7/18/2022 9:23:24 AM
|
Project Closed
|
7/18/2022 9:23:24 AM
|
Project Approved: 7/18/2022
|
7/18/2022 9:05:22 AM
|
Request for Review Comments returned by PCD Project Manager
|
7/13/2022 8:41:37 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
7/12/2022 11:08:24 AM
|
Request for Review Comments email sent for Project 19580 Four Winds Way for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
7/12/2022 11:08:20 AM
|
Request for Review Comments email sent for Project 19580 Four Winds Way for review by Kylie Bagley on behalf of PCD Project Manager
|
7/12/2022 11:07:49 AM
|
Submission Triaged
|
7/12/2022 10:54:24 AM
|
Submission received from Applicant
|
7/12/2022 10:23:58 AM
|
Submission request sent to Applicant
|
7/12/2022 9:56:07 AM
|
Request for Review Comments returned by PCD Project Manager
|
7/8/2022 4:41:48 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
7/5/2022 2:46:35 PM
|
Request for Review Comments returned by PCD Engineering Division
|
6/27/2022 11:35:06 AM
|
Request for Review Comments email sent for Project 19580 Four Winds Way for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
6/27/2022 11:35:03 AM
|
Request for Review Comments email sent for Project 19580 Four Winds Way for review by Kylie Bagley on behalf of PCD Project Manager
|
6/27/2022 11:35:01 AM
|
Request for Review Comments email sent for Project 19580 Four Winds Way for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
6/24/2022 1:26:00 PM
|
Submission Triaged
|
6/24/2022 7:51:06 AM
|
Submission received from Applicant
|
5/25/2022 2:43:44 PM
|
Submission request sent to Applicant
|
5/25/2022 2:42:55 PM
|
Request for Review Comments returned by PCD Project Manager
|
5/25/2022 2:13:31 PM
|
Request for Review Comments email resent for Project 19580 Four Winds Way for review by Kylie Bagley on behalf of PCD Project Manager
|
5/25/2022 9:25:23 AM
|
Request for Review Comments returned by PCD Engineering Division
|
5/25/2022 8:37:05 AM
|
Request for Review Comments returned by PCD Project Manager
|
5/24/2022 5:21:39 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
5/3/2022 1:56:38 PM
|
Request for Review Comments email sent for Project 19580 Four Winds Way for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
5/3/2022 1:56:34 PM
|
Request for Review Comments email sent for Project 19580 Four Winds Way for review by Kylie Bagley on behalf of PCD Project Manager
|
5/3/2022 1:56:32 PM
|
Request for Review Comments email sent for Project 19580 Four Winds Way for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
5/3/2022 1:18:44 PM
|
Submission Triaged
|
4/29/2022 12:59:12 PM
|
Submission received from Applicant
|
4/8/2022 2:26:29 PM
|
Submission request sent to Applicant
|
4/8/2022 2:26:17 PM
|
Request for Review Comments returned by PCD Project Manager
|
4/8/2022 2:25:22 PM
|
Request for Review Comments email resent for Project 19580 Four Winds Way for review by Kylie Bagley on behalf of PCD Project Manager
|
4/8/2022 2:23:47 PM
|
Request for Review Comments returned by PCD Project Manager
|
4/8/2022 2:19:35 PM
|
Request for Review Comments email resent for Project 19580 Four Winds Way for review by Kylie Bagley on behalf of PCD Project Manager
|
4/8/2022 8:25:20 AM
|
Request for Review Comments returned by PCD Project Manager
|
4/7/2022 12:06:48 PM
|
Request for Review Comments returned by PCD Engineering Division
|
4/6/2022 11:19:29 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
4/1/2022 9:26:25 AM
|
Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
|
3/22/2022 3:14:04 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
3/21/2022 2:56:48 PM
|
Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
|
3/18/2022 3:58:26 PM
|
Request for Review Comments email sent for Project 19580 Four Winds Way for review by Administrator/Mgr on behalf of Woodmoor Improvement Association
|
3/18/2022 3:58:23 PM
|
Request for Review Comments email sent for Project 19580 Four Winds Way for review by Division Chief Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District
|
3/18/2022 3:58:21 PM
|
Request for Review Comments email sent for Project 19580 Four Winds Way for review by General Email on behalf of Mountain View Electric Association, Inc.
|
3/18/2022 3:58:19 PM
|
Request for Review Comments email sent for Project 19580 Four Winds Way for review by Joseph Martinez on behalf of US Army Corps of Engineers-Pueblo
|
3/18/2022 3:58:17 PM
|
Request for Review Comments email sent for Project 19580 Four Winds Way for review by CDOT Permits Manager Valerie Vigil on behalf of Colorado Department of Transportation - Pueblo Office
|
3/18/2022 3:58:09 PM
|
Request for Review Comments email sent for Project 19580 Four Winds Way for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
3/18/2022 3:58:01 PM
|
Request for Review Comments email sent for Project 19580 Four Winds Way for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
|
3/18/2022 3:57:58 PM
|
Request for Review Comments email sent for Project 19580 Four Winds Way for review by Kylie Bagley on behalf of PCD Project Manager
|
3/18/2022 3:57:56 PM
|
Request for Review Comments email sent for Project 19580 Four Winds Way for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
3/16/2022 2:11:38 PM
|
Fees paid: 3/16/2022 (Receipt: 1006016)
|
3/16/2022 9:21:48 AM
|
Payment Request sent: 3/16/2022
|
3/16/2022 9:21:48 AM
|
File # Assigned: CDR225
|
3/16/2022 9:21:43 AM
|
Submission Triaged
|
3/16/2022 5:48:32 AM
|
Submission received from Applicant
|
3/8/2022 8:09:56 AM
|
Submission request sent to Applicant
|
3/4/2022 10:28:09 AM
|
Project Manager Assigned: Kylie Bagley
|
3/4/2022 10:28:09 AM
|
Project Created
|