Project Details
- File Number
- AG2237
- Description
- Existing pole barn was not permitted at time it was built prior to our clients purchasing the lot. Building is used for storing hay and grain for livestock. We brought power to the building for lighting and are unable to complete our electrical inspection since the building was never permitted. It is a 880sqft pole barn with metal siding for weather exposure.
- Parcels
- 6224004003 6224004003
- Project Address
-
10705 MILAM RD
COLORADO SPRINGS, CO 80908
- Applicant
-
Gold Rush Construction
Greg Wheatley ( Kailey.wheatley@outlook.com )
(719) 229-8751 Greg Wheatley ( Kailey.wheatley@outlook.com )
(719) 229-8751 - File Prefix
- AG - Agricultural Structure
- Year
- 2022
- Number of Structures
- 1
- New Construction?
- No, Existing structure
- Square Footage
- 880
- # Design Features
- 3
- Exterior Appearance
- Appropriately sized doors to allow for livestock and/or agricultural implements and machinery to enter and exit the structure (REQUIRED); Dutch Doors; Barn Breezeway; Appropriate siding material for weather exposure;
- Use of the Structure
- Shelter for livestock (including hen chickens) or for the storage of the feed and equipment relating to the care, training, raising, and/or maintenance of the livestock (including hen chickens);
- Project Manager
- Mindy Schulz
- Status
- Closed
- Created
- 9/19/2022 2:52:30 PM
View: Review Comments
Document | Date | |
---|---|---|
View | Site Plan Drawing | 9/19/2022 2:52:35 PM |
Date | Comment |
---|---|
3/6/2023 8:46:19 AM | Project Closed |
3/6/2023 8:46:19 AM | Project Denied: 3/6/2023 |
3/6/2023 8:45:29 AM | Submission request canceled |
3/6/2023 8:44:58 AM | Project Manager Assigned: Mindy Madden |
3/6/2023 8:44:46 AM | Supervisor Review Requested |
10/27/2022 7:42:12 AM | Project Manager Assigned: Michael Shannon |
10/27/2022 7:41:19 AM | Project reopened for Inspections |
10/27/2022 7:39:31 AM | Project Manager Assigned: Mindy Madden |
10/27/2022 7:36:51 AM | Request for Approval returned by EPC Code Enforcement |
10/27/2022 7:36:26 AM | Request for Approval sent for Project 10705 MILAM RD for review by Joe Letke on behalf of EPC Code Enforcement |
9/29/2022 7:48:02 AM | Submission request sent to Applicant |
9/22/2022 10:08:59 AM | Request for Approval returned by PCD Site Plans |
9/21/2022 11:20:15 AM | Request for Approval sent for Project 10705 MILAM RD for review by Petra Rangel on behalf of PCD Site Plans |
9/21/2022 11:19:54 AM | Project Manager Assigned: Joe Letke |
9/19/2022 3:06:34 PM | Fees paid: 9/19/2022 (Receipt: 1006945) |
9/19/2022 2:52:36 PM | Payment Request sent: 9/19/2022 |
9/19/2022 2:52:36 PM | File # Assigned: AG2237 |
9/19/2022 2:52:35 PM | Project Created |
9/19/2022 2:52:30 PM | Application Triaged/Accepted |
9/19/2022 1:44:19 PM | Application submitted |