2/1/2023 5:19:44 PM
|
Project Closed
|
2/1/2023 5:19:44 PM
|
Project Approved: 2/1/2023
|
1/3/2023 11:31:59 AM
|
Request for Review Comments returned by County Attorney - Water
|
1/3/2023 7:26:05 AM
|
Request for Review Comments returned by PCD Project Manager
|
12/28/2022 1:10:52 PM
|
Request for Review Comments returned by PCD Engineering Division
|
12/20/2022 3:47:23 PM
|
Submission Triaged
|
12/20/2022 3:39:45 PM
|
Submission received from Applicant
|
12/20/2022 3:26:22 PM
|
Submission request sent to Applicant
|
12/20/2022 11:12:25 AM
|
Submission Triaged
|
12/20/2022 10:54:28 AM
|
Submission received from Applicant
|
12/20/2022 7:32:12 AM
|
Submission request sent to Applicant
|
12/19/2022 2:18:07 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Lori Seago on behalf of County Attorney - Water
|
12/19/2022 2:18:02 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Kari Parsons on behalf of PCD Project Manager
|
12/19/2022 2:18:00 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
12/19/2022 2:04:15 PM
|
Submission Triaged
|
12/19/2022 1:51:56 PM
|
Submission received from Applicant
|
12/19/2022 9:37:08 AM
|
Submission request sent to Applicant
|
12/15/2022 3:54:16 PM
|
Request for Review Comments returned by US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
12/15/2022 9:43:02 AM
|
Request for Review Comments returned by RBD Floodplain
|
12/12/2022 10:50:02 PM
|
Request for Review Comments returned by EPC Health Department
|
12/12/2022 4:18:30 PM
|
Request for Review Comments returned by Black Forest Fire Protection District
|
12/12/2022 8:46:33 AM
|
Submission request sent to Applicant
|
12/9/2022 10:22:34 AM
|
Request for Review Comments returned by County Attorney - Water
|
12/8/2022 12:02:19 PM
|
Request for Review Comments returned by Parks Advisory Board
|
12/6/2022 4:10:34 PM
|
Request for Review Comments returned by Colorado Geological Survey
|
12/5/2022 3:06:33 PM
|
Submission request sent to Applicant
|
12/5/2022 8:30:47 AM
|
Submission request sent to Applicant
|
12/5/2022 8:29:14 AM
|
Request for Review Comments returned by PCD Project Manager
|
12/1/2022 4:49:52 PM
|
Request for Review Comments returned by PCD Engineering Division
|
12/1/2022 1:46:02 PM
|
Submission request sent to Applicant
|
12/1/2022 1:26:13 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
11/30/2022 8:40:25 AM
|
Request for Review Comments email resent for Project Homestead North Filing No. 3 Preliminary Plan for review by Edi Anderson on behalf of County Attorney - Water
|
11/30/2022 8:18:22 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
11/29/2022 3:31:51 PM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
11/29/2022 2:22:35 PM
|
Request for Review Comments returned by County Attorney - Water
|
11/15/2022 8:49:49 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
11/15/2022 7:13:27 AM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
11/15/2022 7:13:25 AM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Deputy Chief James Rebitski on behalf of Black Forest Fire Protection District
|
11/15/2022 7:13:23 AM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
|
11/15/2022 7:13:22 AM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Keith Curtis on behalf of RBD Floodplain
|
11/15/2022 7:13:21 AM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
11/15/2022 7:13:20 AM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
11/15/2022 7:13:19 AM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
11/15/2022 7:13:18 AM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Joseph Martinez on behalf of US Army Corps of Engineers-Pueblo
|
11/15/2022 7:13:17 AM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
11/15/2022 7:13:14 AM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
11/15/2022 7:13:13 AM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by on behalf of Parks Advisory Board
|
11/15/2022 7:13:11 AM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
11/15/2022 7:13:10 AM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Catherine McGarvy on behalf of EPC Health Department
|
11/15/2022 7:13:06 AM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Edi Anderson on behalf of County Attorney - Water
|
11/15/2022 7:13:03 AM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Kari Parsons on behalf of PCD Project Manager
|
11/15/2022 7:13:01 AM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
11/15/2022 7:08:07 AM
|
Submission Triaged
|
11/14/2022 5:47:16 PM
|
Submission received from Applicant
|
9/15/2022 10:29:39 AM
|
Request for Review Comments returned by Parks Advisory Board
|
9/13/2022 11:35:27 AM
|
Submission request sent to Applicant
|
9/13/2022 11:19:52 AM
|
Request for Review Comments returned by PCD Engineering Division
|
9/13/2022 10:51:22 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
9/13/2022 9:40:35 AM
|
Submission Triaged
|
9/13/2022 9:24:22 AM
|
Submission received from Applicant
|
9/13/2022 9:18:36 AM
|
Submission request sent to Applicant
|
9/13/2022 7:25:49 AM
|
Submission request sent to Applicant
|
9/13/2022 7:22:48 AM
|
Submission request sent to Applicant
|
9/13/2022 7:22:39 AM
|
Submission Triaged
|
9/12/2022 5:40:09 PM
|
Submission received from Applicant
|
9/12/2022 5:10:22 PM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
9/8/2022 2:58:47 PM
|
Request for Review Comments returned by PCD Project Manager
|
9/7/2022 12:25:27 PM
|
Request for Review Comments returned by Colorado Parks and Wildlife
|
9/7/2022 10:28:14 AM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
9/6/2022 5:10:17 PM
|
Submission request sent to Applicant
|
9/6/2022 6:50:14 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
9/2/2022 10:50:52 AM
|
Request for Review Comments returned by Colorado Geological Survey
|
9/2/2022 8:03:57 AM
|
Request for Review Comments returned by Colorado Springs Public Works
|
8/31/2022 7:08:17 AM
|
Submission Triaged
|
8/30/2022 6:47:04 PM
|
Submission received from Applicant
|
8/30/2022 12:36:30 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
8/30/2022 10:42:45 AM
|
Request for Review Comments returned by County Attorney - Development Review
|
8/30/2022 8:46:48 AM
|
Request for Review Comments returned by Academy SD 20 Building Fund
|
8/29/2022 12:08:16 PM
|
Request for Review Comments returned by EPC Parks Department
|
8/23/2022 2:38:06 PM
|
Submission request sent to Applicant
|
8/22/2022 9:01:38 AM
|
Request for Review Comments returned by Colorado Springs Planning & Community Development
|
8/22/2022 7:54:20 AM
|
Request for Review Comments returned by Black Forest Fire Protection District
|
8/18/2022 11:11:21 AM
|
Request for Review Comments returned by EPC Environmental Services
|
8/17/2022 11:51:12 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
8/16/2022 12:05:39 PM
|
Request for Review Comments returned by RBD Floodplain
|
8/16/2022 11:04:08 AM
|
Request for Review Comments returned by Colorado State Forest Service
|
8/15/2022 4:54:06 PM
|
Request for Review Comments returned by Black Forest Land Use Committee
|
8/15/2022 4:03:44 PM
|
Request for Review Comments returned by County Attorney - Water
|
8/15/2022 3:55:07 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Susan Davies on behalf of Trails and Open Space Coalition
|
8/15/2022 3:55:06 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Tabitha Barile on behalf of Sterling Ranch Metropolitan District 1-3
|
8/15/2022 3:55:05 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by John Lewis on behalf of Northern EPC Coalition of Community Organizations, Inc. (NEPCO)
|
8/15/2022 3:55:03 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by General Email on behalf of Mountain View Electric Association, Inc.
|
8/15/2022 3:55:02 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Roger Austin on behalf of Mountain Metro Transit (City of COS)
|
8/15/2022 3:55:01 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by District Manager Mariah Hudson on behalf of El Paso County Conservation Dist
|
8/15/2022 3:54:58 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Records Management Lead LaShunda Simpson on behalf of Colorado Springs Public Works
|
8/15/2022 3:54:44 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Gabe Sevigny on behalf of Colorado Springs Planning & Community Development
|
8/15/2022 3:54:39 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
8/15/2022 3:54:37 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Cheryl Pixley on behalf of Black Forest Trails Association
|
8/15/2022 3:54:36 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Terry Stokka on behalf of Black Forest Land Use Committee
|
8/15/2022 3:54:33 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Deputy Chief James Rebitski on behalf of Black Forest Fire Protection District
|
8/15/2022 3:54:30 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Plannig Consultant Donald Smith on behalf of Academy SD 20 Building Fund
|
8/15/2022 3:54:29 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
|
8/15/2022 3:54:28 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Keith Curtis on behalf of RBD Floodplain
|
8/15/2022 3:54:27 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
8/15/2022 3:54:26 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Larry Small on behalf of Fountain Creek Watershed Flood Control & Greenway Dist
|
8/15/2022 3:54:25 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
8/15/2022 3:54:24 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
8/15/2022 3:54:23 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Joseph Martinez on behalf of US Army Corps of Engineers-Pueblo
|
8/15/2022 3:54:22 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Mr. Andy Schlosberg on behalf of Colorado State Forest Service
|
8/15/2022 3:54:21 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Tim Kroening on behalf of Colorado Parks and Wildlife
|
8/15/2022 3:54:15 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
8/15/2022 3:54:14 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
8/15/2022 3:54:12 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by on behalf of Parks Advisory Board
|
8/15/2022 3:54:12 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
8/15/2022 3:54:09 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Bill Elder on behalf of EPC Sheriff's Department
|
8/15/2022 3:54:08 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Bill Elder on behalf of EPC Sheriff's Department
|
8/15/2022 3:54:07 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Joshua Palmer on behalf of EPC Public Works, County Engineer
|
8/15/2022 3:54:05 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by on behalf of EPC Parks Department
|
8/15/2022 3:54:04 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Catherine McGarvy on behalf of EPC Health Department
|
8/15/2022 3:53:59 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Kathy Andrew on behalf of EPC Environmental Services
|
8/15/2022 3:53:58 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Edi Anderson on behalf of County Attorney - Water
|
8/15/2022 3:53:53 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Lori Seago on behalf of County Attorney - Development Review
|
8/15/2022 3:53:50 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Kari Parsons on behalf of PCD Project Manager
|
8/15/2022 3:53:48 PM
|
Request for Review Comments email sent for Project Homestead North Filing No. 3 Preliminary Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
8/15/2022 3:02:43 PM
|
Fees paid: 8/15/2022 (Receipt: 1006785)
|
7/28/2022 9:45:42 AM
|
Payment Request sent: 7/28/2022
|
7/28/2022 9:45:41 AM
|
File # Assigned: SP227
|
7/28/2022 9:45:35 AM
|
Submission Triaged
|
7/27/2022 1:26:12 PM
|
Submission received from Applicant
|
4/28/2022 8:03:32 AM
|
Submission request sent to Applicant
|
4/28/2022 7:59:13 AM
|
Project Manager Assigned: Kari Parsons
|
4/28/2022 7:59:13 AM
|
EA Assigned: EA2060
|
4/28/2022 7:59:13 AM
|
Project Created
|