10/3/2022 10:07:21 AM
|
Project Closed
|
10/3/2022 10:07:21 AM
|
Project Approved: 10/3/2022
|
10/3/2022 9:55:12 AM
|
Project Ready for Approval requests. Review Comment period is complete.
|
9/29/2022 11:29:58 AM
|
Request for Review Comments returned by PCD Engineering Division
|
8/31/2022 11:46:37 AM
|
Request for Review Comments returned by PCD Project Manager
|
8/31/2022 11:35:20 AM
|
Request for Review Comments email sent for Project OAR Midtown Collection at Monument Junction for review by Joshua Palmer on behalf of EPC Public Works, County Engineer
|
8/31/2022 11:35:19 AM
|
Request for Review Comments email sent for Project OAR Midtown Collection at Monument Junction for review by Planner Dan Feuerbach on behalf of PCD Project Manager
|
8/31/2022 11:35:17 AM
|
Request for Review Comments email sent for Project OAR Midtown Collection at Monument Junction for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
8/31/2022 11:28:40 AM
|
No Fees
|
8/31/2022 11:28:40 AM
|
File # Assigned: OAR2296
|
8/31/2022 11:28:40 AM
|
Project Manager Assigned: Planner Dan Feuerbach
|
8/31/2022 11:28:40 AM
|
Project Created
|