Project Details
- File Number
- CON2261
- Project Name
- Widefield Park & Rec Improvements
- Parcels
- 6512300003 6512300003 6513100001 6513100001 6513100003 6513100003
- Applicant
-
Widefield School District
Project Architect Todd Kimes ( toddkimes@lkapartners.com )
(719) 473-8446 x123 Project Architect Todd Kimes ( toddkimes@lkapartners.com )
(719) 473-8446 x123 - File Prefix
- CON - Construction Permit
- Year
- 2022
- Project Manager
- Amanda Rivera
- Status
- Closed
- Created
- 12/8/2022 8:44:34 AM
Document | Comment | ||
---|---|---|---|
View | Unsigned Con Permit | 12/8/2022 10:01:52 AM | |
View | Approved ESQCP (Needs Developer Signatures) 9-21-22 | 12/15/2022 4:18:31 PM | |
View | Nunn Constructions Updated C7.5_ Pond Details Rev.5 Markup Sheet 3-6-23 | 3/22/2023 5:13:53 PM | |
View | Approved Revised Grading And Erosion Control Plan 2-28-23 | 3/23/2023 5:07:59 PM | |
View | Approved Revised Final Drainage Report 3-1-23 | 3/23/2023 5:09:26 PM | |
View | RE WPR Outlet Structure Email 4-6-23 | 4/6/2023 5:25:32 PM | |
View | Kimley-Horn Outlet Structure EOR Letter Revision 4-6-23 | 4/6/2023 5:25:33 PM | |
View | Stormwater Punchlist PA | 8/29/2023 6:52:59 AM |
Document | Date | |
---|---|---|
View | Approved CD's | 12/8/2022 9:19:37 AM |
View | Approved FAE | 12/8/2022 9:19:38 AM |
View | Approved FAE 9-26-22 | 12/15/2022 4:26:08 PM |
View | Approved Final Drainage Report | 12/8/2022 9:19:38 AM |
View | Approved Final Drainage Report 9-21-22 | 12/15/2022 4:40:13 PM |
View | Approved G&E | 12/8/2022 9:19:39 AM |
View | Approved Grading And Erosion Control Plan 9-21-22 | 12/15/2022 4:40:14 PM |
View | Approved Site Development Plan 10-20-22 | 12/15/2022 4:22:41 PM |
View | NA | 3/2/2023 1:53:17 PM |
View | PreCon Documents | 12/8/2022 10:42:36 AM |
View | Receipt For Construction Permit Fees Paid 12-15-22 | 12/15/2022 4:02:04 PM |