3/26/2025 9:21:00 AM
|
Project Closed
|
3/26/2025 9:21:00 AM
|
Project Cancelled: 3/26/2025
|
4/19/2023 7:50:52 AM
|
Submission request sent to Applicant
|
4/18/2023 11:33:04 AM
|
Project reopened for Review Comments
|
3/22/2023 3:01:27 PM
|
Project Closed
|
3/22/2023 3:01:27 PM
|
Project Cancelled: 3/22/2023
|
2/4/2022 7:43:39 PM
|
Request for Review Comments returned by EPC Health Department
|
2/1/2022 11:22:46 AM
|
Request for Review Comments returned by County Attorney - Development Review
|
1/13/2022 8:31:24 AM
|
Submission request sent to Applicant
|
1/13/2022 8:00:16 AM
|
Request for Review Comments returned by PCD Project Manager
|
1/12/2022 4:59:32 PM
|
Request for Review Comments returned by PCD Engineering Division
|
1/12/2022 10:34:19 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
1/11/2022 4:21:13 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
1/11/2022 7:31:21 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
12/30/2021 12:16:32 PM
|
Request for Review Comments returned by Falcon Fire Protection District
|
12/21/2021 4:32:47 PM
|
Request for Review Comments email sent for Project Falcon Big R Store Expansion for review by Administrative Assistant Cathy Hansen-Lee on behalf of Mountain View Electric Association, Inc.
|
12/21/2021 4:32:37 PM
|
Request for Review Comments email sent for Project Falcon Big R Store Expansion for review by Fire Chief Trent Harwig on behalf of Falcon Fire Protection District
|
12/21/2021 4:32:35 PM
|
Request for Review Comments email sent for Project Falcon Big R Store Expansion for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
12/21/2021 4:32:33 PM
|
Request for Review Comments email sent for Project Falcon Big R Store Expansion for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
12/21/2021 4:32:29 PM
|
Request for Review Comments email sent for Project Falcon Big R Store Expansion for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
|
12/21/2021 4:32:27 PM
|
Request for Review Comments email sent for Project Falcon Big R Store Expansion for review by Catherine McGarvy on behalf of EPC Health Department
|
12/21/2021 4:32:19 PM
|
Request for Review Comments email sent for Project Falcon Big R Store Expansion for review by Lori Seago on behalf of County Attorney - Development Review
|
12/21/2021 4:32:17 PM
|
Request for Review Comments email sent for Project Falcon Big R Store Expansion for review by Kylie Bagley on behalf of PCD Project Manager
|
12/21/2021 4:32:15 PM
|
Request for Review Comments email sent for Project Falcon Big R Store Expansion for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
12/21/2021 8:15:40 AM
|
Fees paid: 12/21/2021 (Receipt: 1005546)
|
12/19/2021 7:56:37 AM
|
Project Manager Assigned: Kylie Bagley
|
12/19/2021 7:56:14 AM
|
Payment Request sent: 12/19/2021
|
12/19/2021 7:56:13 AM
|
File # Assigned: PPR2176
|
12/19/2021 7:56:04 AM
|
Submission Triaged
|
12/17/2021 9:21:43 AM
|
Submission received from Applicant
|
9/28/2021 8:22:35 AM
|
Submission request sent to Applicant
|
1/6/2021 12:27:27 PM
|
Submission request sent to Applicant
|
12/29/2020 5:09:43 PM
|
Project Manager Assigned: John Green
|
12/29/2020 5:09:43 PM
|
Project Created
|