request for Review Comments returned by Colorado Geological Survey
|
9/3/2024 1:31:20 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
8/28/2024 2:06:04 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
8/28/2024 8:42:13 AM
|
Request for Review Comments returned by Donald Wescott Fire Protection District
|
8/27/2024 1:22:10 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Jonathan Bradley on behalf of Donald Wescott Fire Protection District
|
8/27/2024 1:22:08 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by LBS Review on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
8/27/2024 1:22:06 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
8/27/2024 1:22:04 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by on behalf of Pikes Peak Regional Building Department
|
8/27/2024 1:22:02 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by george san miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
8/27/2024 1:22:00 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
8/27/2024 1:21:58 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
8/27/2024 1:21:56 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Melissa Van Der Poel on behalf of Colorado Division of Water Resources
|
8/27/2024 1:21:54 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
8/27/2024 1:21:50 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
8/27/2024 1:21:48 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Glenn Reese on behalf of EPC Stormwater Review
|
8/27/2024 1:21:47 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Christina Prete on behalf of EPC Stormwater Review
|
8/27/2024 1:21:44 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Jeff Kramer on behalf of EPC Sheriff's Department
|
8/27/2024 1:21:43 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Christopher Gonzalez on behalf of EPC Sheriff's Department
|
8/27/2024 1:21:41 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Andrew Prehm on behalf of EPC Sheriff's Department
|
8/27/2024 1:21:37 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Kari Parsons on behalf of PCD Project Manager
|
8/27/2024 1:21:33 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Gilbert LaForce on behalf of PCD Engineering Division
|
8/27/2024 1:21:29 PM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Engineering Manager on behalf of PCD Engineering Division
|
8/27/2024 1:18:18 PM
|
Submission request canceled
|
8/27/2024 12:59:13 PM
|
Submission request sent to Applicant
|
8/27/2024 9:15:39 AM
|
Submission Triaged
|
8/27/2024 9:12:39 AM
|
Submission received from Applicant
|
8/2/2024 5:57:41 PM
|
Request for Review Comments returned by EPC Health Department
|
7/29/2024 3:38:46 PM
|
Request for Review Comments returned by Donald Wescott Fire Protection District
|
7/25/2024 12:00:43 PM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
7/24/2024 9:18:50 AM
|
Submission request sent to Applicant
|
7/24/2024 9:13:29 AM
|
Request for Review Comments returned by PCD Project Manager
|
7/24/2024 8:48:35 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Kari Parsons on behalf of PCD Project Manager
|
7/24/2024 8:38:42 AM
|
Request for Review Comments email resent for Project Kettle Creek Estates Filing No. 2 for review by Kari Parsons on behalf of PCD Project Manager
|
7/23/2024 10:27:16 AM
|
Submission request sent to Applicant
|
7/17/2024 5:46:41 PM
|
Request for Review Comments returned by PCD Engineering Division
|
7/17/2024 2:13:08 PM
|
Request for Review Comments returned by PCD Administrative Notice
|
7/17/2024 1:08:56 PM
|
Request for Review Comments returned by PCD Project Manager
|
7/17/2024 12:00:00 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
7/16/2024 5:25:47 PM
|
Request for Review Comments returned by Colorado Geological Survey
|
7/16/2024 2:15:26 PM
|
Request for Review Comments returned by Colorado Parks and Wildlife
|
7/15/2024 3:40:59 PM
|
Request for Review Comments returned by EPC Parks Department
|
7/15/2024 3:15:48 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
7/10/2024 1:39:33 PM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
7/3/2024 9:57:46 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
6/28/2024 7:35:19 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
6/27/2024 9:05:36 AM
|
Request for Review Comments returned by Academy SD 20 Building Fund
|
6/27/2024 8:33:54 AM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
6/26/2024 12:45:28 PM
|
Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
|
6/26/2024 9:00:40 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by General Email on behalf of Mountain View Electric Association, Inc.
|
6/26/2024 9:00:38 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Oliver Watkins on behalf of El Paso County Conservation Dist
|
6/26/2024 9:00:36 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Katie Miller on behalf of El Paso County Conservation Dist
|
6/26/2024 9:00:34 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Mariah Hudson on behalf of El Paso County Conservation Dist
|
6/26/2024 9:00:32 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Scott Ridings on behalf of Donald Wescott Fire Protection District
|
6/26/2024 9:00:30 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by LBS Review on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
6/26/2024 9:00:28 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
6/26/2024 9:00:26 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Tom Gregory on behalf of Academy SD 20 Building Fund
|
6/26/2024 9:00:24 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Donald Smith on behalf of Academy SD 20 Building Fund
|
6/26/2024 9:00:22 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Becky Allan on behalf of Academy SD 20 Building Fund
|
6/26/2024 9:00:20 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by on behalf of Pikes Peak Regional Building Department
|
6/26/2024 9:00:18 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
6/26/2024 9:00:16 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
|
6/26/2024 9:00:14 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by george san miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
6/26/2024 9:00:12 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
6/26/2024 9:00:10 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Travis Sauder on behalf of Colorado Parks and Wildlife
|
6/26/2024 9:00:08 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Tim Kroening on behalf of Colorado Parks and Wildlife
|
6/26/2024 9:00:07 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Karen Voltura on behalf of Colorado Parks and Wildlife
|
6/26/2024 9:00:05 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Cassidy English on behalf of Colorado Parks and Wildlife
|
6/26/2024 9:00:03 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
6/26/2024 9:00:00 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Melissa Van Der Poel on behalf of Colorado Division of Water Resources
|
6/26/2024 8:59:59 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
6/26/2024 8:59:57 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
|
6/26/2024 8:59:55 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
|
6/26/2024 8:59:53 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Arthur Gonzales on behalf of Colorado Department of Transportation - Pueblo Office
|
6/26/2024 8:59:51 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
|
6/26/2024 8:59:49 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Shannon Mustoe on behalf of EPC Stormwater Review
|
6/26/2024 8:59:47 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
6/26/2024 8:59:45 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Glenn Reese on behalf of EPC Stormwater Review
|
6/26/2024 8:59:43 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Christina Prete on behalf of EPC Stormwater Review
|
6/26/2024 8:59:41 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Jeff Kramer on behalf of EPC Sheriff's Department
|
6/26/2024 8:59:39 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Christopher Gonzalez on behalf of EPC Sheriff's Department
|
6/26/2024 8:59:37 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Andrew Prehm on behalf of EPC Sheriff's Department
|
6/26/2024 8:59:35 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by on behalf of EPC Parks Department
|
6/26/2024 8:59:33 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Mike McCarthy on behalf of EPC Health Department
|
6/26/2024 8:59:32 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Catherine McGarvy on behalf of EPC Health Department
|
6/26/2024 8:59:30 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by HEAEH LandUse on behalf of EPC Health Department
|
6/26/2024 8:59:26 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Kari Parsons on behalf of PCD Project Manager
|
6/26/2024 8:59:24 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Gilbert LaForce on behalf of PCD Engineering Division
|
6/26/2024 8:59:22 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Engineering Manager on behalf of PCD Engineering Division
|
6/26/2024 8:59:20 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by on behalf of PCD Administrative Notice
|
6/26/2024 8:59:18 AM
|
Request for Review Comments email sent for Project Kettle Creek Estates Filing No. 2 for review by Miranda Benson on behalf of PCD Administrative Notice
|
6/24/2024 2:51:47 PM
|
Fees paid: 6/24/2024 (Receipt: 1009273)
|
6/24/2024 2:45:57 PM
|
Project Manager Assigned: Scott Weeks
|
6/24/2024 2:40:50 PM
|
Payment Request sent: 6/24/2024
|
6/24/2024 2:40:50 PM
|
File # Assigned: VR246
|
6/24/2024 2:40:43 PM
|
Submission Triaged
|
6/24/2024 2:18:22 PM
|
Submission received from Applicant
|
4/25/2024 9:06:19 AM
|
Submission request sent to Applicant
|
4/25/2024 9:06:09 AM
|
Submission Triaged
|
4/24/2024 2:42:44 PM
|
Submission received from Applicant
|
3/29/2024 7:23:42 AM
|
Submission request sent to Applicant
|
3/29/2024 7:22:29 AM
|
Submission Triaged
|
3/28/2024 6:33:47 PM
|
Submission received from Applicant
|
8/31/2023 8:03:20 AM
|
Submission request sent to Applicant
|
8/25/2023 11:46:19 AM
|
Submission request sent to Applicant
|
8/25/2023 11:39:15 AM
|
Project Manager Assigned: Ryan Howser
|
8/25/2023 11:39:15 AM
|
EA Assigned: EA21111
|
8/25/2023 11:39:15 AM
|
Project Created
|