Project Details
- File Number
- CON2315
- Project Name
- Tri-State-Monument Substation Replacement Site Dev. Plan
- Description
- Replacement of old substation and its components to correct reliability issues. Substation to remain under 50kV, no additional capacity proposed. Exemption from 1041 approved.; Full Landscape not required with Utility
- Location
- 13382 deposit no.
- Parcels
- 6100000088 6100000088 6121003005 6121003005
- Applicant
-
Tri-State Generation and Transmission Association, Inc.
Zach Sutton ( zsutton@tristategt.org )
(720) 454-0699 Zach Sutton ( zsutton@tristategt.org )
(720) 454-0699 - File Prefix
- CON - Construction Permit
- Year
- 2023
- Project Manager
- Spencer Pirzadeh
- Status
- Closed
- Created
- 4/20/2023 2:45:48 PM
Document | Comment | ||
---|---|---|---|
View | CDPS Permit | 5/23/2023 9:28:46 AM |
Document | Date | |
---|---|---|
View | Grading & Erosion Control checklist | 5/23/2023 9:30:50 AM |
View | Erosion and Stormwater Quality Control Permit (ESQCP) | 5/23/2023 9:30:51 AM |
View | Financial Assurance Forms | 5/23/2023 9:30:52 AM |
View | Maintenance Agreement (MS Word version required attachments included) | 5/23/2023 9:30:51 AM |
View | MS4 Post Construction Form | 5/23/2023 9:30:51 AM |
View | PBMP Applicability Form | 5/23/2023 9:30:50 AM |
View | PDB/BMP Operations & Maintenance Manual | 5/23/2023 9:30:50 AM |
View | Stormwater Detention & Infiltration Design Data Worksheet (SDI Worksheet) | 5/23/2023 9:30:51 AM |
View | SWMP checklist | 5/23/2023 9:30:50 AM |
View | Grading & Erosion Control Plan | 5/23/2023 9:30:51 AM |
View | Site Development Plan | 5/23/2023 9:30:49 AM |
View | Drainage Report - Final | 5/23/2023 9:30:52 AM |