9/7/2021 1:11:17 PM
|
Project Manager Assigned: Mercedes Rivas
|
6/10/2021 9:40:20 AM
|
Project Closed
|
6/10/2021 9:40:20 AM
|
Project Approved: 6/10/2021
|
3/4/2021 3:40:49 PM
|
Project reopened for Review Comments
|
1/26/2021 2:19:52 PM
|
Project Closed
|
1/26/2021 2:19:52 PM
|
Project Approved: 1/26/2021
|
1/25/2021 4:51:45 PM
|
Request for Review Comments returned by PCD Engineering Division
|
1/25/2021 11:42:22 AM
|
Request for Review Comments returned by PCD Project Manager
|
1/21/2021 8:51:00 AM
|
Request for Review Comments email sent for Project Reagan Ranch PUD for review by Sophie Kiepe on behalf of PCD Project Manager
|
1/21/2021 8:50:56 AM
|
Request for Review Comments email sent for Project Reagan Ranch PUD for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
1/21/2021 8:48:29 AM
|
Request for Review Comments email sent for Project Reagan Ranch PUD for review by Sophie Kiepe on behalf of PCD Project Manager
|
1/21/2021 8:46:47 AM
|
Request for Review Comments email sent for Project Reagan Ranch PUD for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
12/29/2020 11:46:42 AM
|
Request for Review Comments returned by PCD Project Manager
|
12/29/2020 11:30:15 AM
|
Request for Review Comments returned by PCD Engineering Division
|
12/21/2020 4:34:45 PM
|
Request for Review Comments email sent for Project Reagan Ranch PUD for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
|
12/21/2020 4:34:13 PM
|
Request for Review Comments email sent for Project Reagan Ranch PUD for review by Sophie Kiepe on behalf of PCD Project Manager
|
12/21/2020 4:34:09 PM
|
Request for Review Comments email sent for Project Reagan Ranch PUD for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
12/21/2020 4:29:05 PM
|
Project reopened for Review Comments
|
12/18/2020 10:05:37 AM
|
Project Closed
|
12/18/2020 10:05:37 AM
|
Project Approved: 12/18/2020
|
12/9/2020 2:10:34 PM
|
Request for Review Comments returned by PCD Engineering Division
|
12/8/2020 11:04:35 AM
|
Request for Review Comments returned by PCD Project Manager
|
12/7/2020 4:12:40 PM
|
Project reopened for Review Comments
|
12/1/2020 4:29:57 PM
|
Request for Review Comments email sent for Project Reagan Ranch PUD for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
|
12/1/2020 4:29:55 PM
|
Request for Review Comments email sent for Project Reagan Ranch PUD for review by Sophie Kiepe on behalf of PCD Project Manager
|
12/1/2020 4:29:51 PM
|
Request for Review Comments email sent for Project Reagan Ranch PUD for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
10/21/2020 10:38:15 AM
|
Project Closed
|
10/21/2020 10:38:15 AM
|
Project Approved: 10/21/2020
|
10/21/2020 10:36:31 AM
|
Project Ready for Approval requests. Review Comment period is complete.
|
10/13/2020 2:21:17 PM
|
Request for Review Comments returned by PCD Project Manager
|
10/13/2020 8:31:25 AM
|
Request for Review Comments returned by PCD Engineering Division
|
10/1/2020 8:51:30 AM
|
Request for Review Comments email sent for Project Reagan Ranch PUD for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
|
10/1/2020 8:51:28 AM
|
Request for Review Comments email sent for Project Reagan Ranch PUD for review by Sophie Kiepe on behalf of PCD Project Manager
|
10/1/2020 8:51:26 AM
|
Request for Review Comments email sent for Project Reagan Ranch PUD for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
10/1/2020 8:20:18 AM
|
No Fees
|
10/1/2020 8:20:18 AM
|
File # Assigned: OAR2054
|
10/1/2020 8:20:18 AM
|
Project Manager Assigned: Sophie Kiepe
|
10/1/2020 8:20:18 AM
|
Project Created
|