2/8/2023 8:29:00 AM
|
Project Closed
|
2/8/2023 8:29:00 AM
|
Project Approved: 2/8/2023
|
1/10/2023 9:40:07 AM
|
Request for Review Comments returned by PCD Engineering Division
|
12/20/2022 3:29:01 PM
|
Request for Review Comments email sent for Project 4-Way Commercial Rezoning for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
12/20/2022 3:28:37 PM
|
Submission Triaged
|
12/20/2022 12:08:20 PM
|
Submission received from Applicant
|
12/14/2022 1:35:39 PM
|
Submission request sent to Applicant
|
12/14/2022 1:35:05 PM
|
Request for Review Comments returned by PCD Project Manager
|
12/7/2022 10:42:57 AM
|
Request for Review Comments returned by PCD Engineering Division
|
12/5/2022 4:02:34 PM
|
Project Manager Assigned: Ryan Howser
|
11/22/2022 11:48:13 AM
|
Request for Review Comments email sent for Project 4-Way Commercial Rezoning for review by Kylie Bagley on behalf of PCD Project Manager
|
11/22/2022 11:48:11 AM
|
Request for Review Comments email sent for Project 4-Way Commercial Rezoning for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
11/22/2022 11:46:13 AM
|
Submission Triaged
|
11/22/2022 11:14:44 AM
|
Submission received from Applicant
|
10/20/2022 12:13:35 PM
|
Submission request sent to Applicant
|
10/20/2022 12:13:18 PM
|
Request for Review Comments returned by PCD Project Manager
|
10/20/2022 7:39:34 AM
|
Request for Review Comments returned by PCD Engineering Division
|
10/17/2022 3:38:00 PM
|
Request for Review Comments returned by Meadow Lake Airport Association
|
10/17/2022 10:31:29 AM
|
Project Manager Assigned: Kylie Bagley
|
10/14/2022 2:50:06 PM
|
Request for Review Comments returned by Colorado Parks and Wildlife
|
10/6/2022 3:27:52 PM
|
Request for Review Comments returned by PCD Administrative Notice
|
10/5/2022 5:45:18 PM
|
Request for Review Comments returned by Upper Black Squirrel Creek GWMD
|
9/28/2022 9:06:26 AM
|
Request for Review Comments returned by County Attorney - Development Review
|
9/26/2022 4:47:58 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
9/26/2022 10:08:30 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
9/25/2022 5:34:09 PM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
9/23/2022 3:47:21 PM
|
Request for Review Comments returned by County Attorney - Water
|
9/23/2022 3:16:02 PM
|
Request for Review Comments returned by RBD Floodplain
|
9/23/2022 3:12:48 PM
|
Request for Review Comments email sent for Project 4-Way Commercial Rezoning for review by deric clemons on behalf of Natural Resources Conservation Service (Federal Agency)
|
9/23/2022 3:12:47 PM
|
Request for Review Comments email sent for Project 4-Way Commercial Rezoning for review by General Email on behalf of Mountain View Electric Association, Inc.
|
9/23/2022 3:12:46 PM
|
Request for Review Comments email sent for Project 4-Way Commercial Rezoning for review by Dave Elliott on behalf of Meadow Lake Airport Association
|
9/23/2022 3:12:45 PM
|
Request for Review Comments email sent for Project 4-Way Commercial Rezoning for review by Elizabeth Dukes on behalf of Falcon School District 49
|
9/23/2022 3:12:44 PM
|
Request for Review Comments email sent for Project 4-Way Commercial Rezoning for review by Fire Chief Trent Harwig on behalf of Falcon Fire Protection District
|
9/23/2022 3:12:43 PM
|
Request for Review Comments email sent for Project 4-Way Commercial Rezoning for review by District Manager Mariah Hudson on behalf of El Paso County Conservation Dist
|
9/23/2022 3:12:41 PM
|
Request for Review Comments email sent for Project 4-Way Commercial Rezoning for review by Santiago Tijerina on behalf of Black Hills Energy-Aquila
|
9/23/2022 3:12:40 PM
|
Request for Review Comments email sent for Project 4-Way Commercial Rezoning for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
|
9/23/2022 3:12:39 PM
|
Request for Review Comments email sent for Project 4-Way Commercial Rezoning for review by Keith Curtis on behalf of RBD Floodplain
|
9/23/2022 3:12:38 PM
|
Request for Review Comments email sent for Project 4-Way Commercial Rezoning for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
9/23/2022 3:12:37 PM
|
Request for Review Comments email sent for Project 4-Way Commercial Rezoning for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
9/23/2022 3:12:36 PM
|
Request for Review Comments email sent for Project 4-Way Commercial Rezoning for review by Joseph Martinez on behalf of US Army Corps of Engineers-Pueblo
|
9/23/2022 3:12:35 PM
|
Request for Review Comments email sent for Project 4-Way Commercial Rezoning for review by Tim Kroening on behalf of Colorado Parks and Wildlife
|
9/23/2022 3:12:34 PM
|
Request for Review Comments email sent for Project 4-Way Commercial Rezoning for review by CDOT Permits Program Mgr Valerie Vigil on behalf of Colorado Department of Transportation - Pueblo Office
|
9/23/2022 3:12:32 PM
|
Request for Review Comments email sent for Project 4-Way Commercial Rezoning for review by on behalf of Parks Advisory Board
|
9/23/2022 3:12:31 PM
|
Request for Review Comments email sent for Project 4-Way Commercial Rezoning for review by Edi Anderson on behalf of County Attorney - Water
|
9/23/2022 3:12:27 PM
|
Request for Review Comments email sent for Project 4-Way Commercial Rezoning for review by Lori Seago on behalf of County Attorney - Development Review
|
9/23/2022 3:12:26 PM
|
Request for Review Comments email sent for Project 4-Way Commercial Rezoning for review by Matthew Fitzsimmons on behalf of PCD Project Manager
|
9/23/2022 3:12:25 PM
|
Request for Review Comments email sent for Project 4-Way Commercial Rezoning for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
9/23/2022 3:12:23 PM
|
Request for Review Comments email sent for Project 4-Way Commercial Rezoning for review by on behalf of PCD Administrative Notice
|
9/23/2022 2:32:59 PM
|
Fees paid: 9/23/2022 (Receipt: 1006982)
|
9/23/2022 11:13:23 AM
|
Payment Request sent: 9/23/2022
|
9/23/2022 11:13:23 AM
|
File # Assigned: CS223
|
9/23/2022 11:13:20 AM
|
Submission Triaged
|
9/22/2022 4:17:26 PM
|
Submission received from Applicant
|
7/5/2022 1:27:25 PM
|
Submission request sent to Applicant
|
6/29/2022 11:28:46 AM
|
Project Manager Assigned: Matthew Fitzsimmons
|
6/29/2022 11:28:46 AM
|
EA Assigned: EA22107
|
6/29/2022 11:28:46 AM
|
Project Created
|