1/25/2022 3:09:18 PM
|
Project Closed
|
1/25/2022 3:09:18 PM
|
Project Approved: 1/25/2022
|
1/20/2022 3:50:23 PM
|
Request for Review Comments returned by PCD Project Manager
|
1/13/2022 4:45:30 PM
|
Request for Review Comments email sent for Project 5925 Coyote Lane ADM for review by Nina Ruiz on behalf of PCD Project Manager
|
1/13/2022 4:44:44 PM
|
Submission Triaged
|
1/13/2022 3:15:56 PM
|
Submission received from Applicant
|
1/13/2022 3:08:16 PM
|
Submission request sent to Applicant
|
1/13/2022 11:10:49 AM
|
Submission request sent to Applicant
|
1/12/2022 8:29:30 AM
|
Request for Review Comments returned by PCD Project Manager
|
1/5/2022 4:42:04 PM
|
Request for Review Comments email resent for Project 5925 Coyote Lane ADM for review by Nina Ruiz on behalf of PCD Project Manager
|
12/27/2021 11:49:12 AM
|
Request for Review Comments returned by PCD Project Manager
|
12/22/2021 12:26:52 PM
|
Request for Review Comments email sent for Project 5925 Coyote Lane ADM for review by Nina Ruiz on behalf of PCD Project Manager
|
12/21/2021 11:50:05 AM
|
Fees paid: 12/21/2021 (Receipt: 1005548)
|
12/19/2021 8:01:18 AM
|
Payment Request sent: 12/19/2021
|
12/19/2021 8:01:18 AM
|
File # Assigned: ADM2177
|
12/19/2021 8:01:13 AM
|
Submission Triaged
|
12/17/2021 4:25:32 PM
|
Submission received from Applicant
|
12/17/2021 3:29:16 PM
|
Submission request sent to Applicant
|
12/17/2021 3:27:34 PM
|
Project Manager Assigned: John Green
|
12/17/2021 3:27:34 PM
|
Project Created
|