11/30/2021 3:59:57 PM
|
Project Closed
|
11/30/2021 3:59:57 PM
|
Project Approved: 11/30/2021
|
11/30/2021 3:59:00 PM
|
Request for Review Comments returned by PCD Project Manager
|
11/29/2021 10:09:46 AM
|
Request for Review Comments returned by PCD Engineering Division
|
11/23/2021 10:20:57 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
11/19/2021 9:31:29 AM
|
Request for Review Comments returned by Black Forest Fire Protection District
|
11/16/2021 2:14:51 PM
|
Request for Review Comments email sent for Project MVEA --- Vollmer South Construction Drawings for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
11/16/2021 2:14:47 PM
|
Request for Review Comments email sent for Project MVEA --- Vollmer South Construction Drawings for review by Ryan Howser on behalf of PCD Project Manager
|
11/16/2021 2:14:41 PM
|
Request for Review Comments email sent for Project MVEA --- Vollmer South Construction Drawings for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
11/16/2021 2:13:59 PM
|
Submission Triaged
|
11/15/2021 2:09:50 PM
|
Submission received from Applicant
|
11/12/2021 3:22:27 PM
|
Submission request sent to Applicant
|
11/12/2021 3:21:15 PM
|
Request for Review Comments returned by PCD Project Manager
|
11/10/2021 5:12:12 PM
|
Request for Review Comments returned by PCD Engineering Division
|
11/10/2021 11:50:50 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
11/9/2021 10:51:35 AM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
11/1/2021 11:49:08 AM
|
Request for Review Comments returned by Black Forest Land Use Committee
|
11/1/2021 7:43:17 AM
|
Request for Review Comments returned by Academy SD 20 Building Fund
|
10/28/2021 1:02:01 PM
|
Request for Review Comments email sent for Project MVEA --- Vollmer South Construction Drawings for review by Tabitha Barile on behalf of Sterling Ranch Metropolitan District 1-3
|
10/28/2021 1:01:59 PM
|
Request for Review Comments email sent for Project MVEA --- Vollmer South Construction Drawings for review by District Manager Pamela Davison on behalf of El Paso County Conservation Dist
|
10/28/2021 1:01:56 PM
|
Request for Review Comments email sent for Project MVEA --- Vollmer South Construction Drawings for review by Cheryl Pixley on behalf of Black Forest Trails Association
|
10/28/2021 1:01:54 PM
|
Request for Review Comments email sent for Project MVEA --- Vollmer South Construction Drawings for review by Terry Stokka on behalf of Black Forest Land Use Committee
|
10/28/2021 1:01:52 PM
|
Request for Review Comments email sent for Project MVEA --- Vollmer South Construction Drawings for review by Deputy Chief James Rebitski on behalf of Black Forest Fire Protection District
|
10/28/2021 1:01:50 PM
|
Request for Review Comments email sent for Project MVEA --- Vollmer South Construction Drawings for review by Plannig Consultant Donald Smith on behalf of Academy SD 20 Building Fund
|
10/28/2021 1:01:48 PM
|
Request for Review Comments email sent for Project MVEA --- Vollmer South Construction Drawings for review by Joseph Martinez on behalf of US Army Corps of Engineers-Pueblo
|
10/28/2021 1:01:46 PM
|
Request for Review Comments email sent for Project MVEA --- Vollmer South Construction Drawings for review by CDOT Permits Manager Valerie Vigil on behalf of Colorado Department of Transportation - Pueblo Office
|
10/28/2021 1:01:38 PM
|
Request for Review Comments email sent for Project MVEA --- Vollmer South Construction Drawings for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
10/28/2021 1:01:32 PM
|
Request for Review Comments email sent for Project MVEA --- Vollmer South Construction Drawings for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
|
10/28/2021 1:01:29 PM
|
Request for Review Comments email sent for Project MVEA --- Vollmer South Construction Drawings for review by Ryan Howser on behalf of PCD Project Manager
|
10/28/2021 1:01:27 PM
|
Request for Review Comments email sent for Project MVEA --- Vollmer South Construction Drawings for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
10/28/2021 10:58:14 AM
|
Fees paid: 10/28/2021 (Receipt: 1005323)
|
10/18/2021 4:46:39 PM
|
Payment Request sent: 10/18/2021
|
10/18/2021 4:46:38 PM
|
File # Assigned: CDR2116
|
10/18/2021 4:46:29 PM
|
Submission Triaged
|
10/18/2021 9:16:09 AM
|
Submission received from Applicant
|
10/5/2021 11:17:26 AM
|
Submission request sent to Applicant
|
10/5/2021 11:16:59 AM
|
Project Manager Assigned: Ryan Howser
|
10/5/2021 11:16:59 AM
|
Project Created
|