1/29/2026 4:43:59 PM
|
Project Closed
|
|
1/29/2026 4:43:59 PM
|
Project completed: 1/29/2026
|
|
9/24/2024 7:26:08 AM
|
Executive Determination Requested
|
|
8/8/2024 11:17:50 AM
|
County Attorney Letter Issued
|
|
6/5/2024 7:05:01 AM
|
County Attorney Letter Requested
|
|
5/14/2024 12:09:06 PM
|
Executive Determination Requested
|
|
1/2/2024 5:19:52 PM
|
Project Manager Assigned: April Smith
|
|
5/31/2023 11:32:28 AM
|
Notice of Violation sent
|
|
4/17/2023 7:52:15 PM
|
No Fees
|
|
4/17/2023 7:52:15 PM
|
File # Assigned: CE23230
|
|
4/17/2023 7:52:14 PM
|
Project Manager Assigned: Michael Shannon
|
|
4/17/2023 7:52:14 PM
|
Project Created
|
|
4/17/2023 7:52:12 PM
|
Application Triaged/Accepted
|
|
4/17/2023 7:52:11 PM
|
Application submitted
|