9/30/2024 12:00:16 PM
|
Project Closed
|
|
9/30/2024 12:00:16 PM
|
Project Approved: 9/30/2024
|
|
9/30/2024 7:41:08 AM
|
Request for Review Comments returned by PCD Project Manager
|
|
9/27/2024 3:43:00 PM
|
Request for Review Comments returned by PCD Engineering Division
|
|
9/17/2024 8:00:58 AM
|
Project Manager Assigned: Kylie Bagley
|
|
9/13/2024 2:50:00 PM
|
Request for Review Comments email sent for Project Karmen Line Land Use for review by on behalf of EPC Public Works, County Engineer
|
|
9/13/2024 2:49:58 PM
|
Request for Review Comments email sent for Project Karmen Line Land Use for review by on behalf of EPC Public Works, County Engineer
|
|
9/13/2024 2:49:54 PM
|
Request for Review Comments email sent for Project Karmen Line Land Use for review by Kari Parsons on behalf of PCD Project Manager
|
|
9/13/2024 2:49:50 PM
|
Request for Review Comments email sent for Project Karmen Line Land Use for review by Gilbert LaForce on behalf of PCD Engineering Division
|
|
9/13/2024 2:49:49 PM
|
Request for Review Comments email sent for Project Karmen Line Land Use for review by Engineering Manager on behalf of PCD Engineering Division
|
|
9/13/2024 2:49:21 PM
|
Project reopened for Review Comments
|
|
9/13/2024 2:48:38 PM
|
Project Manager Assigned: Ryan Howser
|
|
7/14/2023 8:40:26 AM
|
Project Closed
|
|
7/14/2023 8:40:26 AM
|
Project Approved: 7/14/2023
|
|
7/14/2023 8:29:24 AM
|
Request for Review Comments returned by PCD Project Manager
|
|
7/12/2023 10:51:38 AM
|
Request for Review Comments returned by PCD Engineering Division
|
|
7/6/2023 11:30:38 AM
|
Request for Review Comments email sent for Project Karmen Line Land Use for review by Lekishia Bellamy on behalf of PCD Project Manager
|
|
7/6/2023 11:30:37 AM
|
Request for Review Comments email sent for Project Karmen Line Land Use for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
|
7/6/2023 11:28:55 AM
|
Request for Review Comments email sent for Project Karmen Line Land Use for review by County Engineer on behalf of EPC Public Works, County Engineer
|
|
7/6/2023 11:28:54 AM
|
Request for Review Comments email sent for Project Karmen Line Land Use for review by County Engineer on behalf of EPC Public Works, County Engineer
|
|
7/6/2023 11:28:53 AM
|
Request for Review Comments email sent for Project Karmen Line Land Use for review by Lekishia Bellamy on behalf of PCD Project Manager
|
|
7/6/2023 11:28:52 AM
|
Request for Review Comments email sent for Project Karmen Line Land Use for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
|
7/5/2023 1:01:58 PM
|
No Fees
|
|
7/5/2023 1:01:58 PM
|
File # Assigned: OAR2337
|
|
7/5/2023 1:01:58 PM
|
Project Manager Assigned: Lekishia Bellamy
|
|
7/5/2023 1:01:58 PM
|
Project Created
|