8/19/2024 2:36:59 PM
|
Project Closed
|
8/19/2024 2:36:59 PM
|
Project Approved: 8/19/2024
|
7/17/2024 3:20:20 PM
|
Project Ready for Approval requests. Review Comment period is complete.
|
7/10/2024 11:10:30 AM
|
Request for Review Comments returned by PCD Engineering Division
|
7/10/2024 5:02:22 AM
|
Fees paid: 7/10/2024 (Receipt: 1009324)
|
7/9/2024 9:18:59 AM
|
Payment Request sent: 7/9/2024
|
6/28/2024 2:15:15 PM
|
Request for Review Comments email sent for Project Apex Village Rezone for review by Gilbert LaForce on behalf of PCD Engineering Division
|
6/28/2024 2:15:11 PM
|
Request for Review Comments email sent for Project Apex Village Rezone for review by Engineering Manager on behalf of PCD Engineering Division
|
6/28/2024 1:10:37 PM
|
Project reopened for Review Comments
|
6/3/2024 10:07:39 AM
|
Request for Review Comments sent for Project 16888 Elbert Road Map Amendment (Rezoning) CC for review by Engineering Manager on behalf of PCD Engineering Division
|
5/20/2024 3:06:06 PM
|
Project Closed
|
5/20/2024 3:06:06 PM
|
Project Approved: 5/20/2024
|
5/20/2024 3:04:57 PM
|
Request for Review Comments returned by PCD Project Manager
|
5/20/2024 2:17:59 PM
|
Request for Review Comments returned by PCD Engineering Division
|
5/6/2024 11:16:00 AM
|
Request for Review Comments email sent for Project 16888 Elbert Road Map Amendment (Rezoning) CC for review by Kari Parsons on behalf of PCD Project Manager
|
5/6/2024 11:15:56 AM
|
Request for Review Comments email sent for Project 16888 Elbert Road Map Amendment (Rezoning) CC for review by Gilbert LaForce on behalf of PCD Engineering Division
|
5/6/2024 11:15:53 AM
|
Request for Review Comments email sent for Project 16888 Elbert Road Map Amendment (Rezoning) CC for review by Engineering Manager on behalf of PCD Engineering Division
|
5/6/2024 11:13:39 AM
|
Submission Triaged
|
5/1/2024 2:15:41 PM
|
Submission received from Applicant
|
4/22/2024 8:39:39 AM
|
Submission request sent to Applicant
|
4/22/2024 8:38:30 AM
|
Request for Review Comments returned by PCD Project Manager
|
4/18/2024 4:45:05 PM
|
Request for Review Comments returned by PCD Engineering Division
|
4/16/2024 9:55:43 PM
|
Fees paid: 4/16/2024 (Receipt: 1009017)
|
4/16/2024 3:10:17 PM
|
Payment Request sent: 4/16/2024
|
4/15/2024 8:08:35 AM
|
Request for Review Comments returned by PCD Administrative Notice
|
4/5/2024 8:54:40 AM
|
Request for Review Comments sent for Project 16888 Elbert Road Map Amendment (Rezoning) CC for review by on behalf of PCD Administrative Notice
|
4/5/2024 8:48:50 AM
|
Request for Review Comments email sent for Project 16888 Elbert Road Map Amendment (Rezoning) CC for review by Kari Parsons on behalf of PCD Project Manager
|
4/5/2024 8:48:47 AM
|
Request for Review Comments email sent for Project 16888 Elbert Road Map Amendment (Rezoning) CC for review by Gilbert LaForce on behalf of PCD Engineering Division
|
4/5/2024 8:48:43 AM
|
Request for Review Comments email sent for Project 16888 Elbert Road Map Amendment (Rezoning) CC for review by Engineering Manager on behalf of PCD Engineering Division
|
4/5/2024 8:41:53 AM
|
Submission Triaged
|
4/5/2024 4:49:37 AM
|
Submission received from Applicant
|
3/16/2024 2:46:26 PM
|
Request for Review Comments returned by EPC Health Department
|
2/29/2024 3:53:34 PM
|
Submission request sent to Applicant
|
2/29/2024 3:52:44 PM
|
Request for Review Comments returned by PCD Project Manager
|
2/29/2024 3:51:58 PM
|
Request for Review Comments returned by PCD Engineering Division
|
2/29/2024 3:35:37 PM
|
Request for Review Comments returned by PCD Project Manager
|
2/29/2024 11:38:33 AM
|
Request for Review Comments sent for Project 16888 Elbert Road Map Amendment (Rezoning) CC for review by on behalf of PCD Administrative Notice
|
2/28/2024 10:12:58 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
2/26/2024 2:59:54 PM
|
Request for Review Comments returned by Peyton 23
|
2/9/2024 11:38:15 AM
|
Request for Review Comments returned by EPC Environmental Services
|
2/9/2024 10:02:17 AM
|
Request for Review Comments returned by EPC Parks Department
|
2/8/2024 4:05:02 PM
|
Request for Review Comments returned by EPC Sheriff's Department
|
2/8/2024 11:51:08 AM
|
Request for Review Comments returned by Falcon Fire Protection District
|
2/8/2024 10:37:34 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
2/8/2024 10:17:25 AM
|
Request for Review Comments email sent for Project 16888 Elbert Road Map Amendment (Rezoning) CC for review by Greg Land on behalf of Peyton 23
|
2/8/2024 10:17:23 AM
|
Request for Review Comments email sent for Project 16888 Elbert Road Map Amendment (Rezoning) CC for review by Derek Burnside on behalf of Peyton 23
|
2/8/2024 10:17:21 AM
|
Request for Review Comments email sent for Project 16888 Elbert Road Map Amendment (Rezoning) CC for review by General Email on behalf of Mountain View Electric Association, Inc.
|
2/8/2024 10:17:19 AM
|
Request for Review Comments email sent for Project 16888 Elbert Road Map Amendment (Rezoning) CC for review by Jackie Evans on behalf of Kiowa Conservation Dist
|
2/8/2024 10:17:17 AM
|
Request for Review Comments email sent for Project 16888 Elbert Road Map Amendment (Rezoning) CC for review by Trent Harwig on behalf of Falcon Fire Protection District
|
2/8/2024 10:17:15 AM
|
Request for Review Comments email sent for Project 16888 Elbert Road Map Amendment (Rezoning) CC for review by Curtis Kauffman on behalf of Falcon Fire Protection District
|
2/8/2024 10:17:13 AM
|
Request for Review Comments email sent for Project 16888 Elbert Road Map Amendment (Rezoning) CC for review by on behalf of Pikes Peak Regional Building Department
|
2/8/2024 10:17:11 AM
|
Request for Review Comments email sent for Project 16888 Elbert Road Map Amendment (Rezoning) CC for review by Jeff Kramer on behalf of EPC Sheriff's Department
|
2/8/2024 10:17:09 AM
|
Request for Review Comments email sent for Project 16888 Elbert Road Map Amendment (Rezoning) CC for review by Christopher Gonzalez on behalf of EPC Sheriff's Department
|
2/8/2024 10:17:07 AM
|
Request for Review Comments email sent for Project 16888 Elbert Road Map Amendment (Rezoning) CC for review by Andrew Prehm on behalf of EPC Sheriff's Department
|
2/8/2024 10:17:05 AM
|
Request for Review Comments email sent for Project 16888 Elbert Road Map Amendment (Rezoning) CC for review by on behalf of EPC Parks Department
|
2/8/2024 10:17:02 AM
|
Request for Review Comments email sent for Project 16888 Elbert Road Map Amendment (Rezoning) CC for review by Mike McCarthy on behalf of EPC Health Department
|
2/8/2024 10:17:00 AM
|
Request for Review Comments email sent for Project 16888 Elbert Road Map Amendment (Rezoning) CC for review by Catherine McGarvy on behalf of EPC Health Department
|
2/8/2024 10:16:58 AM
|
Request for Review Comments email sent for Project 16888 Elbert Road Map Amendment (Rezoning) CC for review by HEAEH LandUse on behalf of EPC Health Department
|
2/8/2024 10:16:56 AM
|
Request for Review Comments email sent for Project 16888 Elbert Road Map Amendment (Rezoning) CC for review by Kathy Andrew on behalf of EPC Environmental Services
|
2/8/2024 10:16:50 AM
|
Request for Review Comments email sent for Project 16888 Elbert Road Map Amendment (Rezoning) CC for review by Hao Vo on behalf of PCD Engineering Division
|
2/8/2024 10:16:49 AM
|
Request for Review Comments email sent for Project 16888 Elbert Road Map Amendment (Rezoning) CC for review by Gilbert LaForce on behalf of PCD Engineering Division
|
2/8/2024 10:16:47 AM
|
Request for Review Comments email sent for Project 16888 Elbert Road Map Amendment (Rezoning) CC for review by Engineering Manager on behalf of PCD Engineering Division
|
2/6/2024 4:53:51 AM
|
Fees paid: 2/6/2024 (Receipt: 1008763)
|
1/25/2024 2:42:38 PM
|
Project Manager Assigned: Kylie Bagley
|
1/25/2024 2:42:22 PM
|
Payment Request sent: 1/25/2024
|
1/25/2024 2:42:22 PM
|
File # Assigned: P242
|
1/25/2024 2:42:16 PM
|
Submission Triaged
|
1/25/2024 1:41:08 PM
|
Submission received from Applicant
|
1/24/2024 8:30:03 AM
|
Submission request sent to Applicant
|
1/24/2024 8:29:54 AM
|
Submission Triaged
|
1/24/2024 6:27:27 AM
|
Submission received from Applicant
|
1/23/2024 4:12:41 PM
|
Submission request sent to Applicant
|
1/23/2024 4:12:15 PM
|
Submission Triaged
|
1/23/2024 2:40:25 PM
|
Submission received from Applicant
|
1/23/2024 7:10:36 AM
|
Project Manager Assigned: Ashlyn Mathy
|
1/23/2024 7:09:59 AM
|
Submission request sent to Applicant
|
1/23/2024 7:09:51 AM
|
Submission Triaged
|
1/22/2024 11:21:22 AM
|
Submission received from Applicant
|
1/9/2024 4:39:30 PM
|
Submission request sent to Applicant
|
1/9/2024 4:38:51 PM
|
Submission Triaged
|
1/9/2024 4:09:10 PM
|
Submission received from Applicant
|
1/9/2024 7:49:12 AM
|
Submission request sent to Applicant
|
1/9/2024 7:45:19 AM
|
Submission Triaged
|
1/8/2024 4:49:06 PM
|
Submission received from Applicant
|
10/17/2023 8:47:22 AM
|
Submission request sent to Applicant
|
10/17/2023 8:47:15 AM
|
Submission Triaged
|
10/17/2023 7:44:27 AM
|
Submission received from Applicant
|
8/22/2023 11:45:46 AM
|
Submission request sent to Applicant
|
8/22/2023 10:58:40 AM
|
Project Manager Assigned: Kylie Bagley
|
8/22/2023 10:58:39 AM
|
EA Assigned: EA2342
|
8/22/2023 10:58:39 AM
|
Project Created
|