Project Details

Search


File Number
SF2143
Project Name
Rollin Ridge Pond B access from Hodgen Rd. driveway
Description
Modifying Plat Note 16
Applicant
Donald Smith
Dave Jones ( chipita1@comcast.net ) Dave Jones ( chipita1@comcast.net )
File Prefix
SF - Final Plat
Year
2021
Project Manager
Remove Ashlyn Mathy
Status
Closed
Created
6/1/2021 3:33:35 PM

View: Review Comments


Approved Documents (1)

Link Document
View Construction Drawings (Plans/Profiles)


Additional Documents (4)

Link Document Comment
View Zero Tax Certification
View Title Commitment (Lot 2)
View Title Commitment (Lot 3)
View Final Plat Amendment NO.1 14968


Review Documents (9)

Link Document Date
View Adjacent Property Owner Notification (Includes letter and certified mailing receipts) 11/19/2021 2:26:54 PM
View Application/Petition Form 11/19/2021 2:26:55 PM
View Legal Description (MS WORD Version required) 11/19/2021 2:26:57 PM
View Letter of Intent 11/19/2021 2:26:58 PM
View Title Commitment (Current within 30 days of submittal) 11/19/2021 2:26:58 PM
View Vicinity/Location Map 11/19/2021 2:26:59 PM
View Construction Drawings (Plans/Profiles) 4/26/2022 1:15:32 PM
View Final Plat Drawings 3/11/2022 10:35:00 AM
View Fire Commitment Letter 11/23/2021 11:38:34 AM



Events (44)

Date Comment
6/2/2022 1:43:02 PM Submission request sent to Applicant
5/19/2022 10:21:54 AM Project Closed
5/19/2022 10:21:54 AM Project Approved: 5/19/2022
5/19/2022 10:21:42 AM Project Ready for Approval requests. Review Comment period is complete.
5/19/2022 10:21:25 AM Request for Review Comments returned by PCD Project Manager
5/11/2022 8:56:09 AM Request for Review Comments returned by PCD Engineering Division
5/9/2022 5:02:10 PM Request for Review Comments email sent for Project Rollin Ridge Pond B access from Hodgen Rd. driveway for review by Ashlyn Mathy on behalf of PCD Project Manager
5/9/2022 5:02:08 PM Request for Review Comments email sent for Project Rollin Ridge Pond B access from Hodgen Rd. driveway for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
5/9/2022 5:01:38 PM Project Manager Assigned: Ashlyn Mathy
5/9/2022 5:01:15 PM Submission Triaged
4/26/2022 1:15:48 PM Submission received from Applicant
4/12/2022 10:29:05 AM Project Manager Assigned: Nina Ruiz
4/5/2022 8:11:38 AM Submission request sent to Applicant
4/5/2022 8:11:09 AM Request for Review Comments returned by PCD Project Manager
4/5/2022 8:08:17 AM Request for Review Comments email resent for Project Rollin Ridge Pond B access from Hodgen Rd. driveway for review by John Green on behalf of PCD Project Manager
4/5/2022 8:06:37 AM Request for Review Comments returned by PCD Project Manager
3/30/2022 4:13:08 PM Request for Review Comments returned by PCD Engineering Division
3/11/2022 3:01:38 PM Request for Review Comments email sent for Project Rollin Ridge Pond B access from Hodgen Rd. driveway for review by John Green on behalf of PCD Project Manager
3/11/2022 3:01:34 PM Request for Review Comments email sent for Project Rollin Ridge Pond B access from Hodgen Rd. driveway for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
3/11/2022 3:00:59 PM Submission Triaged
3/11/2022 10:35:10 AM Submission received from Applicant
1/12/2022 8:57:37 AM Submission request sent to Applicant
1/12/2022 8:57:17 AM Request for Review Comments returned by PCD Project Manager
1/12/2022 8:50:05 AM Request for Review Comments email resent for Project Rollin Ridge Pond B access from Hodgen Rd. driveway for review by John Green on behalf of PCD Project Manager
1/12/2022 8:49:11 AM Request for Review Comments returned by PCD Project Manager
1/12/2022 8:48:36 AM Request for Review Comments email resent for Project Rollin Ridge Pond B access from Hodgen Rd. driveway for review by John Green on behalf of PCD Project Manager
1/12/2022 8:09:18 AM Request for Review Comments returned by PCD Project Manager
1/3/2022 1:42:22 PM Request for Review Comments returned by PCD Engineering Division
12/29/2021 3:51:48 PM Request for Review Comments returned by Pikes Peak Regional Building Department
12/9/2021 10:03:58 AM Request for Review Comments returned by County Attorney - Water
12/9/2021 7:47:17 AM Request for Review Comments email sent for Project Rollin Ridge Pond B access from Hodgen Rd. driveway for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
12/9/2021 7:47:15 AM Request for Review Comments email sent for Project Rollin Ridge Pond B access from Hodgen Rd. driveway for review by Edi Anderson on behalf of County Attorney - Water
12/9/2021 7:47:13 AM Request for Review Comments email sent for Project Rollin Ridge Pond B access from Hodgen Rd. driveway for review by John Green on behalf of PCD Project Manager
12/9/2021 7:47:10 AM Request for Review Comments email sent for Project Rollin Ridge Pond B access from Hodgen Rd. driveway for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
12/2/2021 12:22:32 PM Fees paid: 12/2/2021 (Receipt: 1005456)
11/25/2021 8:17:15 PM Payment Request sent: 11/25/2021
11/25/2021 8:17:15 PM File # Assigned: SF2143
11/25/2021 8:17:06 PM Submission Triaged
11/25/2021 8:15:25 PM Project Manager Assigned: John Green
11/23/2021 11:39:05 AM Submission received from Applicant
6/14/2021 4:52:38 PM Submission request sent to Applicant
6/1/2021 3:36:02 PM Submission request sent to Applicant
6/1/2021 3:33:58 PM Project Manager Assigned: Nina Ruiz
6/1/2021 3:33:58 PM Project Created