8/8/2023 11:50:28 AM
|
Project Closed
|
8/8/2023 11:50:28 AM
|
Project Approved: 8/8/2023
|
8/8/2023 11:50:15 AM
|
Project Ready for Approval requests. Review Comment period is complete.
|
8/8/2023 11:47:01 AM
|
Request for Review Comments returned by PCD Project Manager
|
8/7/2023 6:37:47 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
8/4/2023 12:46:13 PM
|
Request for Review Comments returned by EPC Health Department
|
8/3/2023 8:21:13 AM
|
Request for Review Comments returned by PCD Engineering Division
|
7/24/2023 3:12:40 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
7/24/2023 3:11:43 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Ashlyn Mathy on behalf of PCD Project Manager
|
7/24/2023 3:11:41 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
7/24/2023 3:11:11 PM
|
Submission Triaged
|
7/24/2023 2:19:07 PM
|
Submission received from Applicant
|
7/24/2023 9:58:37 AM
|
Submission request sent to Applicant
|
7/24/2023 9:44:10 AM
|
Submission Triaged
|
7/21/2023 5:57:45 PM
|
Submission received from Applicant
|
7/11/2023 8:11:25 AM
|
Submission request sent to Applicant
|
7/11/2023 8:11:02 AM
|
Request for Review Comments returned by PCD Project Manager
|
7/11/2023 8:08:16 AM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Ashlyn Mathy on behalf of PCD Project Manager
|
7/11/2023 8:07:23 AM
|
Submission request sent to Applicant
|
7/7/2023 10:16:11 AM
|
Submission request sent to Applicant
|
7/7/2023 10:15:24 AM
|
Request for Review Comments returned by PCD Project Manager
|
7/5/2023 2:20:22 PM
|
Request for Review Comments returned by PCD Engineering Division
|
7/5/2023 2:15:20 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
6/21/2023 8:45:01 AM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
6/21/2023 8:44:58 AM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Joshua Palmer on behalf of EPC Public Works, County Engineer
|
6/21/2023 8:44:57 AM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Catherine McGarvy on behalf of EPC Health Department
|
6/21/2023 8:44:48 AM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Ashlyn Mathy on behalf of PCD Project Manager
|
6/21/2023 8:44:42 AM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
6/21/2023 8:43:45 AM
|
Submission Triaged
|
6/20/2023 6:20:17 PM
|
Submission received from Applicant
|
6/14/2023 3:51:09 PM
|
Submission request sent to Applicant
|
6/14/2023 2:47:21 PM
|
Submission request sent to Applicant
|
5/1/2023 12:49:12 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
4/24/2023 2:19:26 PM
|
Submission request sent to Applicant
|
4/24/2023 2:11:00 PM
|
Request for Review Comments returned by PCD Project Manager
|
4/24/2023 9:26:52 AM
|
Request for Review Comments returned by PCD Engineering Division
|
4/20/2023 9:23:20 AM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
4/20/2023 8:40:57 AM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Ashlyn Mathy on behalf of PCD Project Manager
|
4/20/2023 8:40:55 AM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
4/19/2023 9:31:26 AM
|
Submission Triaged
|
4/18/2023 12:06:57 PM
|
Submission received from Applicant
|
4/18/2023 11:35:54 AM
|
Submission request sent to Applicant
|
4/7/2023 3:46:31 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
4/7/2023 3:46:28 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Ashlyn Mathy on behalf of PCD Project Manager
|
4/7/2023 3:46:26 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
4/7/2023 3:45:46 PM
|
Submission Triaged
|
4/7/2023 3:39:51 PM
|
Submission received from Applicant
|
1/23/2023 2:35:44 PM
|
Submission request sent to Applicant
|
1/23/2023 2:34:12 PM
|
Request for Review Comments returned by PCD Project Manager
|
1/22/2023 2:41:56 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
1/18/2023 4:26:33 PM
|
Request for Review Comments returned by PCD Engineering Division
|
12/28/2022 7:39:32 AM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
12/28/2022 7:39:30 AM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Ashlyn Mathy on behalf of PCD Project Manager
|
12/28/2022 7:39:28 AM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
12/28/2022 7:32:19 AM
|
Submission Triaged
|
12/27/2022 3:35:31 PM
|
Submission received from Applicant
|
11/9/2022 2:25:25 PM
|
Submission request sent to Applicant
|
11/9/2022 2:23:08 PM
|
Request for Review Comments returned by PCD Project Manager
|
11/9/2022 12:16:47 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
10/24/2022 3:36:12 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
10/24/2022 2:13:03 PM
|
Request for Review Comments returned by PCD Engineering Division
|
10/17/2022 10:37:56 AM
|
Project Manager Assigned: Ashlyn Mathy
|
10/3/2022 7:49:47 PM
|
Submission Triaged
|
10/3/2022 4:40:09 PM
|
Submission received from Applicant
|
10/3/2022 4:18:00 PM
|
Submission request sent to Applicant
|
10/3/2022 11:31:01 AM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Joshua Palmer on behalf of EPC Public Works, County Engineer
|
10/3/2022 11:31:00 AM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Catherine McGarvy on behalf of EPC Health Department
|
10/3/2022 11:30:57 AM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Matthew Fitzsimmons on behalf of PCD Project Manager
|
10/3/2022 11:30:55 AM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
10/3/2022 11:30:12 AM
|
Submission Triaged
|
9/30/2022 2:43:51 PM
|
Submission received from Applicant
|
7/29/2022 2:53:16 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
7/28/2022 3:30:07 PM
|
Submission request sent to Applicant
|
7/28/2022 3:22:01 PM
|
Request for Review Comments returned by PCD Project Manager
|
7/27/2022 4:20:06 PM
|
Request for Review Comments returned by PCD Engineering Division
|
7/27/2022 3:24:52 PM
|
Request for Review Comments returned by Cherokee Metro Dist
|
7/19/2022 2:17:08 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
7/19/2022 10:06:29 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
7/13/2022 3:06:57 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
7/13/2022 3:06:37 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Matthew Fitzsimmons on behalf of PCD Project Manager
|
7/13/2022 3:03:32 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Matthew Fitzsimmons on behalf of PCD Project Manager
|
7/13/2022 3:03:29 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
7/13/2022 2:20:49 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by General Email on behalf of Mountain View Electric Association, Inc.
|
7/13/2022 2:20:48 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Jeff Munger on behalf of Cherokee Metro Dist
|
7/13/2022 2:20:47 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
7/13/2022 2:20:46 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
7/13/2022 2:20:43 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
|
7/13/2022 2:20:41 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Catherine McGarvy on behalf of EPC Health Department
|
7/13/2022 2:20:39 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Matthew Fitzsimmons on behalf of PCD Project Manager
|
7/13/2022 2:20:37 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
7/13/2022 2:16:42 PM
|
Submission Triaged
|
7/12/2022 3:06:06 PM
|
Submission received from Applicant
|
6/14/2022 11:00:55 AM
|
Submission request sent to Applicant
|
6/14/2022 10:54:29 AM
|
Request for Review Comments returned by PCD Project Manager
|
6/8/2022 9:57:57 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
6/2/2022 7:31:54 PM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
6/2/2022 3:55:51 PM
|
Request for Review Comments returned by PCD Engineering Division
|
6/2/2022 10:55:24 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
6/1/2022 3:17:57 PM
|
Request for Review Comments returned by Cherokee Metro Dist
|
6/1/2022 10:27:50 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
6/1/2022 8:11:54 AM
|
Request for Review Comments returned by Colorado Springs Public Works
|
5/25/2022 3:26:52 PM
|
Request for Review Comments returned by Cimarron Hills Fire
|
5/17/2022 10:13:42 AM
|
Request for Review Comments returned by PCD Administrative Notice
|
5/16/2022 11:36:04 AM
|
Request for Review Comments returned by Colorado Springs Planning & Community Development
|
5/11/2022 2:42:50 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by General Email on behalf of Mountain View Electric Association, Inc.
|
5/11/2022 2:42:49 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by District Manager Mariah Hudson on behalf of El Paso County Conservation Dist
|
5/11/2022 2:42:48 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Records Management Lead LaShunda Simpson on behalf of Colorado Springs Public Works
|
5/11/2022 2:42:47 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Gabe Sevigny on behalf of Colorado Springs Planning & Community Development
|
5/11/2022 2:42:46 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Division Chief John McLeod on behalf of Cimarron Hills Fire
|
5/11/2022 2:42:45 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Jeff Munger on behalf of Cherokee Metro Dist
|
5/11/2022 2:42:44 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
5/11/2022 2:42:42 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
5/11/2022 2:42:39 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
|
5/11/2022 2:42:38 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Catherine McGarvy on behalf of EPC Health Department
|
5/11/2022 2:42:33 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Matthew Fitzsimmons on behalf of PCD Project Manager
|
5/11/2022 2:42:31 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
5/11/2022 2:42:30 PM
|
Request for Review Comments email sent for Project 6855 Constitution Ave Mini Warehouse Building Site Development Plan for review by on behalf of PCD Administrative Notice
|
5/10/2022 2:00:39 PM
|
Fees paid: 5/10/2022 (Receipt: 1006294)
|
5/2/2022 11:52:00 AM
|
Payment Request sent: 5/2/2022
|
5/2/2022 11:52:00 AM
|
File # Assigned: PPR2224
|
5/2/2022 11:51:55 AM
|
Submission Triaged
|
5/2/2022 8:58:26 AM
|
Submission received from Applicant
|
4/27/2022 8:41:45 PM
|
Project Manager Assigned: Matthew Fitzsimmons
|
4/27/2022 8:41:30 PM
|
Submission request sent to Applicant
|
4/27/2022 8:41:21 PM
|
Submission Triaged
|
4/26/2022 6:54:16 PM
|
Submission received from Applicant
|
4/21/2022 3:44:09 PM
|
Project Manager Assigned: Kylie Bagley
|
2/3/2022 4:50:21 PM
|
Submission request sent to Applicant
|
1/31/2022 1:19:23 PM
|
Project Manager Assigned: Kari Parsons
|
1/31/2022 1:19:23 PM
|
EA Assigned: EA228
|
1/31/2022 1:19:23 PM
|
Project Created
|