Project Details

Search


File Number
PPR2214
Project Name
3745 Mulberry Rd Site Development Plan
Description
Proposing 5 new structures per VA213
Parcels
1300000469 1300000469
Applicant
Mulbeery Ridge LLC
Jennifer Zezlina ( jzezlina@rmg-engineers.com ) Jennifer Zezlina ( jzezlina@rmg-engineers.com )
File Prefix
PPR - Plot Plan Review
Year
2022
Project Manager
Ryan Howser
Status
Closed
Created
11/15/2021 10:52:33 AM

View: Review Comments


Approved Documents (1)

Link Document
View Site Development Plan


Review Documents (11)

Link Document Date
View Application/Petition Form 3/21/2022 2:59:22 PM
View Legal Description (MS WORD Version required) 3/11/2022 12:14:56 PM
View Letter of Intent 4/22/2022 10:05:45 AM
View Title Commitment (Current within 30 days of submittal) 3/18/2022 9:26:35 AM
View Vicinity/Location Map 3/11/2022 12:14:56 PM
View Floor Plans (24" x 36") 3/11/2022 2:56:33 PM
View PBMP Applicability Form 3/21/2022 5:48:48 PM
View Landscape Plan drawings 4/22/2022 10:05:44 AM
View Lighting Plan 3/21/2022 2:59:23 PM
View Site Development Plan 4/22/2022 10:05:45 AM
View Elevation Plans 3/11/2022 2:56:33 PM



Events (51)

Date Comment
8/2/2022 4:31:04 PM Project Closed
8/2/2022 4:31:04 PM Project Approved: 8/2/2022
8/2/2022 3:11:29 PM Request for Review Comments returned by EPC Code Enforcement Inspections
7/29/2022 2:47:07 PM Request for Review Comments email sent for Project 3745 Mulberry Rd Site Development Plan for review by Joe Letke on behalf of EPC Code Enforcement Inspections
7/29/2022 2:46:25 PM Project reopened for Review Comments
6/2/2022 8:27:31 AM Project Closed
6/2/2022 8:27:31 AM Project Approved: 6/2/2022
5/18/2022 3:54:09 PM Project Ready for Approval requests. Review Comment period is complete.
5/18/2022 3:50:01 PM Request for Review Comments returned by PCD Project Manager
5/9/2022 8:13:54 AM Request for Review Comments returned by Pikes Peak Regional Building Department
4/27/2022 7:54:08 AM Request for Review Comments email sent for Project 3745 Mulberry Rd Site Development Plan for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
4/27/2022 7:54:07 AM Request for Review Comments email sent for Project 3745 Mulberry Rd Site Development Plan for review by Ryan Howser on behalf of PCD Project Manager
4/27/2022 7:53:18 AM Submission Triaged
4/22/2022 10:06:05 AM Submission received from Applicant
4/14/2022 1:28:28 PM Submission request sent to Applicant
4/14/2022 1:27:27 PM Request for Review Comments returned by PCD Project Manager
4/14/2022 1:09:04 PM Request for Review Comments returned by EPC Stormwater Review
4/14/2022 11:25:58 AM Request for Review Comments returned by Mountain View Electric Association, Inc.
4/13/2022 10:38:52 AM Request for Review Comments returned by Pikes Peak Regional Building Department
4/11/2022 8:48:14 AM Request for Review Comments returned by PCD Engineering Division
4/8/2022 8:56:33 AM Project Manager Assigned: Ryan Howser
4/7/2022 1:54:40 PM Request for Review Comments returned by County Attorney - Development Review
3/30/2022 11:34:25 AM Request for Review Comments returned by EPC Environmental Services
3/29/2022 8:19:55 AM Request for Review Comments returned by 911 Authority - El Paso/Teller County
3/23/2022 1:38:39 PM Request for Review Comments email sent for Project 3745 Mulberry Rd Site Development Plan for review by Mark Stanwood on behalf of Tri-County Fire Protection District
3/23/2022 1:38:38 PM Request for Review Comments email sent for Project 3745 Mulberry Rd Site Development Plan for review by General Email on behalf of Mountain View Electric Association, Inc.
3/23/2022 1:38:37 PM Request for Review Comments email sent for Project 3745 Mulberry Rd Site Development Plan for review by Dwight Barnes on behalf of Miami Yoder 60 JT
3/23/2022 1:38:36 PM Request for Review Comments email sent for Project 3745 Mulberry Rd Site Development Plan for review by District Manager on behalf of Double El Conservation Dist northeast EPC
3/23/2022 1:38:35 PM Request for Review Comments email sent for Project 3745 Mulberry Rd Site Development Plan for review by Joe Valdez on behalf of Black Hills Energy-Aquila
3/23/2022 1:38:28 PM Request for Review Comments email sent for Project 3745 Mulberry Rd Site Development Plan for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
3/23/2022 1:38:27 PM Request for Review Comments email sent for Project 3745 Mulberry Rd Site Development Plan for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
3/23/2022 1:38:26 PM Request for Review Comments email sent for Project 3745 Mulberry Rd Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
3/23/2022 1:38:22 PM Request for Review Comments email sent for Project 3745 Mulberry Rd Site Development Plan for review by Catherine McGarvy on behalf of EPC Health Department
3/23/2022 1:38:18 PM Request for Review Comments email sent for Project 3745 Mulberry Rd Site Development Plan for review by Kathy Andrew on behalf of EPC Environmental Services
3/23/2022 1:38:17 PM Request for Review Comments email sent for Project 3745 Mulberry Rd Site Development Plan for review by Lori Seago on behalf of County Attorney - Development Review
3/23/2022 1:38:16 PM Request for Review Comments email sent for Project 3745 Mulberry Rd Site Development Plan for review by John Green on behalf of PCD Project Manager
3/23/2022 1:38:15 PM Request for Review Comments email sent for Project 3745 Mulberry Rd Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
3/22/2022 5:48:17 PM Fees paid: 3/22/2022 (Receipt: 1006041)
3/21/2022 9:06:09 PM Payment Request sent: 3/21/2022
3/21/2022 9:06:09 PM File # Assigned: PPR2214
3/21/2022 9:06:01 PM Submission Triaged
3/21/2022 9:03:11 PM Project Manager Assigned: John Green
3/21/2022 8:49:14 PM Submission received from Applicant
1/11/2022 10:50:54 AM Submission request sent to Applicant
1/11/2022 10:50:43 AM Submission request canceled
1/11/2022 10:33:56 AM Submission request sent to Applicant
1/11/2022 10:33:40 AM Submission request canceled
1/5/2022 9:17:42 AM Submission request sent to Applicant
1/5/2022 9:17:31 AM Submission request canceled
11/15/2021 1:56:46 PM Submission request sent to Applicant
11/15/2021 10:52:50 AM Project Created