4/14/2021 5:34:50 PM
|
Project Closed
|
4/14/2021 5:34:50 PM
|
Project Approved: 4/14/2021
|
4/14/2021 7:53:41 AM
|
Request for Review Comments returned by PCD Project Manager
|
4/13/2021 5:59:29 PM
|
Request for Review Comments returned by PCD Engineering Division
|
4/7/2021 10:32:34 AM
|
Request for Review Comments email sent for Project Peak Technology Campus OAR for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
|
4/7/2021 10:32:32 AM
|
Request for Review Comments email sent for Project Peak Technology Campus OAR for review by John Green on behalf of PCD Project Manager
|
4/7/2021 10:32:28 AM
|
Request for Review Comments email sent for Project Peak Technology Campus OAR for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
4/7/2021 10:29:49 AM
|
Project reopened for Review Comments
|
2/2/2021 10:55:13 AM
|
Project Closed
|
2/2/2021 10:55:13 AM
|
Project Approved: 2/2/2021
|
1/12/2021 10:48:01 AM
|
Request for Review Comments returned by PCD Project Manager
|
1/10/2021 9:45:16 PM
|
Request for Review Comments returned by PCD Engineering Division
|
1/4/2021 7:41:51 AM
|
Request for Review Comments email sent for Project Peak Technology Campus OAR for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
|
1/4/2021 7:41:49 AM
|
Request for Review Comments email sent for Project Peak Technology Campus OAR for review by John Green on behalf of PCD Project Manager
|
1/4/2021 7:41:47 AM
|
Request for Review Comments email sent for Project Peak Technology Campus OAR for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
1/4/2021 7:38:34 AM
|
No Fees
|
1/4/2021 7:38:34 AM
|
File # Assigned: OAR212
|
1/4/2021 7:38:33 AM
|
Project Manager Assigned: John Green
|
1/4/2021 7:38:33 AM
|
Project Created
|