10/28/2024 5:15:08 PM
|
Project Closed
|
10/28/2024 5:15:08 PM
|
Project completed: 10/28/2024
|
9/24/2024 7:10:37 AM
|
Project Manager Assigned: Dominic Lira
|
6/6/2024 3:41:44 PM
|
Notice of Violation sent
|
5/15/2024 12:36:32 PM
|
Executive Determination Requested
|
5/15/2024 12:31:21 PM
|
Executive Determination Requested
|
4/4/2024 1:03:22 PM
|
Notice of Violation sent
|
4/4/2024 12:47:59 PM
|
Notice of Violation sent
|
4/4/2024 12:43:09 PM
|
Notice of Violation sent
|
2/21/2024 11:05:20 AM
|
Project Manager Assigned: Scott Shevock
|
10/4/2021 7:55:42 AM
|
Litigation Pending
|
9/13/2021 1:26:20 PM
|
Executive Determination Issued
|
8/25/2021 1:57:36 PM
|
Executive Determination Requested
|
7/25/2021 6:24:24 PM
|
Supervisor Letter Issued
|
6/17/2021 8:47:51 AM
|
Notice of Violation sent
|
6/13/2021 8:31:06 AM
|
No Fees
|
6/13/2021 8:31:06 AM
|
File # Assigned: CE21499
|
6/13/2021 8:31:06 AM
|
Project Manager Assigned: Scott Shevock
|
6/13/2021 8:31:06 AM
|
Project Created
|
6/13/2021 8:31:03 AM
|
Application Triaged/Accepted
|
6/13/2021 8:31:01 AM
|
Application submitted
|