6/28/2023 12:47:28 PM
|
Project Closed
|
6/28/2023 12:47:28 PM
|
Project Cancelled: 6/28/2023
|
6/3/2021 6:19:36 PM
|
Request for Review Comments returned by PCD Engineering Division
|
6/3/2021 12:28:33 PM
|
Request for Review Comments returned by PCD Project Manager
|
5/20/2021 2:32:42 PM
|
Request for Review Comments email sent for Project Woodmen East Commercial Center No. 1 Annexation for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
|
5/20/2021 2:32:40 PM
|
Request for Review Comments email sent for Project Woodmen East Commercial Center No. 1 Annexation for review by Ryan Howser on behalf of PCD Project Manager
|
5/20/2021 2:32:38 PM
|
Request for Review Comments email sent for Project Woodmen East Commercial Center No. 1 Annexation for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
5/20/2021 1:48:58 PM
|
No Fees
|
5/20/2021 1:48:58 PM
|
File # Assigned: ANX214
|
5/20/2021 1:48:57 PM
|
Project Manager Assigned: Ryan Howser
|
5/20/2021 1:48:57 PM
|
Project Created
|