6/21/2022 8:14:22 AM
|
Project Closed
|
6/21/2022 8:14:22 AM
|
Project Approved: 6/21/2022
|
6/16/2022 7:16:06 AM
|
Request for Review Comments returned by PCD Engineering Division
|
6/10/2022 3:30:53 PM
|
Submission Triaged
|
6/10/2022 7:44:05 AM
|
Submission received from Applicant
|
6/9/2022 5:17:51 PM
|
Submission request sent to Applicant
|
6/9/2022 3:30:38 PM
|
Request for Review Comments email sent for Project Rolling Hills Ranch North & Sanctuary Early Grading Permit for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
6/9/2022 9:54:56 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
6/8/2022 4:01:43 PM
|
Request for Review Comments returned by PCD Project Manager
|
6/7/2022 4:44:02 PM
|
Request for Review Comments returned by PCD Engineering Division
|
5/17/2022 1:37:42 PM
|
Request for Review Comments email sent for Project Rolling Hills Ranch North & Sanctuary Early Grading Permit for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
5/17/2022 1:37:39 PM
|
Request for Review Comments email sent for Project Rolling Hills Ranch North & Sanctuary Early Grading Permit for review by Ryan Howser on behalf of PCD Project Manager
|
5/17/2022 1:37:36 PM
|
Request for Review Comments email sent for Project Rolling Hills Ranch North & Sanctuary Early Grading Permit for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
5/17/2022 1:36:56 PM
|
Submission Triaged
|
5/17/2022 8:48:43 AM
|
Submission received from Applicant
|
5/17/2022 8:34:31 AM
|
Submission request sent to Applicant
|
5/17/2022 8:33:55 AM
|
Submission Triaged
|
5/16/2022 6:55:56 AM
|
Submission received from Applicant
|
5/13/2022 5:09:14 PM
|
Submission request sent to Applicant
|
5/13/2022 5:08:59 PM
|
Submission Triaged
|
5/13/2022 8:38:04 AM
|
Submission received from Applicant
|
5/3/2022 4:11:51 PM
|
Submission request sent to Applicant
|
5/3/2022 4:11:06 PM
|
Request for Review Comments returned by PCD Project Manager
|
4/28/2022 3:17:27 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
4/28/2022 3:01:52 PM
|
Request for Review Comments returned by PCD Engineering Division
|
4/27/2022 12:45:52 PM
|
Request for Review Comments returned by Parks Advisory Board
|
4/27/2022 12:43:38 PM
|
Request for Review Comments returned by EPC Parks Department
|
4/13/2022 10:02:04 AM
|
Request for Review Comments email sent for Project Rolling Hills Ranch North & Sanctuary Early Grading Permit for review by on behalf of Parks Advisory Board
|
4/13/2022 10:02:02 AM
|
Request for Review Comments email sent for Project Rolling Hills Ranch North & Sanctuary Early Grading Permit for review by on behalf of EPC Parks Department
|
4/6/2022 7:28:59 AM
|
Request for Review Comments email sent for Project Rolling Hills Ranch North & Sanctuary Early Grading Permit for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
4/6/2022 7:28:55 AM
|
Request for Review Comments email sent for Project Rolling Hills Ranch North & Sanctuary Early Grading Permit for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
|
4/6/2022 7:28:54 AM
|
Request for Review Comments email sent for Project Rolling Hills Ranch North & Sanctuary Early Grading Permit for review by Ryan Howser on behalf of PCD Project Manager
|
4/6/2022 7:28:53 AM
|
Request for Review Comments email sent for Project Rolling Hills Ranch North & Sanctuary Early Grading Permit for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
4/6/2022 7:22:04 AM
|
Fees paid: 4/6/2022 (Receipt: 1006120)
|
4/5/2022 5:21:45 PM
|
Payment Request sent: 4/5/2022
|
4/5/2022 4:58:05 PM
|
Payment Request sent: 4/5/2022
|
4/5/2022 4:57:57 PM
|
File # Assigned: EGP222
|
4/5/2022 4:17:11 PM
|
Project Manager Assigned: Ryan Howser
|
4/5/2022 4:17:11 PM
|
EA Assigned: EA21205
|
4/5/2022 4:17:11 PM
|
Project Created
|