10/11/2021 3:11:55 PM
|
Project Closed
|
10/11/2021 3:11:55 PM
|
Project Approved: 10/11/2021
|
8/5/2021 7:00:10 AM
|
Request for Review Comments returned by PCD Project Manager
|
8/5/2021 6:59:18 AM
|
Request for Review Comments email resent for Project Seclusion Rezone for review by Mercedes Rivas on behalf of PCD Project Manager
|
8/4/2021 5:12:12 PM
|
Request for Review Comments returned by PCD Project Manager
|
7/29/2021 3:05:49 PM
|
Request for Review Comments returned by PCD Engineering Division
|
7/29/2021 2:57:24 PM
|
Request for Review Comments email sent for Project Seclusion Rezone for review by Mercedes Rivas on behalf of PCD Project Manager
|
7/29/2021 2:57:19 PM
|
Request for Review Comments email sent for Project Seclusion Rezone for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
7/29/2021 2:56:47 PM
|
Submission Triaged
|
7/29/2021 2:33:08 PM
|
Submission received from Applicant
|
7/29/2021 2:13:31 PM
|
Submission request sent to Applicant
|
7/29/2021 2:12:40 PM
|
Request for Review Comments returned by PCD Project Manager
|
7/29/2021 2:12:04 PM
|
Request for Review Comments email resent for Project Seclusion Rezone for review by Mercedes Rivas on behalf of PCD Project Manager
|
7/27/2021 3:08:45 PM
|
Submission request sent to Applicant
|
7/27/2021 3:07:33 PM
|
Request for Review Comments returned by PCD Project Manager
|
7/27/2021 12:54:42 PM
|
Request for Review Comments returned by PCD Engineering Division
|
7/7/2021 7:28:31 AM
|
Request for Review Comments email sent for Project Seclusion Rezone for review by Mercedes Rivas on behalf of PCD Project Manager
|
7/7/2021 7:28:25 AM
|
Request for Review Comments email sent for Project Seclusion Rezone for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
7/7/2021 7:26:50 AM
|
Submission Triaged
|
7/2/2021 3:39:13 PM
|
Submission received from Applicant
|
7/1/2021 8:23:43 AM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
6/30/2021 12:53:43 PM
|
Request for Review Comments email sent for Project Seclusion Rezone for review by Melissa Andrews on behalf of Falcon School District 49
|
6/30/2021 12:53:41 PM
|
Request for Review Comments email sent for Project Seclusion Rezone for review by Fire Chief Trent Harwig on behalf of Falcon Fire Protection District
|
6/22/2021 9:20:07 AM
|
Submission request sent to Applicant
|
6/22/2021 9:19:04 AM
|
Request for Review Comments returned by PCD Project Manager
|
6/21/2021 11:52:10 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
6/17/2021 8:25:57 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
6/16/2021 9:16:14 AM
|
Request for Review Comments returned by PCD Engineering Division
|
6/15/2021 10:08:45 AM
|
Request for Review Comments returned by Black Forest Fire Protection District
|
6/4/2021 7:13:09 AM
|
Request for Review Comments returned by Academy SD 20 Building Fund
|
6/2/2021 1:17:01 PM
|
Request for Review Comments returned by Upper Black Squirrel Creek GWMD
|
6/2/2021 10:55:24 AM
|
Request for Review Comments returned by EPC Environmental Services
|
6/1/2021 5:11:57 PM
|
Request for Review Comments email sent for Project Seclusion Rezone for review by General Email on behalf of Mountain View Electric Association, Inc.
|
6/1/2021 5:11:55 PM
|
Request for Review Comments email sent for Project Seclusion Rezone for review by District Manager Pamela Davison on behalf of El Paso County Conservation Dist
|
6/1/2021 5:11:53 PM
|
Request for Review Comments email sent for Project Seclusion Rezone for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
6/1/2021 5:11:49 PM
|
Request for Review Comments email sent for Project Seclusion Rezone for review by Terry Stokka on behalf of Black Forest Land Use Committee
|
6/1/2021 5:11:47 PM
|
Request for Review Comments email sent for Project Seclusion Rezone for review by Deputy Chief James Rebitski on behalf of Black Forest Fire Protection District
|
6/1/2021 5:11:45 PM
|
Request for Review Comments email sent for Project Seclusion Rezone for review by Plannig Consultant Donald Smith on behalf of Academy SD 20 Building Fund
|
6/1/2021 5:11:43 PM
|
Request for Review Comments email sent for Project Seclusion Rezone for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
|
6/1/2021 5:11:41 PM
|
Request for Review Comments email sent for Project Seclusion Rezone for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
6/1/2021 5:11:39 PM
|
Request for Review Comments email sent for Project Seclusion Rezone for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
|
6/1/2021 5:11:37 PM
|
Request for Review Comments email sent for Project Seclusion Rezone for review by Catherine McGarvy on behalf of EPC Health Department
|
6/1/2021 5:11:23 PM
|
Request for Review Comments email sent for Project Seclusion Rezone for review by Kathy Andrew on behalf of EPC Environmental Services
|
6/1/2021 5:11:20 PM
|
Request for Review Comments email sent for Project Seclusion Rezone for review by Mercedes Rivas on behalf of PCD Project Manager
|
6/1/2021 5:11:18 PM
|
Request for Review Comments email sent for Project Seclusion Rezone for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
6/1/2021 8:06:21 AM
|
Fees paid: 6/1/2021 (Receipt: 1004483)
|
5/20/2021 2:11:12 PM
|
Payment Request sent: 5/20/2021
|
5/20/2021 2:11:12 PM
|
File # Assigned: P213
|
5/20/2021 2:10:48 PM
|
Submission Triaged
|
5/20/2021 2:09:02 PM
|
Project Manager Assigned: Mercedes Rivas
|
5/19/2021 4:27:27 PM
|
Submission received from Applicant
|
12/16/2020 4:50:59 PM
|
Submission request sent to Applicant
|
12/14/2020 4:11:12 PM
|
Project Manager Assigned: John Green
|
12/14/2020 4:11:12 PM
|
Project Created
|